TeraWulf is a bitcoin miner turning into a data-centre landlord
New York and Kentucky
where its campuses and grid connections are
Whole buildings
each rented to one tenant
Ten to twenty years
the length of its leases
TeraWulf finds sites with big grid connections, builds the shell, power and cooling, and rents each building for ten years or more. The tenant brings its own computers.
The company · 2 · What exactly does it sell?
Rent is now most of its sales; mining is fading
Third-quarter 2026 sales
75%25%
HPC data centre leasingBitcoin mining
Of the leasing money, $46.0 million was rent; the rest was fit-out and power passed on to tenants. Mining was 90% of sales in 2025.
The company · 3 · How does it make money?
Rent from long leases, once the buildings are finished
About $27 billionof rent signed over the leases' lives
About $1.5 billionof yearly profit after running costs, once all is built
102 of 839 MWpaying rent at the end of September
The three tenants, Fluidstack, Core42 and Anthropic, add up to that rent only when every building is finished. Most of it sits on a Kentucky campus still being built.
Is it a good business? · 4 · What gives it an edge?
What it holds is power already connected to the grid
About 750 MWapproved plan at Lake Mariner, New York
482 MWapproved on an old smelter's wires in Kentucky
Googlepromises to pay if the main tenants fail
Power is the scarce thing. That is why big AI tenants signed long leases with a company that finished its first data hall only in 2025. It wins on speed, not on price.
Is it a good business? · 5 · What is the catch?
The buyers build their own, and rivals sell the same
Almost 60%of space the largest buyers build themselves
Cipherrents halls to TeraWulf's own main tenant
$215.4 millionpay in shares in nine months, above sales
TeraWulf competes on speed, long terms and Google's credit, not on lower rent. And it pays its people heavily in new shares.
Is it a good business? · 6 · What does its record show?
Mining paid until 2025; rent took over in 2026
Sales, $M
69.2
140.1
168.5
190.8
Dec 2023Dec 2024Dec 2025last 12 mo
Sales$168.5Msales in 2025, 90% from mining
Rent$115.9Mleasing sales in nine months of 2026
Loss$88.2Moperating loss in the third quarter
The sales record says little about the future, because the business is switching from mining to renting, and it loses money while the buildings go up.
Is it a good business? · 7 · How much room is there to grow?
Demand doubled, and powered space is nearly gone
25 GWtaken up by North American data centres, first half of 2026
95%of what is being built is spoken for in advance
1.4%of space free in the main US markets, a record low
The limit on TeraWulf's growth is power it can deliver and money to build, not tenants. Muskie, its third site, has a gigawatt of power and no tenant yet.
Is it a good business? · 8 · Who is in charge?
Founders own a lot and are paid a lot
Paul Pragerco-founder, chief executive since 2021
15.9%of the shares owned by insiders
$39.4 millionchief executive's pay in 2025
A trust for staff of Prager's private company takes 2% of data-centre spending, and the New York land is leased from a company he controls.
The story right now · 9 · Why do AI companies rent buildings?
AI companies need powered buildings faster than they can build
Under 1,500 MWfree in the main US markets in mid-2026, about six months of demand
Anthropicone of TeraWulf's three tenants
AI computers need buildings with huge power supplies now. Building their own takes years, so AI companies rent from landlords that already have a grid connection.
The story right now · 10 · How does a landlord pay to build?
New buildings are paid for with debt and new shares
A tenant signs a leaseRent starts when the hall is done.
TeraWulf borrows to build$3.2 billion of notes in New York.
It also sells new shares54.51 million sold in April.
Each share owns lessUnless rent grows faster.
The signed rent is real, but new shares spread it over more owners. Shares out rose 19% this year, so growth can cost shareholders.
The story right now · 11 · What changed lately?
