Riot Platforms

This is the archived full research. Read the story

A Texas bitcoin miner turning its grid connections into data centres it rents to AI companies for up to twenty years.

Our viewNeutral Medium conviction
The scores
The profile · 1-4
Growth2/4 ↑

Q3 sales were flat at $181.4M as mining fell and engineering grew; rent from the signed leases starts in 2027.

Business quality2/4 ↑

Most revenue is mining, a price-taker; the connected Texas power is scarce, but five listed rivals lease the same thing to the same tenants.

Financial position2/4 →

Liquidity of $950M and no equity raised, but $7.7-7.9B of building needs $6.1-7.0B of unarranged project debt and a bridge due December.

Execution record3/4 →

AMD's first 25 MW arrived on time in five months; the promised AMD term loan is unfiled, and the record is one hall.

Per share capture2/4 →

Shares rose 8% in fifteen months on stock awards, a 40 million-share convertible sits near the price, and the lab needs $210-460M of equity.

Potential3/4 ↑

1,151 MW signed for 10 to 20 years with dated delivery and about $38B of rent; the contracts are committed, the financing is not.

Risk profile2/4 →

One tenant is about 97% of contracted rent, and the build's financing resolves in a few steps, the Rockdale takeout and Corsicana's project debt.

Valuation3/4 ↑

About $6.5B against $2.2B a year of contracted rent profit pays for the plan working; the build is unfinanced and one tenant pays most.

Evidence quality3/4 →

Leases, mining costs and debt are filed and grid scarcity is ERCOT's; the rent margins, takeout and tenant's name rest on management and the press.

The bet · 2-3 years
Speculation7.1×

If it works 7.1× · if it fails you keep about 68%.

The Verdict

We rate Riot Platforms Neutral. Today it is a bitcoin miner that loses money once its machines wear out, so the business is mixed, but it has signed three data-centre leases. The price is a fraction of the rent profit those leases should earn by mid-2028, which makes it fair rather than dear. What holds us back is the money to build: the large Rockdale hall runs on a short bridge loan, the long-term lenders are not signed and one lab is nearly all of the rent. As a bet it is speculative: several times today if all are built.

The long caseRiot already holds Texas grid power that the state is now rationing, and AI tenants will pay for twenty years to use it.

How we weighed it

The price against our value

Cuts both ways

No fair value is drawn: the forecasts show no lasting profit after stock pay, so the bet prices it.

The business

Against it

Mixed

A mixed business near the weak end: mining loses money after wear.

Growth against what the price assumes

In its favour

Signed leases give large rent growth once built.

What could go wrong

Against it

The financing may slip, one lab is nearly all of the rent, two large builds must be delivered and more shares may come.

Against competitors

Cuts both ways

Priced between pure miners and converted landlords, which fits its stage.

How its group is behaving

Cuts both ways

AI hosting names move together on AI spending and funding news.

The latest news and report

Cuts both ways

The last report took one half of the route to Attractive and left the financing open.

The evidence under this - 6 claims
C14facthigh confidence
AMD leased 25 MW at Rockdale in January 2026 for 10 years with three five-year extensions; it was delivered in January and May, on time and on budget per the company. In April AMD took 25 MW more, due 10 MW in November 2026 and 15 MW in May 2027, and holds options on 50 MW plus a conditional right to 100 MW. AMD pays power at cost and reimburses fit-out plus a margin.
current state · 2026-06-30written 2026-10-18
C15facthigh confidence
In August 2026 Riot signed a lease with a frontier AI lab for 191 MW of critical IT capacity at Rockdale, a Tier 3 build-to-suit: 96 MW due December 2027 and the rest June 2028. The 20-year term starts at full delivery and carries two five-year renewals and about $9.1B of base rent. With AMD, 241 MW is leased.
against this
  • The lease is described in the 10-Q and an 8-K item, but the contract itself has not been filed as an exhibit.
  • No rent is paid until the first hall is delivered in December 2027.
current state · 2026-08-10written 2026-10-18
C16management claimmedium confidence
Management expects the two leases to bring about $520M of revenue a year on average, $63.6M from AMD's 50 MW and $457M from the lab, and $416-462M of yearly operating income at an 80% to 90% margin. Building them costs $2.3-2.5B, $11-12M per megawatt for the lab hall.
against this
  • The margin is an estimate: the only rent billed so far is $4.9M in Q2 on AMD's first 25 MW (C03), at an 84% lease gross margin by management's account.
  • The averages include yearly rent escalators over the full terms, so early years earn less.
forwardwritten 2026-10-18
C36factmedium confidence
On 4 November 2026 Riot announced a 15-year triple-net powered land lease with a frontier AI lab for the whole Corsicana campus, 910 MW of critical IT capacity: about $28B of rent over the initial term, $1.8B a year on average at a 99% margin, delivered in three phases (400 MW in September 2027, 200 MW in January 2028, 310 MW in July 2028). Riot builds the land, power and powered pads for about $6M per megawatt, $5.5B in all, of which $4M a megawatt is reimbursed to the tenant for its modules after each phase delivers and pays rent; the tenant owns and runs the computers and pays power as a pass-through.
against this
  • The release does not name the tenant, and the lease itself is not yet filed; the tenant may be the same unnamed lab as at Rockdale, which would concentrate rent further (C19).
  • The 99% margin and 33% yield are management's estimates before financing costs; the $3.64B tenant reimbursement is to come from project debt that has not been arranged, or through rent credits at an implied 12% a year.
current state · 2026-11-04written 2026-11-04
C17facthigh confidence
To start the 191 MW build Riot took a $573.0M delayed-draw loan from lenders led by Morgan Stanley, secured only on the project and not on Riot, at SOFR plus 2.75%. The 8-K says it matures on 31 December 2026; the 10-Q filed four days earlier said 15 October 2026, subject to extension on refinancing.
against this

The lender has no claim on Riot itself, so a failed takeout would cost the project rather than the parent.

current state · 2026-08-14written 2026-10-18
C26inferencemedium confidence
At $17.83 the company is valued at about $6.5B including debt, cash and investments, against average yearly net operating income management expects of about $2.2B once all 1,151 MW of signed leases are in service by July 2028: $1.8B from Corsicana, $361-406M from the Rockdale lab lease and $50M from AMD. Building them costs $7.7-7.9B, with $6.1-7.0B of non-recourse project debt illustrated, so debt service stands ahead of shareholders for most of it.
against this
  • Average NOI is before the cost of the debt that builds the leases and over the full 10- to 20-year terms, with early years earning less.
  • The mining, engineering and bitcoin that the price also buys are outside that NOI (C33).
  1. 2026-11-04editedre-struck at the 3 November close on the three signed leases
  2. 2026-11-13editedre-struck at the 12 November close on the bridged company value
current state · 2026-11-12written 2026-10-18
01

The company

Riot sells what its power can make. Most of it runs about 44 EH/s of bitcoin-mining machines at Rockdale, Corsicana and in Kentucky. A growing part goes into data-centre halls built for AI companies, which bring their own chips and pay rent for space, cooling and power.

