MARA runs one of the largest bitcoin-mining fleets
Bitcoin mining
about 71 EH/s of machines
Cash and coins
held after selling bitcoin
Power sites
offered to AI tenants
MARA runs computers that earn new bitcoin, holds the coins and cash it has built up, and wants to rent its power sites to AI data centres.
The company · 2 · What exactly does it sell?
Nearly every sales dollar comes from mining
Each $1 of sales, third quarter of 2026
97%3%
Bitcoin miningOther services
Its French cloud unit, Exaion, signed a four-year $79M contract to rent out AI chips. No data-centre rent has started.
The company · 3 · How does it make money?
Mining now earns less than it costs
$27.7earned per unit of mining power a day
$30.8MARA's cost per unit a day
About $420Mof cash used a year
The network pays miners in bitcoin, so when bitcoin falls every machine earns less. At November's price, what a unit of mining power earns a day is below what it costs MARA.
Is it a good business? · 4 · What gives it an edge?
MARA has no edge in mining, only size
5.4%of all miners' rewards, in line with its machines
More than 438 GWof power requested on the Texas grid
2,000 MWpower letter at Matagorda, not yet built
Every miner sells the same coin at the same price. What could be scarce is connected power, which AI tenants want, but MARA has not leased any yet.
Big tenants can also buy land and power themselves. Under its venture with Starwood, MARA keeps only part of each project it leases.
Is it a good business? · 6 · What does its record show?
Sales follow bitcoin, and the losses are large
Sales-35%third-quarter sales against a year ago
Loss$1.31Bloss in 2025, after a profit in 2024
Shares+14%more shares in 2025
Sales rose in 2025 because bitcoin was dearer, not because demand grew. Machine wear and hosting fees stay fixed when bitcoin falls.
Is it a good business? · 7 · How much room is there to grow?
The AI market is huge; MARA's share is not signed
More than 438 GWof large power requests in Texas, mostly data centres
About $1.98Mrent per megawatt a year on Riot's lease
About 0.5%Matagorda's 2,000 MW of those requests
Many requests will never be built. The limit is signing a tenant, not the size of the market.
Is it a good business? · 8 · Who is in charge?
Fred Thiel has run MARA since 2021
Since 2021Fred Thiel in charge, also chairman
Under 1%owned by directors and officers
21.6%of votes backed pay in 2025
In 2026 management sold about 40,500 coins to buy back notes, repay loans and approve buying back its own shares. Bonuses still reward computing power running, not cash.
The story right now · 9 · Why does bitcoin's price decide almost everything?
Bitcoin's price sets both MARA's sales and its savings
$71,688average per coin mined in the third quarter
$114,440a year earlier
20,415coins still held
Nearly all sales are bitcoin mined, and the coins it holds are much of what it owns. When bitcoin falls, both drop at once.
The story right now · 10 · Why do miners keep earning less?
More machines and a falling coin squeeze every miner
The network pays a fixed amountNew coins every ten minutes, shared by all.
Each miner gets its shareIn proportion to its machines.
Rivals add machinesEvery miner's share shrinks.
Bitcoin fallsEach coin is worth less too.
When both happen, a unit of mining power earns less than it costs, as now. That is why MARA wants rent from AI tenants instead.
The story right now · 11 · What changed lately?
MARA sold coins to clear its loans
13,597bitcoin sold for about $1.1B
$750Mof coin-backed loans repaid
$500Mapproved to buy back its own shares
$1.5Bgas plant purchase approved on 4 November
Mixed quarter
The lease promised for this year became two leases that could slip into next year.
The story right now · 12 · What is everyone arguing about?
Will MARA sign a lease before its cushion wears down?
Many investors think
A cheap miner about to become an AI landlord
We think
A loss-making mine on a cushion of cash and coins
Cash and coins cover the notes with a little to spare, but mining uses about $420M a year. A signed lease of 200 MW or more would change our mind.
The price and our view · 13 · What is a share worth?
The price pays a small premium for leases nobody has signed
0.8×if it works
59%kept if it fails
Multiples of the company's value when the bet was last struck, 16 Nov 2026.
We put no single value on a share, because the business earns no lasting profit. The price is about 1.33 times what MARA owns less what it owes, at today's bitcoin.
The price and our view · 14 · How could we be wrong?
Bitcoin, the notes and a costly plant
Bitcoin falls furtherBiggest
Sales and the coins held drop together.
Notes fall dueWatch
About $924M can be asked back in 2027.
The gas plantUnknown
About $0.6B of cash before any tenant.
Rivals sign firstShowing now
Riot already leased 910 MW.