Google backed the Kentucky lease; Muskie still has no tenant
$76.2 millionthird-quarter sales
Googlenow stands behind the Anthropic lease too
Fluorsigned to build the Kentucky campus
$728.4 milliona paper gain on Google's warrants
Mixed quarter
The shares fell 43.8% in six months. Kentucky's utility doubled Muskie's power to a gigawatt, but TeraWulf must fund customer bill credits first.
The story right now · 12 · What is everyone arguing about?
Is the pipeline worth what analysts think?
Many investors think
A large AI landlord with a long pipeline
We think
Signed rent is real; growing beyond it may cost new shares
Every analyst says buy. We are wrong if Kentucky's debt is raised with no new shares and Muskie signs a strong tenant.
The price and our view · 13 · What is a share worth?
No single value here: it is priced as a bet
2.2×if it works
1%kept if it fails
Multiples of the company's value when the bet was last struck, 16 Nov 2026.
We put no single value on a share here, because the business does not yet earn a lasting profit. Instead we ask what the shares pay if the plan works, and what is left if it fails.
The price and our view · 14 · How could we be wrong?
Slips, two big tenants and new shares
A slip becomes a patternBiggest
New York halls moved into early 2027.
Your slice can shrinkShowing now
Shares out rose 19% this year.
Two tenants carry the rentWatch
Anthropic is not yet rated investment grade.
Rent per megawattUnknown
Only the totals are public.
Muskie brings bills before rent: $100 million of customer credits and a gas plant's financing cost.
The price and our view · 15 · How will we know?
February shows whether the New York build pays on time
A Muskie lease signed without new sharesGood sign
Kentucky's debt raised on Google's support, no new sharesWe turn positive
Another slip, a higher cost or a share saleWe turn negative
FEB 202725
Fourth-quarter 2026 results and the annual report. Companies report every three months; each report is a test of the story.
Our view moves on these business events, not on a price line, since we put no single value on a share here.
The price and our view · 16 · So, what do we think?
Google-backed rent, priced about at what it is worth
Speculationthe kind of bet this is
NeutralMedium conviction
TeraWulf, a former bitcoin miner, rents data centres whole on long leases. Counting the Kentucky debt, the price pays about what the signed rent supports. As a bet, it pays well if Muskie leases and leaves little if not. Neutral.
↑ ↓ to move · C for contents
What it does
More about the company
Who it is
TeraWulf finds sites with big grid connections, builds data centres on them and rents each building to one tenant for ten years or more. The tenant brings its own computers; TeraWulf supplies the power, the cooling and the shell.
Buyers come to it because powered space is scarce: under 1,500 megawatts was free across the main U.S. markets in mid-2026, about six months of demand. The alternative is to build it themselves, which the largest buyers do for almost 60% of their space.
How it makes money
Rent is now most of the money. Third-quarter 2026 revenue was $76.2 million: $63.0 million from leasing, $46.0 million of it rent, and $13.2 million from mining bitcoin, which is being shut down hall by hall.
Only 102 of the 839 leased megawatts were paying rent at the end of September. Management says the leases total about $27 billion, about $1.5 billion a year of profit after running costs once all is built.
Growth and profit
What growth costs
It is too early to say whether growth will make TeraWulf more profitable. Building costs billions while rent has barely started, and pay in shares runs above sales. Management says the leasing profit will reach about 85% of rent once the halls fill; today it is 17%.
Its record
The numbers
Is it growing?Steady
Sales grew 14% over the twelve months to Sep 2026, slower than the 20% in the year to Dec 2025.
Is it profitable?Losing
Operating margin is −250%, down from −42% in the year to Dec 2023.
Does growth pay off?Unclear
Running costs take 276¢ of each sales dollar, up from 96¢ in the year to Dec 2023.
Does it earn good returns?Poor
Shareholders' money lost 140% a year, down from −33% in the year to Dec 2023.
How long can it keep going?Short
It used $3.11B of cash over the last twelve months, so the $1.60B it holds lasts about 0.5 years at that pace.