The tenants' alternative is to find land and wait for a new grid connection in Texas, which the state now hands out in batches from 2028. Riot's sites already have theirs.

The evidence under this - 4 claims
C01facthigh confidence
Riot reports three segments: Bitcoin Mining, Data Center (a reportable segment since Q1 2026) and Engineering, which makes electrical gear through ESS Metron and E4A. At 30 June 2026 it had 1,292 MW of developed power, Rockdale 700 MW, Corsicana 400 MW and Kentucky 192 MW, and 44.4 EH/s of miners deployed.
current state · 2026-06-30written 2026-10-18
C14facthigh confidence
AMD leased 25 MW at Rockdale in January 2026 for 10 years with three five-year extensions; it was delivered in January and May, on time and on budget per the company. In April AMD took 25 MW more, due 10 MW in November 2026 and 15 MW in May 2027, and holds options on 50 MW plus a conditional right to 100 MW. AMD pays power at cost and reimburses fit-out plus a margin.
current state · 2026-06-30written 2026-10-18
C15facthigh confidence
In August 2026 Riot signed a lease with a frontier AI lab for 191 MW of critical IT capacity at Rockdale, a Tier 3 build-to-suit: 96 MW due December 2027 and the rest June 2028. The 20-year term starts at full delivery and carries two five-year renewals and about $9.1B of base rent. With AMD, 241 MW is leased.
against this
  • The lease is described in the 10-Q and an 8-K item, but the contract itself has not been filed as an exhibit.
  • No rent is paid until the first hall is delivered in December 2027.
current state · 2026-08-10written 2026-10-18
C21factmedium confidence
Texas regulators approved ERCOT's Batch Zero process in June 2026: new loads of 75 MW or more are studied together, results due April 2027, with yearly allocations for 2028 to 2032. Riot's chief executive says Rockdale and Corsicana sit outside it because their power is already under existing interconnection agreements.
against this

That Riot's sites are outside the batch is management's statement; ERCOT publishes no list of exempt sites.

current state · 2026-07-29written 2026-10-18

How it makes money

Today almost all money comes from bitcoin: Riot's machines win new coins and it sells them every month, so revenue rises and falls with the bitcoin price. Its engineering arm also sells switchgear and power rooms.

The new money is rent. A tenant signs for 10 or 20 years, pays a base rent that rises each year, and pays for its power at cost. Management expects about 80 to 90 cents of each rent dollar to be profit.

The evidence under this - 6 claims
C03facthigh confidence
Q2 2026 revenue was $174.2M against $153.0M a year earlier: Bitcoin Mining $113.7M (from $140.9M), Data Center $23.2M ($4.9M of rent and $18.3M of tenant fit-out) and Engineering $37.3M. The net loss was $237.2M, $0.68 a share, and adjusted EBITDA was a loss of $69.7M.
historical · Q2 2026written 2026-10-18
C05facthigh confidence
In Q2 2026 Riot mined 1,587 bitcoin worth $71,667 each when mined. Its cost to mine one, before miner depreciation, was $49,912 (69.6% of value); including miner depreciation it was $90,631 (126.5%). A year earlier the figures were $48,992 and $91,244 against a value of $98,800.
historical · Q2 2026written 2026-10-18
C06inferencehigh confidence
Riot's cost to mine nets off power credits that the income statement books on a separate line, outside cost of revenue. Without them Q2 2026's cost before depreciation was $56,247 a bitcoin, not $49,912: the credits were worth $6,335 a coin. They were $31.1M in the first half against $16.1M a year earlier.
against this
  • The credits are real cash, earned by selling fixed-price power back to the grid when prices spike (C07).
  • Management discloses both figures in the same table, so nothing is hidden, only framed.
historical · Q2 2026written 2026-10-18
C14facthigh confidence
AMD leased 25 MW at Rockdale in January 2026 for 10 years with three five-year extensions; it was delivered in January and May, on time and on budget per the company. In April AMD took 25 MW more, due 10 MW in November 2026 and 15 MW in May 2027, and holds options on 50 MW plus a conditional right to 100 MW. AMD pays power at cost and reimburses fit-out plus a margin.
current state · 2026-06-30written 2026-10-18
C16management claimmedium confidence
Management expects the two leases to bring about $520M of revenue a year on average, $63.6M from AMD's 50 MW and $457M from the lab, and $416-462M of yearly operating income at an 80% to 90% margin. Building them costs $2.3-2.5B, $11-12M per megawatt for the lab hall.
against this
  • The margin is an estimate: the only rent billed so far is $4.9M in Q2 on AMD's first 25 MW (C03), at an 84% lease gross margin by management's account.
  • The averages include yearly rent escalators over the full terms, so early years earn less.
forwardwritten 2026-10-18
C23facthigh confidence
The Engineering segment had a $177.1M order backlog at the end of Q2 2026, about 90% for data centres, and sold $8.9M of gear to Riot's own projects in the quarter beside $37.3M to outside customers.
  1. 2026-11-13editedre-checked against the Q3 10-Q, which gives no backlog figure; held to the Q4 report
current state · 2026-06-30written 2026-10-18
Where the money comes from, stream by stream
StreamShare of sales (FY 2025)How it earns it
Bitcoin mining89.0%Bitcoin earned by its own machines in a mining pool and sold monthly.
Engineering10.0%Switchgear, power rooms and electrical work sold to outside customers, mostly data centres.
Data-centre rent2.8%Base rent and power passed through on AMD's halls; $4.9M of rent in Q2 2026.
Tenant fit-out10.5%Equipment Riot buys and installs for AMD and is repaid for at cost plus a margin.

Who runs it

Jason Les has run Riot since 2021 and signed both leases this year. Directors and officers own about 7.8% of the company; their sales in the past year were all pre-arranged. Shareholders rejected the pay plan in 2025 after large one-time awards. This year's bonus rewards bitcoin output and profit against peers and data-centre revenue and profit; long-term awards ride on the share price against the market.