If coins run low with no lease, MARA may sell new shares; about $1.5B of a share programme is unused.
The price and our view · 15 · How will we know?
February shows whether a lease is signed
A lease of 200 MW or more through StarwoodWe turn positive
Long Ridge closed with cash left above $0.6BGood sign
Coins held under 10,000 or new shares soldWe turn negative
FEB 202725
Fourth-quarter 2026 results, about 25 February. Companies report every three months; each report is a test of the story.
Our view also turns negative on price alone if the company is valued at 1.8 times what it owned less owed in September with no lease.
The price and our view · 16 · So, what do we think?
A cushioned miner whose AI plan is still unsigned
Priced for successthe kind of bet this is
NeutralMedium conviction
Mining loses cash at today's bitcoin, but cash and coins cover the notes, and the price pays only a small premium for leases nobody has signed. Neutral.
↑ ↓ to move · C for contents
What it does
More about the company
Who it is
Bitcoin is created by computers racing to solve a puzzle; about every ten minutes the network pays 3.125 new bitcoin, plus fees, to whoever solves it first. MARA runs tens of thousands of these machines on its own sites and in other companies' buildings, and won about 5.4% of all rewards in the third quarter.
Its new plan is to use the same power for AI data centres: Starwood would build halls on MARA's sites and find tenants, and MARA would keep 10% to 50% of each project.
How it makes money
Almost all revenue is bitcoin mined: $159.0M of $164.2M in the third quarter. It rises and falls with bitcoin's price and with how much computing power the rest of the network adds. MARA's cost was $30.8 per petahash a day, a unit of mining power, and the electricity alone cost $39,674 per coin mined.
Exaion, its French cloud unit, signed a four-year $79M contract to rent out AI chips, its first in the United States.
Growth and profit
What growth costs
Growth has not made the business more profitable. Sales rose in 2025 while a profit turned into a $1.31B loss, and in 2026 sales are falling with bitcoin while machine wear, hosting fees and overheads stay fixed: $150.9M of depreciation and $75.8M of overheads in one quarter.
Why it wins
The evidence
There is no protection on the mining side. Every miner sells the same coin at the same price, and the network pays each one in proportion to its computing power: MARA's 5.4% share of rewards is simply its share of the machines. When bitcoin falls, every miner earns less at once.
Connected power is scarce, which is what an AI tenant pays for, but MARA has not yet turned any of it into a lease.
Who could beat it
The rivals in full
Other converted miners already offer the same thing: Riot signed a 910 MW, 15-year lease, and Hut 8, TeraWulf, IREN and Core Scientific describe leasing powered sites to AI tenants. The biggest tenants can also buy land and power themselves. In mining, every new machine added anywhere in the world cuts the share of rewards MARA's machines earn.
Each rival
Converted miners and AI landlords: Riot, Hut 8, TeraWulf, IREN, Core Scientific, CleanSparkRIOTHUTWULFIRENCORZCLSK
Offer the same powered sites to the same AI tenants; Riot, TeraWulf and Core Scientific have already signed long leases.
Hyperscalers and AI labs building their own campusesin house
Adding machines raises network difficulty and cuts the share of rewards MARA's fleet earns.
How big it could get
The market and who has signed
The market
Texas's grid operator was tracking more than 438 GW of requests from large users in June 2026, nearly 89% data centres; many will never be built. Riot's lease shows what a converted site can earn: about $1.98M of rent per megawatt a year. MARA's largest Texas option, a 2,000 MW power letter at Matagorda, is about half a percent of those requests, and none of it is leased.
Who runs it
Leaders, pay and the cash
Who runs it
Fred Thiel has run MARA since April 2021 and also chairs the board. Directors and officers own under 1% of the shares. Only about a fifth of votes backed executive pay in 2025; bonuses pay on how much computing power is running and long-term awards on hashrate, megawatts and the share price against rivals.
Insiders sold steadily under plans set in advance and bought nothing in the past year.
What they did with the money
In 2025 MARA spent heavily on machines and bitcoin, partly with new shares: diluted shares rose 14%. In 2026 it reversed course, selling about 40,500 coins to buy back about $1.0B of notes, repay its loans and approve a buyback. It sold only $46.5M of new shares this year and has about $1.5B more it could sell.
The last report
The latest report
Sales fell with bitcoin; coins sold to clear loans; leases slip again
What it did to the thesis Mixed quarter
It made the downside safer: the loans backed by coins are gone and cash is up. It did nothing for the case for more, because mining earns less and the lease promised for this year may slip.