Are shares being diluted?Diluting
The share count rose 173% in 2.8 years, and pay in shares costs 116% of sales.
Why it wins
The evidence
What TeraWulf holds is power already connected. Lake Mariner has an approved plan to grow to about 750 megawatts, and the Kentucky campus sits on the wires of a closed aluminium smelter, with the state regulator's approval for 482 megawatts.
That is why Google-backed tenants and Anthropic signed long leases with a company that finished its first data hall only in 2025. It buys a place in line, not pricing power: nobody publishes what each megawatt rents for.
Who could beat it
The rivals in full
The biggest buyers mostly build their own data centres, and rivals sell the same thing: Cipher rents halls to Fluidstack, TeraWulf's own main tenant, and Applied Digital signs 15-year leases with the same kind of buyer. TeraWulf's answer is speed, long terms and Google's credit, not lower rent.
Each rival
Amazon, Google, Microsoft and Meta building their own capacityAMZNGOOGLMSFTMETA
The buyer stops leasing a powered shell and builds the substation, hall and cooling itself, as it does for almost 60% of its capacity.
The same product to the same buyer: approximately 15-year leases to investment-grade hyperscalers.
MARA Holdings, Riot Platforms and the other listed bitcoin minersMARARIOT
The same fixed issuance of bitcoin: every machine a rival adds lowers TeraWulf's share of each day's reward.
How big it could get
The market and who has signed
The market
Demand is running hot. North American data centres absorbed 25 gigawatts in the first half of 2026, double a year earlier, and 95% of what is being built was spoken for in advance.
The government's energy statisticians expect servers to take a growing share of the power used by commercial buildings for decades. The limit on TeraWulf is power it can deliver and money to build, not tenants.
Who has signed
Fluidstack signed for 378 megawatts at Lake Mariner for 10 years, with Google promising to pay if Fluidstack fails. Core42 took 60 megawatts there. Anthropic signed for about 401 megawatts in Kentucky for 20 years, with Google's support starting once the last hall opens. Some New York halls moved into early 2027.
Who runs it
Leaders, pay and the cash
Who runs it
Paul Prager co-founded TeraWulf and has run it since 2021; the finance chief has been in post since 2022. Insiders own about 16%. The chief executive was paid $39.4 million in 2025, much of it on share-price targets of about $6. A trust for staff of Prager's private company takes 2% of data-centre spending, and the New York land is leased from a company he controls.
The last report
The latest report
Rent was most of TeraWulf's revenue; a Google warrant gain made the profit
What it did to the thesis Mixed quarter
The rent is real and the build is on budget, but one building slipped, stock pay stays heavy and Muskie has no tenant, so the case holds without getting stronger.
The report
The third-quarter 2026 report, out on 6 November, showed leasing taking over. Revenue was $76.2 million, $63.0 million of it from leasing. The business still lost $88.2 million before interest, and net income of $709.9 million came from a $728.4 million accounting gain on Google's warrants, not from operations.
What's happening now
The background
The next test is the fourth-quarter report, due about 25 February 2027: whether the fourth building is paying rent, the fifth is on course for March, and the Kentucky campus's debt is raised without new shares.
Where we disagree
Both sides in full
The market
Every analyst rates it a buy, with targets near twice the price: they see a large AI landlord with a long pipeline.
We believe
The signed rent is worth about today's price; the pipeline is real but unsigned, and paying for it may take new shares.
The argument
The difference is in the filings: 19% more shares in ten months, pay in shares above revenue, one building already moved later, and most of the rent sitting on a campus not yet built.
We would be wrong if the Kentucky debt is raised on Google's support with no new shares and Muskie leases to a strong tenant without new equity.
What it's worth
How we value it
No fair value: the analysts' forecasts show no lasting operating profit after stock pay, so a value built on earnings would rest on a guess; the bet prices it instead.