The evidence under this - 3 claims
C30facthigh confidence
Directors and officers owned 29.6 million shares, 7.82%, at the 2026 proxy's record date, Jason Les 9.4 million and Executive Chairman Benjamin Yi 10.6 million. All nine open-market sales by insiders in the past year, 366,255 shares, were under pre-arranged trading plans; there were no purchases.
current state · 2026-04-30written 2026-10-18
C31facthigh confidence
Only 31.5% of votes backed executive pay in 2025, after large one-time awards in 2024. The 2026 bonus is 25% bitcoin output against peers, 25% adjusted EBITDA against peers, 15% data-centre revenue, 15% data-centre operating income and 20% strategy; long-term awards pay on share return against the Russell 3000, capped at target when the return is negative.
current state · 2026-04-30written 2026-10-18
C18management claimmedium confidence
Management plans to replace the bridge with long-term debt once a high investment-grade backstop is finalised, borrowing 80% to 90% of cost, and the Q3 deck still shows that backstop as being finalised with the $573M interim facility in place; the $180M AMD term loan is 'finalizing' with SOFR plus 250 basis points targeted (C38).
against this
  • No takeout or AMD loan closing had been announced by 4 November 2026.
  • Management declined to name the backstop provider or terms (C34), and the deck says lenders are more selective.
  1. 2026-11-04editedstatus at the Q3 results: neither the takeout nor the AMD loan was announced as closed
forwardwritten 2026-10-18
02

Why it wins, and who could beat it

Why customers come back

The advantage is power that is already connected. ERCOT, which runs the Texas grid, counts about 474 GW of requests from large users, mostly data centres, against 5.9 GW actually switched on, and now studies new requests in batches with allocations from 2028.

Riot's Rockdale and Corsicana sites run on existing agreements, which the chief executive says keeps them outside that queue. That is why two tenants signed 241 MW within seven months.

The evidence under this - 4 claims
C20facthigh confidence
ERCOT, the Texas grid operator, was tracking about 474 GW of large loads seeking to connect in June 2026, about 90% data centres, against 5.9 GW energized; 29.9 GW had met interconnection requirements for 2027.
against this

ERCOT says much of the queue is speculative: 284 GW by 2032 has submitted no studies.

current state · 2026-06-30written 2026-10-18
C21factmedium confidence
Texas regulators approved ERCOT's Batch Zero process in June 2026: new loads of 75 MW or more are studied together, results due April 2027, with yearly allocations for 2028 to 2032. Riot's chief executive says Rockdale and Corsicana sit outside it because their power is already under existing interconnection agreements.
against this

That Riot's sites are outside the batch is management's statement; ERCOT publishes no list of exempt sites.

current state · 2026-07-29written 2026-10-18
C14facthigh confidence
AMD leased 25 MW at Rockdale in January 2026 for 10 years with three five-year extensions; it was delivered in January and May, on time and on budget per the company. In April AMD took 25 MW more, due 10 MW in November 2026 and 15 MW in May 2027, and holds options on 50 MW plus a conditional right to 100 MW. AMD pays power at cost and reimburses fit-out plus a margin.
current state · 2026-06-30written 2026-10-18
C15facthigh confidence
In August 2026 Riot signed a lease with a frontier AI lab for 191 MW of critical IT capacity at Rockdale, a Tier 3 build-to-suit: 96 MW due December 2027 and the rest June 2028. The 20-year term starts at full delivery and carries two five-year renewals and about $9.1B of base rent. With AMD, 241 MW is leased.
against this
  • The lease is described in the 10-Q and an 8-K item, but the contract itself has not been filed as an exhibit.
  • No rent is paid until the first hall is delivered in December 2027.
current state · 2026-08-10written 2026-10-18

The threat

Riot is not alone. TeraWulf, Cipher, IREN, Core Scientific and Hut 8 converted their own mines and lease them to the same AI tenants, and Applied Digital builds about 150 MW campuses for hyperscalers. The tenants can also build their own once Texas hands out new power. The engineering arm competes with makers such as Powell Industries.

The evidence under this - 3 claims
C28facthigh confidence
Rival filings describe the same product: Cipher says several miners, naming Hut 8, IREN, TeraWulf, Core Scientific and Applied Digital, have signed leases with hyperscalers and HPC tenants; TeraWulf calls itself an owner of HPC infrastructure on reused industrial sites; Applied Digital builds about 150 MW campuses in 14 to 18 months for investment-grade hyperscalers.
current state · 2026-07-29written 2026-10-18
C20facthigh confidence
ERCOT, the Texas grid operator, was tracking about 474 GW of large loads seeking to connect in June 2026, about 90% data centres, against 5.9 GW energized; 29.9 GW had met interconnection requirements for 2027.
against this

ERCOT says much of the queue is speculative: 284 GW by 2032 has submitted no studies.

current state · 2026-06-30written 2026-10-18
C35facthigh confidence
Powell Industries says it develops, designs, manufactures and services custom-engineered equipment that distributes and controls electrical energy, including power control room substations, electrical houses and switchgear, typically awarded in competitive bids: the products of Riot's Engineering segment.
current state · 2025-09-30written 2026-10-18

The rivals: WULF, CIFR, IREN, CORZ, HUT, APLD, MARA, CLSK, POWL, and 2 more that are private, in-house or listed abroad.

Who else does this, rival by rival
TickerRivalWhere it competesHow far alongPriced against it
WULF · CIFR · IREN · CORZ · HUTOther converted miners: TeraWulf, Cipher, IREN, Core Scientific, Hut 8Priced against it: YesData CenterOn saleYes
APLDApplied DigitalPriced against it: YesData CenterOn saleYes
In-houseTenants building their own data centresPriced against it: In-houseData CenterOn saleIn-house
Not listedNew sites given power in ERCOT's Batch Zero studyPriced against it: Not listedData CenterAnnouncedNot listed
MARA · CLSKOther bitcoin miners: MARA, CleanSparkPriced against it: YesBitcoin MiningOn saleYes
POWLPowell IndustriesPriced against it: One segment onlyEngineeringOn saleOne segment only
03

How big it could get

How big this could get

ERCOT counts 29.9 GW of large users cleared to connect by 2027. Charged at the rent Riot's two leases imply, about $2.16M a megawatt a year, that would be roughly $65B a year, an upper bound since not all of it is data centres.

Riot's 241 MW is under 1% of that, so the market is not the limit; finding the power, the tenant and the money is.

The evidence under this - 3 claims
C20facthigh confidence
ERCOT, the Texas grid operator, was tracking about 474 GW of large loads seeking to connect in June 2026, about 90% data centres, against 5.9 GW energized; 29.9 GW had met interconnection requirements for 2027.
against this

ERCOT says much of the queue is speculative: 284 GW by 2032 has submitted no studies.

current state · 2026-06-30written 2026-10-18
C16management claimmedium confidence
Management expects the two leases to bring about $520M of revenue a year on average, $63.6M from AMD's 50 MW and $457M from the lab, and $416-462M of yearly operating income at an 80% to 90% margin. Building them costs $2.3-2.5B, $11-12M per megawatt for the lab hall.
against this
  • The margin is an estimate: the only rent billed so far is $4.9M in Q2 on AMD's first 25 MW (C03), at an 84% lease gross margin by management's account.
  • The averages include yearly rent escalators over the full terms, so early years earn less.
forwardwritten 2026-10-18
C15facthigh confidence
In August 2026 Riot signed a lease with a frontier AI lab for 191 MW of critical IT capacity at Rockdale, a Tier 3 build-to-suit: 96 MW due December 2027 and the rest June 2028. The 20-year term starts at full delivery and carries two five-year renewals and about $9.1B of base rent. With AMD, 241 MW is leased.
against this
  • The lease is described in the 10-Q and an 8-K item, but the contract itself has not been filed as an exhibit.
  • No rent is paid until the first hall is delivered in December 2027.
current state · 2026-08-10written 2026-10-18

Who has signed

AMD has signed for 50 MW over 10 years and the frontier lab for 191 MW over 20, both firm leases described in the filings. The lab is unnamed by Riot; Bloomberg reported Anthropic. Corsicana's whole site is under a letter of intent with one tenant, which binds nobody.