The report
In the third quarter of 2026 sales fell 35% to $164.2M as the price of each bitcoin mined dropped from $114,440 to $71,688. Reported profit of $632.1M came from the rise in the value of bitcoin held during the quarter, not from mining.
After the quarter MARA sold 13,597 bitcoin for about $1.1B, repaid all $750M of loans backed by its coins and approved a $500M share buyback. It now targets two data-centre leases by year-end but says they could slip into next year.
What's happening now
The background
The next test is the fourth-quarter report, due around 25 February 2027: whether a lease is signed, how much cash Long Ridge took, and how many coins are left.
Where we disagree
Both sides in full
The market
A cheap miner on its way to becoming an AI landlord, held back by bitcoin's fall.
We believe
A loss-making mine on a cushion of cash and coins; the AI plan is real but unsigned, so fair rather than cheap.
The argument
Bears see a miner losing money as bitcoin falls; bulls see the next Riot, the cheapest of its rivals and ready to sign leases. We see both halves: the coins cushion the downside, but nothing is signed, so the price is fair rather than cheap.
The evidence against us: if a lease of 200 MW or more is signed at a rent near Riot's, today's price would look low.
What it's worth
How we value it
No fair value: the analysts' forecasts show an operating loss in every year to 2029 and the business has no lasting profit after stock pay, so the bet and book value price it.
The bet
This bet is on the data-centre business. If one 200 MW lease is signed at Riot's rent and MARA keeps half of it, its share of rent would be about $198M a year. Added to what MARA owns after another year of mining losses, that is still worth less than today's price.
If no lease comes, shareholders keep the cash, the coins and a mine that loses money: about three fifths of today's value.
The bet
Seen as a bet
This bet is on the data-centre business. If one 200 MW lease is signed at Riot's rent and MARA keeps half of it, its share of rent would be about $198M a year. Added to what MARA owns after another year of mining losses, that is still worth less than today's price.
If no lease comes, shareholders keep the cash, the coins and a mine that loses money: about three fifths of today's value.
What could go wrong
Every risk
The risks
Bitcoin falls further
Mining revenue and the value of the coins held both drop at once.
Notes fall due
Holders can ask for about $924M back in 2027, paid from cash and coins.
The plant takes cash first
Long Ridge needs about $0.6B and carries its own debt before any AI tenant pays.
Rivals sign first
Riot and others are already leasing sites to the same tenants.
One Texas study
Matagorda's power waits on the grid operator's batch study, which a state audit may delay.
What we still do not know
Which site MARA contributes to Starwood first, and how much of each project it keeps.
Whether Exaion's $3B of interest turns into more signed contracts.
Whether an AI tenant signs for Long Ridge before the build starts in 2027.
What changes our view
Every route to a new view
Every route to a new view
→ Attractive
A data-centre lease of 200 MW or more is signed through Starwood with a creditworthy tenant.
→ Unattractive
Bitcoin held falls below 10,000 coins with no lease signed. New shares are sold to meet the note repayments or close Long Ridge.
→ Unattractive
The company's value rises to 1.8 times what it owned less what it owed in September, with no lease signed.
The next test
It supports the case if
A lease of 200 MW or more is signed, Long Ridge closed with cash left above $0.6B, and no shares were sold.
It pressures the case if
No lease, the coins held fall below 15,000, or shares are sold under the programme.
We would also be wrong if
The coins held fall below 15,000 by the fourth-quarter report.
Long Ridge closes but leaves under $0.6B of cash.
The verdict
Scores and how we weighed it
The scores
Growth
1 of 4
Business quality
2 of 4
Financial position
2 of 4
Execution record
2 of 4
Per share capture
2 of 4
Potential
2 of 4
Risk profile
2 of 4
Valuation
3 of 4
Evidence quality
3 of 4
How we weighed it
ValueMixed
No fair value is drawn: the forecasts show losses every year. The price sits near book marked to today's bitcoin, cheap against rivals who have signed rent.
BusinessNegative
A weak business: a price-taker whose mining loses cash at today's bitcoin price, with no lease to show its sites earn more.
GrowthNegative
Sales are falling with bitcoin's price, and the leases that would add rent keep slipping.
RisksNegative
Bitcoin's price drives revenue and the coins held, note puts fall due next year, and the gas plant takes cash before it earns.
RivalsMixed
The cheapest of its filed rivals on book value, because the dearer ones have already signed long leases.
The groupMixed
Miners and AI landlords move together on bitcoin and on news of AI spending.
Latest newsMixed
The last report swapped coins for cash and cleared the loans, but pushed the lease target out again.