The bet
This is a bet that TeraWulf leases Muskie's first phase on the same terms as its first three leases, without new shares. Then the company could be worth about twice today's price, though new leases bring new debt.
If leasing fails, a tenant walks before Google's support starts, or the Kentucky campus is stranded half built, little is left for shareholders: the noteholders are paid first, and mining is being shut down.
The bet
Seen as a bet
This is a bet that TeraWulf leases Muskie's first phase on the same terms as its first three leases, without new shares. Then the company could be worth about twice today's price, though new leases bring new debt.
If leasing fails, a tenant walks before Google's support starts, or the Kentucky campus is stranded half built, little is left for shareholders: the noteholders are paid first, and mining is being shut down.
What could go wrong
Every risk
The risks
A slip becomes a pattern
Lake Mariner's tenant space was due in 2026 and was moved hall by hall into early 2027.
Two tenants carry the rent
Fluidstack and Anthropic hold almost all of it, and Anthropic is not yet rated investment grade.
Your slice can shrink
Shares rose 19% this year, and Google's warrants, unvested awards and convertible notes sit above today's count.
Muskie brings bills first
TeraWulf pays $100 million of bill credits and a gas plant's financing cost before any tenant signs.
Insiders mostly sell
Insiders sold 17 times in a year, nine by choice, including the finance chief at $16.14.
What we still do not know
What rent each lease pays per unit of power; only the totals are public.
What Justified will finally cost: Fluor's maximum price is still being set.
Fluidstack's and Anthropic's own finances in detail: neither publishes full accounts.
Who, if anyone, will lease Muskie, and on what terms.
What changes our view
Every route to a new view
Every route to a new view
→ Attractive
The Kentucky campus's debt raised on Google's support with no new shares, and the fifth New York building paying rent by 31 March 2027. A Muskie lease signed with a strong tenant or backer, paid for without new shares.
→ Unattractive
Kentucky slips past mid-2028 or costs over $12 million a megawatt, or the fifth New York building is not paying rent by June 2027. New shares sold to pay for Kentucky or Muskie. A tenant stops paying, or Google's promise is called on, at either campus.
The next test
It supports the case if
All four CB-4 halls paid rent in the fourth quarter, CB-5 is dated to the first quarter, the Abernathy $150M arrived, and Justified's financing closed or launched on Google's support with no share sale.
It pressures the case if
CB-4 or CB-5 moves later, Justified's cost estimate rises above $12M per MW, any common shares are sold, or cash overhead rises above the third quarter's $27.1M.
We would also be wrong if
Muskie still has no tenant at the end of 2027.
The verdict
Scores and how we weighed it
The scores
Growth
3 of 4
Business quality
3 of 4
Financial position
2 of 4
Execution record
3 of 4
Per share capture
2 of 4
Potential
3 of 4
Risk profile
2 of 4
Valuation
3 of 4
Evidence quality
3 of 4
How we weighed it
ValueMixed
No fair value is drawn: forecasts show no lasting profit after stock pay. The signed rent is priced close to what it is worth once the Kentucky debt is counted.
BusinessMixed
Connected power and Google-backed tenants, but the same tenants sign with rivals and the record is short.
GrowthPositive
Rent is rising fast as Lake Mariner's halls open, and Kentucky doubles it from late in the coming year if built on time.
RisksNegative
Most rent rests on one AI lab with Google behind it, the second campus is unbuilt, and new shares may fund the next.
RivalsMixed
No filed rival compares cleanly; Cipher and Applied Digital offer the same product to the same buyers.
The groupMixed
AI hosting names move together on AI spending and credit news, and the group has fallen hard since summer.
Latest newsPositive
Google's support for the Anthropic lease and Fluor's contract made the second campus financeable; the quarter's rent rose.
In plain words
Selling new shares
A company can raise money by creating new shares and selling them. The company gets cash, but the same business is now divided into more slices, so each existing share owns a little less of it. This is called dilution.