The evidence under this - 4 claims
C14facthigh confidence
AMD leased 25 MW at Rockdale in January 2026 for 10 years with three five-year extensions; it was delivered in January and May, on time and on budget per the company. In April AMD took 25 MW more, due 10 MW in November 2026 and 15 MW in May 2027, and holds options on 50 MW plus a conditional right to 100 MW. AMD pays power at cost and reimburses fit-out plus a margin.
current state · 2026-06-30written 2026-10-18
C15facthigh confidence
In August 2026 Riot signed a lease with a frontier AI lab for 191 MW of critical IT capacity at Rockdale, a Tier 3 build-to-suit: 96 MW due December 2027 and the rest June 2028. The 20-year term starts at full delivery and carries two five-year renewals and about $9.1B of base rent. With AMD, 241 MW is leased.
against this
  • The lease is described in the 10-Q and an 8-K item, but the contract itself has not been filed as an exhibit.
  • No rent is paid until the first hall is delivered in December 2027.
current state · 2026-08-10written 2026-10-18
C19factmedium confidence
Bloomberg reported, and ForkLog repeated, that the frontier AI lab behind the 191 MW lease is Anthropic; Riot has not named its tenant.
against this

Riot's own filings say only a leading frontier AI lab; the name rests on unnamed sources in the press.

current state · 2026-08-11written 2026-10-18
C22factmedium confidence
Management signed the Corsicana lease on 4 November 2026: 910 MW of critical IT capacity for the whole campus, up from the 756 MW it had described under a non-binding letter of intent (C36).
against this

The lease terms are management's account; the contract has not been filed as an exhibit.

  1. 2026-11-04editedthe letter of intent was converted into a signed lease, so the claim is resolved
historical · October to November 2026written 2026-10-18
04

The results

The numbers

Is it growing?Slow

Sales grew 6.1% over the twelve months to Sep 2026, slower than the 72% in the year to Dec 2025.

Dec 2021: $213MDec 2022: $259MDec 2023: $281MDec 2024: $377MDec 2025: $647M12 mo to Sep 2026: $676M$213M$676M
Is it profitable?Losing

Operating margin is −211%, down from −22% in the year to Dec 2023.

Dec 2021: −14%Dec 2022: −198%Dec 2023: −22%Dec 2024: 41%Dec 2025: −96%12 mo to Sep 2026: −211%−14%−211%
How steady is it?Swingy

Yearly sales growth has ranged from +8.3% to +17× over the last 5 years.

Dec 2021: +17×Dec 2022: +22%Dec 2023: +8.3%Dec 2024: +34%Dec 2025: +72%+17×+72%
Does it earn good returns?Poor

Shareholders' money lost 51% a year, down from −1.9% in the year to Dec 2021.

Dec 2021: −1.9%Dec 2022: −41%Dec 2023: −3.3%Dec 2024: 4.3%Dec 2025: −22%12 mo to Sep 2026: −51%−1.9%−51%
How long can it keep going?Short

It used $901M of cash over the last twelve months, so the $669M it holds lasts about 0.7 years at that pace.

Dec 2021: −$233MDec 2022: −$148MDec 2023: −$161MDec 2024: −$495MDec 2025: −$774M12 mo to Sep 2026: −$901M−$233M−$901M
Is the balance sheet safe?Net cash

It holds $669M of cash against $657M of debt, $12.4M more cash than it owes.

Dec 2023: $596MDec 2024: −$307MDec 2025: −$607M12 mo to Sep 2026: $12.4M$596M$12.4M
Are shares being diluted?Diluting

The share count rose 303% in 4.8 years, and pay in shares costs 19% of sales.

Dec 2021: 93.5MDec 2022: 139MDec 2023: 175MDec 2024: 319MDec 2025: 341M12 mo to Sep 2026: 376M93.5M376M
All the numbers

Filed figures from the company's 10-K and 10-Q, read 2026-11-09. Fiscal years end in December.

Dec 2021Dec 2022Dec 2023Dec 2024Dec 202512 mo to Sep 2026
Size and growth
Sales$213M$259M$281M$377M$647M$676M
Sales growth+17×+22%+8.3%+34%+72%+6.1%
Profit
Operating margin−14%−198%−22%41%−96%−211%
Net margin−7.2%−197%−18%29%−102%−211%
What growth costs, per sales dollar
Selling, general and admin41%26%36%71%46%46%
Pay in shares32%9.5%11%33%19%19%
Capital spending69%57%69%64%31%46%
Cash
Cash from operations−$86.1M$530K$33.1M−$255M−$573M−$593M
Free cash flow−$233M−$148M−$161M−$495M−$774M−$901M
Balance sheet
Cash and short-term investments$323M$230M$597M$278M$234M$669M
Debt--$783K$585M$841M$657M
Net cash--$596M−$307M−$607M$12.4M
Returns and shares
Return on capital---5.4%--
Shares (diluted)93.5M139M175M319M341M376M

What growth costs

Growth has not made Riot more profitable. Sales rose 72% in 2025 while the company swung to a large loss, and this year more sales came with less gross profit, because mining earns less per machine as the network grows. Rent should change that, but so far it is a sliver of revenue.

The evidence under this - 3 claims
C02facthigh confidence
In 2025 revenue was $647.4M against $376.7M in 2024, almost all from Bitcoin Mining ($576.3M against $321.0M) on higher bitcoin prices and more hash rate. The net loss was $663.2M against net income of $109.4M in 2024.
historical · FY 2025written 2026-10-18
C03facthigh confidence
Q2 2026 revenue was $174.2M against $153.0M a year earlier: Bitcoin Mining $113.7M (from $140.9M), Data Center $23.2M ($4.9M of rent and $18.3M of tenant fit-out) and Engineering $37.3M. The net loss was $237.2M, $0.68 a share, and adjusted EBITDA was a loss of $69.7M.
historical · Q2 2026written 2026-10-18
C04facthigh confidence
Segment gross profit in Q2 2026 was $43.5M against $68.4M a year earlier: Bitcoin Mining $24.5M, Data Center $6.5M and Engineering $12.5M. Below that sat $82.0M of selling, general and administrative cost, $97.8M of depreciation and amortisation and a $28.0M impairment of Rockdale mining construction.
historical · Q2 2026written 2026-10-18

The last report (4 Nov)

Quarter ended September 2026, filed figures.

1%
Sales growth
against the same quarter a year earlier
4.1%
Growth from the quarter before
against 4.2% the quarter before that
1¢
Operating profit
per dollar of sales

Riot signed a 15-year lease with a frontier AI lab for all of its Corsicana site, 910 MW worth about $28B of rent, with the first 400 MW due in September 2027. The tenant owns the computers; Riot builds the land and power for about $6M a megawatt.

The quarter itself was flat: sales of $181.4M, with mining down and engineering up, and a profit of one cent a share. The financing for the Rockdale hall was still not closed, and the segment profits await the full filing.

What it did to the thesisIt took one half of the route to Attractive and left the other, the financing, open, so the view stays Neutral. The lease also makes one lab nearly all of the rent, which raises the stakes on the build.

The quarter in detail

Sales growth from the previous quarter, filed figures.

Earnings per share $0.01 against $-0.34 expected; $0.01 as filed, with no adjustments.

The evidence under this - 4 claims
C36factmedium confidence
On 4 November 2026 Riot announced a 15-year triple-net powered land lease with a frontier AI lab for the whole Corsicana campus, 910 MW of critical IT capacity: about $28B of rent over the initial term, $1.8B a year on average at a 99% margin, delivered in three phases (400 MW in September 2027, 200 MW in January 2028, 310 MW in July 2028). Riot builds the land, power and powered pads for about $6M per megawatt, $5.5B in all, of which $4M a megawatt is reimbursed to the tenant for its modules after each phase delivers and pays rent; the tenant owns and runs the computers and pays power as a pass-through.
against this
  • The release does not name the tenant, and the lease itself is not yet filed; the tenant may be the same unnamed lab as at Rockdale, which would concentrate rent further (C19).
  • The 99% margin and 33% yield are management's estimates before financing costs; the $3.64B tenant reimbursement is to come from project debt that has not been arranged, or through rent credits at an implied 12% a year.
current state · 2026-11-04written 2026-11-04
C37facthigh confidence
Q3 2026 revenue was $181.4M against $180.2M a year earlier: Bitcoin Mining $116.0M (from $160.8M) on 1,637 bitcoin mined at an average price of $70,855, Data Center $18.4M ($7.7M of base rent and $10.2M of tenant fit-out) and Engineering $47.0M (from $19.1M). Cost to mine excluding depreciation was $39,265 a bitcoin after $24.7M of power credits. Net income was $25M, $0.01 a share, against a consensus loss of about $0.33. Segment gross profit and the full statements await the 10-Q.
against this
  • The release gives no segment gross profit, so the pre-registered mining gross profit of $40M is unanswered until the 10-Q.
  • Net income reflects non-cash charges and mark-to-market on the bitcoin held, which the presentation says (the Q3 2026 presentation, slide 20); it is not a measure of the mining business.
historical · Q3 2026written 2026-11-04
C38management claimmedium confidence
At the Q3 2026 results Riot's financing was still unfinished: the $573M Morgan Stanley interim facility 'remains in place' while a high investment-grade credit backstop for Rockdale is finalised, the $180M AMD term loan is described as closed or expected to close shortly, and Corsicana financing is to launch in 2027. Riot says credit-led spreads have widened since September and lenders are more selective. It sold 20,264 bitcoin for about $1.5B in the first nine months and ended September with $950.2M of cash and bitcoin ($748.2M cash including $79.2M restricted, and 2,418 bitcoin worth $202.0M), no equity raised in 2026, and says none is currently anticipated for announced projects.
against this
  • Management planned the AMD term loan for the end of Q3 and the Rockdale takeout 'near term' on the Q2 call (C18, C34); neither has been announced as closed, and the deck's cumulative sources chart shows $0.8B to $1.5B of Riot cash equity needed against about $1.2B of near-term liquidity.
  • The deck's illustrative project debt is $6.1B to $7.0B across Rockdale and Corsicana, sized to contracted rent, in a market the deck itself calls tighter.
forwardwritten 2026-11-04
C22factmedium confidence
Management signed the Corsicana lease on 4 November 2026: 910 MW of critical IT capacity for the whole campus, up from the 756 MW it had described under a non-binding letter of intent (C36).
against this

The lease terms are management's account; the contract has not been filed as an exhibit.

  1. 2026-11-04editedthe letter of intent was converted into a signed lease, so the claim is resolved
historical · October to November 2026written 2026-10-18
What management did with the money

Management sold 9,665 bitcoin in the first half of 2026 to pay for building and repaid a $200M loan in September. It sold no new shares in 2026, but stock awards still lifted the share count 8% in fifteen months.

Insiders in 2026Q3: 5 purchases and 14 sales, from their Form 4 filings.

The evidence under this - 3 claims
C10facthigh confidence
Riot sold 20,264 bitcoin for about $1.5B in the first nine months of 2026 and held 2,418 on 30 September, worth $202.0M; cash was $748.2M, $79.2M of it restricted. It repaid in full and ended the $200M Coinbase facility, releasing all pledged bitcoin.
against this

Bitcoin sales were the main source of funding and little bitcoin is left to sell (2,418 coins), so the next funding must come from project debt or new capital.

  1. 2026-11-04editedQ3 2026 position: most of the bitcoin is sold and the Coinbase loan is repaid
current state · 2026-09-30written 2026-10-18
C11facthigh confidence
Debt principal at 30 September 2026 was $674.5M: $594.4M of 0.75% convertible notes due 2030, $34.3M on the $50M revolver, $20.0M on the $20M revolver, $20.8M drawn on the $573M Rockdale facility, which matures on 31 December 2026, and a $5.0M note. The $200M Coinbase loan was repaid in full in September.
  1. 2026-11-13editedre-sourced to the Q3 10-Q, filed 4 November, which the earnings review had not read
current state · 2026-09-30written 2026-10-18
C13facthigh confidence
Shares outstanding rose from 350.2 million on 1 April 2025 to 375.1 million on 30 September 2026 and were 375.2 million on 2 November. No shares were sold under the at-the-market program in the first nine months of 2026; the increase came from about 8.2 million restricted stock awards and 1.4 million settled stock units, net of tax withholding.
  1. 2026-11-13editedre-sourced to the Q3 10-Q share count
current state · 2026-11-02written 2026-10-18
05

The price, and where we disagree

In short. Fair: about $6.5B is a fraction of the contracted rent, but pays for the leases being built and financed, which has not happened yet.

Share price
$17.83
close,
Company value for each $1 of sales
9.6
rivals' middle 14.0 · its 6-year normal 8.0

The shares fell 40% in three weeks to $13.72 on 16 October with no news from Riot, then rose to $17.83 by 12 November after the Corsicana lease and Q3 results of 4 November.

The test now is financing: the $573M Rockdale loan falls due on 31 December with $20.8M drawn at the end of September, and the long-term lenders and the AMD loan were not yet announced as closed.

The evidence under this - 6 claims
C11facthigh confidence
Debt principal at 30 September 2026 was $674.5M: $594.4M of 0.75% convertible notes due 2030, $34.3M on the $50M revolver, $20.0M on the $20M revolver, $20.8M drawn on the $573M Rockdale facility, which matures on 31 December 2026, and a $5.0M note. The $200M Coinbase loan was repaid in full in September.
  1. 2026-11-13editedre-sourced to the Q3 10-Q, filed 4 November, which the earnings review had not read
current state · 2026-09-30written 2026-10-18
C17facthigh confidence
To start the 191 MW build Riot took a $573.0M delayed-draw loan from lenders led by Morgan Stanley, secured only on the project and not on Riot, at SOFR plus 2.75%. The 8-K says it matures on 31 December 2026; the 10-Q filed four days earlier said 15 October 2026, subject to extension on refinancing.
against this

The lender has no claim on Riot itself, so a failed takeout would cost the project rather than the parent.

current state · 2026-08-14written 2026-10-18
C24facthigh confidence
The shares closed at $17.83 on 12 November 2026, up from $13.72 on 16 October and $14.02 on 3 November, and about 10% above a year earlier; the market value was $6.69B.
  1. 2026-11-04editedre-struck at the 3 November close
  2. 2026-11-13editedre-struck at the 12 November close
historical · 2025-11 to 2026-11-12written 2026-10-18
C25facthigh confidence
From 25 September to 16 October 2026 Riot fell 40%, MARA 40%, CleanSpark 40%, Cipher 49%, IREN 39%, Applied Digital 31%, Hut 8 30%, TeraWulf 26% and Core Scientific 22%, while bitcoin fell about 4% and the Nasdaq-100 fund about 5%. Riot filed no results or lease news in that time.
historical · 2026-09-25 to 2026-10-16written 2026-10-18
C36factmedium confidence
On 4 November 2026 Riot announced a 15-year triple-net powered land lease with a frontier AI lab for the whole Corsicana campus, 910 MW of critical IT capacity: about $28B of rent over the initial term, $1.8B a year on average at a 99% margin, delivered in three phases (400 MW in September 2027, 200 MW in January 2028, 310 MW in July 2028). Riot builds the land, power and powered pads for about $6M per megawatt, $5.5B in all, of which $4M a megawatt is reimbursed to the tenant for its modules after each phase delivers and pays rent; the tenant owns and runs the computers and pays power as a pass-through.
against this
  • The release does not name the tenant, and the lease itself is not yet filed; the tenant may be the same unnamed lab as at Rockdale, which would concentrate rent further (C19).
  • The 99% margin and 33% yield are management's estimates before financing costs; the $3.64B tenant reimbursement is to come from project debt that has not been arranged, or through rent credits at an implied 12% a year.
current state · 2026-11-04written 2026-11-04
C38management claimmedium confidence
At the Q3 2026 results Riot's financing was still unfinished: the $573M Morgan Stanley interim facility 'remains in place' while a high investment-grade credit backstop for Rockdale is finalised, the $180M AMD term loan is described as closed or expected to close shortly, and Corsicana financing is to launch in 2027. Riot says credit-led spreads have widened since September and lenders are more selective. It sold 20,264 bitcoin for about $1.5B in the first nine months and ended September with $950.2M of cash and bitcoin ($748.2M cash including $79.2M restricted, and 2,418 bitcoin worth $202.0M), no equity raised in 2026, and says none is currently anticipated for announced projects.
against this
  • Management planned the AMD term loan for the end of Q3 and the Rockdale takeout 'near term' on the Q2 call (C18, C34); neither has been announced as closed, and the deck's cumulative sources chart shows $0.8B to $1.5B of Riot cash equity needed against about $1.2B of near-term liquidity.
  • The deck's illustrative project debt is $6.1B to $7.0B across Rockdale and Corsicana, sized to contracted rent, in a market the deck itself calls tighter.
forwardwritten 2026-11-04
The betSpeculation
If it works
7.1×
from today's value, valued like its peers
If it fails
keep 68%
of today's market value: the rest of the company, less its debt
How we value it

No fair value: the analysts' forecasts show no lasting operating profit after stock pay, so a value built on earnings would rest on a guess; the bet prices it instead.

How we read the multiple

A buyer gets a mining business that loses money after depreciation, an engineering arm, about 11,380 bitcoin at June's count and two signed leases. The leases do the work in the valuation.

  1. Management expects the three leases to earn about $2.2B a year of rent profit by mid-2028.
  2. The company is valued at about $6.5B today, debt and cash included.
  3. That is a low multiple of the rent profit, before $7.7-7.9B of building costs.
  4. Most of that building is to be borrowed, so new debt will sit ahead of shareholders.

Against its own history. Below what buyers usually pay for each dollar of its sales, because the price fell while sales grew; the market pays less than before for mining.

The evidence under this - 5 claims
C26inferencemedium confidence
At $17.83 the company is valued at about $6.5B including debt, cash and investments, against average yearly net operating income management expects of about $2.2B once all 1,151 MW of signed leases are in service by July 2028: $1.8B from Corsicana, $361-406M from the Rockdale lab lease and $50M from AMD. Building them costs $7.7-7.9B, with $6.1-7.0B of non-recourse project debt illustrated, so debt service stands ahead of shareholders for most of it.
against this
  • Average NOI is before the cost of the debt that builds the leases and over the full 10- to 20-year terms, with early years earning less.
  • The mining, engineering and bitcoin that the price also buys are outside that NOI (C33).
  1. 2026-11-04editedre-struck at the 3 November close on the three signed leases
  2. 2026-11-13editedre-struck at the 12 November close on the bridged company value
current state · 2026-11-12written 2026-10-18
C16management claimmedium confidence
Management expects the two leases to bring about $520M of revenue a year on average, $63.6M from AMD's 50 MW and $457M from the lab, and $416-462M of yearly operating income at an 80% to 90% margin. Building them costs $2.3-2.5B, $11-12M per megawatt for the lab hall.
against this
  • The margin is an estimate: the only rent billed so far is $4.9M in Q2 on AMD's first 25 MW (C03), at an 84% lease gross margin by management's account.
  • The averages include yearly rent escalators over the full terms, so early years earn less.
forwardwritten 2026-10-18
C36factmedium confidence
On 4 November 2026 Riot announced a 15-year triple-net powered land lease with a frontier AI lab for the whole Corsicana campus, 910 MW of critical IT capacity: about $28B of rent over the initial term, $1.8B a year on average at a 99% margin, delivered in three phases (400 MW in September 2027, 200 MW in January 2028, 310 MW in July 2028). Riot builds the land, power and powered pads for about $6M per megawatt, $5.5B in all, of which $4M a megawatt is reimbursed to the tenant for its modules after each phase delivers and pays rent; the tenant owns and runs the computers and pays power as a pass-through.
against this
  • The release does not name the tenant, and the lease itself is not yet filed; the tenant may be the same unnamed lab as at Rockdale, which would concentrate rent further (C19).
  • The 99% margin and 33% yield are management's estimates before financing costs; the $3.64B tenant reimbursement is to come from project debt that has not been arranged, or through rent credits at an implied 12% a year.
current state · 2026-11-04written 2026-11-04
C27facthigh confidence
On company value to trailing sales Riot's filed cohort runs from CleanSpark and MARA, the two pure miners, at the bottom to TeraWulf at the top; Riot sits third of nine, below the converted landlords Cipher, Hut 8, IREN and Core Scientific.
current state · 2026-10-18written 2026-10-18
C18management claimmedium confidence
Management plans to replace the bridge with long-term debt once a high investment-grade backstop is finalised, borrowing 80% to 90% of cost, and the Q3 deck still shows that backstop as being finalised with the $573M interim facility in place; the $180M AMD term loan is 'finalizing' with SOFR plus 250 basis points targeted (C38).
against this
  • No takeout or AMD loan closing had been announced by 4 November 2026.
  • Management declined to name the backstop provider or terms (C34), and the deck says lenders are more selective.
  1. 2026-11-04editedstatus at the Q3 results: neither the takeout nor the AMD loan was announced as closed
forwardwritten 2026-10-18
Priced against its rivals

The competitors its own annual report names, each confirmed against the rival's filing. Measured on company value for each $1 of sales, cheapest first:

TickerCompanycompany value for each $1 of sales
CLSKCleanSpark3.9×
MARAMARA Holdings4.6×
RIOTRiot Platforms9.6×
APLDApplied Digital12.7×
CORZCore Scientific13.9×
HUTHut 814.1×
IRENIREN Limited21.5×
CIFRCipher Mining56.4×
WULFTeraWulf60.3×

The middle of the other 8 is 14.0. Riot Platforms, Inc. is 3rd cheapest of 9.

Rivals' figures come from a data provider, so read the spread of the group rather than any single pair.

Priced between the pure miners and the converted landlords, which is where a miner with leases signed but not yet paying belongs; the whole group fell together.

The bet: what it pays if it works

The bet is the data-centre business. If all three signed leases are built and financed, it could be worth several times what today's price pays for the whole company, and more if AMD's options follow.

If the large leases fail, shareholders keep AMD's halls, the mining business, the engineering arm and the bitcoin, which on miners' prices is a large part of today's value.

Data Center revenue in two to three yearsMegawatts of critical IT capacity leased neededValued like its peersLike the cheapest
$63.60Mabout 29 at 100% kept0.8×0.7×
$2.32B (the big win)about 1.1K at 100% kept7.1×2.5×

To pay 2× (a Fair bet) it would need about $482.66M of Data Center revenue (about 223 megawatts of critical IT capacity leased); to pay 5× (a Cheap bet), about $1.57B of Data Center revenue (about 727 megawatts of critical IT capacity leased), at the same multiple.

Each row is Data Center alone, plus the rest of the company (Bitcoin Mining and Engineering) counted at about $3.40B.

The steps it has to take

  • Done AMD's first 25 MW delivered
  • Done 191 MW lease signed with a frontier AI lab
  • Slipped $180M term loan on AMD's first 25 MW closed due 2026-12
  • In progress Long-term financing replaces the $573M bridge due 2026-12
  • In progress AMD's second 25 MW delivered due 2027-05
  • Done Corsicana letter of intent turned into a lease
  • In progress First 96 MW delivered to the frontier lab due 2027-12
  • Not started All 191 MW delivered and the 20-year term begins due 2028-06
The detail behind the label
Rating
Cheap
the big win's payoff against the 2× and 5× lines
Valued like the cheapest
2.5×
the same success, the lowest comparison
The option
19.3×
what Data Center is worth if it works, against what the price pays for it
The evidence under this - 8 claims
C14facthigh confidence
AMD leased 25 MW at Rockdale in January 2026 for 10 years with three five-year extensions; it was delivered in January and May, on time and on budget per the company. In April AMD took 25 MW more, due 10 MW in November 2026 and 15 MW in May 2027, and holds options on 50 MW plus a conditional right to 100 MW. AMD pays power at cost and reimburses fit-out plus a margin.
current state · 2026-06-30written 2026-10-18
C15facthigh confidence
In August 2026 Riot signed a lease with a frontier AI lab for 191 MW of critical IT capacity at Rockdale, a Tier 3 build-to-suit: 96 MW due December 2027 and the rest June 2028. The 20-year term starts at full delivery and carries two five-year renewals and about $9.1B of base rent. With AMD, 241 MW is leased.
against this
  • The lease is described in the 10-Q and an 8-K item, but the contract itself has not been filed as an exhibit.
  • No rent is paid until the first hall is delivered in December 2027.
current state · 2026-08-10written 2026-10-18
C16management claimmedium confidence
Management expects the two leases to bring about $520M of revenue a year on average, $63.6M from AMD's 50 MW and $457M from the lab, and $416-462M of yearly operating income at an 80% to 90% margin. Building them costs $2.3-2.5B, $11-12M per megawatt for the lab hall.
against this
  • The margin is an estimate: the only rent billed so far is $4.9M in Q2 on AMD's first 25 MW (C03), at an 84% lease gross margin by management's account.
  • The averages include yearly rent escalators over the full terms, so early years earn less.
forwardwritten 2026-10-18
C36factmedium confidence
On 4 November 2026 Riot announced a 15-year triple-net powered land lease with a frontier AI lab for the whole Corsicana campus, 910 MW of critical IT capacity: about $28B of rent over the initial term, $1.8B a year on average at a 99% margin, delivered in three phases (400 MW in September 2027, 200 MW in January 2028, 310 MW in July 2028). Riot builds the land, power and powered pads for about $6M per megawatt, $5.5B in all, of which $4M a megawatt is reimbursed to the tenant for its modules after each phase delivers and pays rent; the tenant owns and runs the computers and pays power as a pass-through.
against this
  • The release does not name the tenant, and the lease itself is not yet filed; the tenant may be the same unnamed lab as at Rockdale, which would concentrate rent further (C19).
  • The 99% margin and 33% yield are management's estimates before financing costs; the $3.64B tenant reimbursement is to come from project debt that has not been arranged, or through rent credits at an implied 12% a year.
current state · 2026-11-04written 2026-11-04
C33inferencemedium confidence
Mining, engineering and other lines together brought about $600.9M of revenue in the year to September 2026, the business that remains if the data-centre line fails.
against this

Mining revenue moves with hashprice (C09) and may shrink as Rockdale power moves to the lab.

  1. 2026-11-13editedrolled to the year to September from the Q3 10-Q
current state · 2026-09-30written 2026-10-18
C05facthigh confidence
In Q2 2026 Riot mined 1,587 bitcoin worth $71,667 each when mined. Its cost to mine one, before miner depreciation, was $49,912 (69.6% of value); including miner depreciation it was $90,631 (126.5%). A year earlier the figures were $48,992 and $91,244 against a value of $98,800.
historical · Q2 2026written 2026-10-18
C10facthigh confidence
Riot sold 20,264 bitcoin for about $1.5B in the first nine months of 2026 and held 2,418 on 30 September, worth $202.0M; cash was $748.2M, $79.2M of it restricted. It repaid in full and ended the $200M Coinbase facility, releasing all pledged bitcoin.
against this

Bitcoin sales were the main source of funding and little bitcoin is left to sell (2,418 coins), so the next funding must come from project debt or new capital.

  1. 2026-11-04editedQ3 2026 position: most of the bitcoin is sold and the Coinbase loan is repaid
current state · 2026-09-30written 2026-10-18
C17facthigh confidence
To start the 191 MW build Riot took a $573.0M delayed-draw loan from lenders led by Morgan Stanley, secured only on the project and not on Riot, at SOFR plus 2.75%. The 8-K says it matures on 31 December 2026; the 10-Q filed four days earlier said 15 October 2026, subject to extension on refinancing.
against this

The lender has no claim on Riot itself, so a failed takeout would cost the project rather than the parent.

current state · 2026-08-14written 2026-10-18

Where we disagree with the market

The market believes

A miner turning into an AI landlord: 21 of 22 analysts rate it a buy after two big leases.

We believe

The leases are real and nearly cover the price, but the building is not yet financed and mining burns cash meanwhile.

Bulls count the rent. The filings show it starts in December 2027, the large hall runs on a loan due this December, and the bitcoin paying the gap is being sold down. If the long-term lenders sign without new shares, the gap closes and we are too cautious.

What analysts say, and the evidence
Analysts positive
96%
of 23, 1 Nov
Four months earlier
95%
of 21, 1 Jul
The evidence under this - 5 claims
C29facthigh confidence
Analyst ratings were 95.5% positive across 22 analysts on 1 October 2026, against 100% of 20 in February. Short interest was 48.2 million shares, 13.8% of the float, at the 30 September settlement.
current state · 2026-10-01written 2026-10-18
C26inferencemedium confidence
At $17.83 the company is valued at about $6.5B including debt, cash and investments, against average yearly net operating income management expects of about $2.2B once all 1,151 MW of signed leases are in service by July 2028: $1.8B from Corsicana, $361-406M from the Rockdale lab lease and $50M from AMD. Building them costs $7.7-7.9B, with $6.1-7.0B of non-recourse project debt illustrated, so debt service stands ahead of shareholders for most of it.
against this
  • Average NOI is before the cost of the debt that builds the leases and over the full 10- to 20-year terms, with early years earning less.
  • The mining, engineering and bitcoin that the price also buys are outside that NOI (C33).
  1. 2026-11-04editedre-struck at the 3 November close on the three signed leases
  2. 2026-11-13editedre-struck at the 12 November close on the bridged company value
current state · 2026-11-12written 2026-10-18
C17facthigh confidence
To start the 191 MW build Riot took a $573.0M delayed-draw loan from lenders led by Morgan Stanley, secured only on the project and not on Riot, at SOFR plus 2.75%. The 8-K says it matures on 31 December 2026; the 10-Q filed four days earlier said 15 October 2026, subject to extension on refinancing.
against this

The lender has no claim on Riot itself, so a failed takeout would cost the project rather than the parent.

current state · 2026-08-14written 2026-10-18
C18management claimmedium confidence
Management plans to replace the bridge with long-term debt once a high investment-grade backstop is finalised, borrowing 80% to 90% of cost, and the Q3 deck still shows that backstop as being finalised with the $573M interim facility in place; the $180M AMD term loan is 'finalizing' with SOFR plus 250 basis points targeted (C38).
against this
  • No takeout or AMD loan closing had been announced by 4 November 2026.
  • Management declined to name the backstop provider or terms (C34), and the deck says lenders are more selective.
  1. 2026-11-04editedstatus at the Q3 results: neither the takeout nor the AMD loan was announced as closed
forwardwritten 2026-10-18
C10facthigh confidence
Riot sold 20,264 bitcoin for about $1.5B in the first nine months of 2026 and held 2,418 on 30 September, worth $202.0M; cash was $748.2M, $79.2M of it restricted. It repaid in full and ended the $200M Coinbase facility, releasing all pledged bitcoin.
against this

Bitcoin sales were the main source of funding and little bitcoin is left to sell (2,418 coins), so the next funding must come from project debt or new capital.

  1. 2026-11-04editedQ3 2026 position: most of the bitcoin is sold and the Coinbase loan is repaid
current state · 2026-09-30written 2026-10-18
06

What could go wrong, and how we would know

The risks

  • The financing slips. If lenders lend less than planned, Riot must sell more bitcoin or issue shares to fund its part; the deck says lenders are more selective.
  • One tenant. The frontier lab is about 97% of the contracted rent across Rockdale and Corsicana; a delay or dispute with it moves almost the whole case.
  • Delivering two big builds. Riot has delivered one 25 MW hall; it must now deliver 191 MW at Rockdale and 910 MW at Corsicana on dates from September 2027.
  • More shares. Stock awards keep adding shares, and the 2030 notes become about 40 million shares above about $14.86.
  • Bitcoin falls. Mining revenue moves with bitcoin; a lower price means less cash from selling the 2,418 coins left.
  • Rivals with new power. Once Texas hands out new grid capacity from 2028, sites like Riot's become less scarce.
The evidence under this - 9 claims
C17facthigh confidence
To start the 191 MW build Riot took a $573.0M delayed-draw loan from lenders led by Morgan Stanley, secured only on the project and not on Riot, at SOFR plus 2.75%. The 8-K says it matures on 31 December 2026; the 10-Q filed four days earlier said 15 October 2026, subject to extension on refinancing.
against this

The lender has no claim on Riot itself, so a failed takeout would cost the project rather than the parent.

current state · 2026-08-14written 2026-10-18
C18management claimmedium confidence
Management plans to replace the bridge with long-term debt once a high investment-grade backstop is finalised, borrowing 80% to 90% of cost, and the Q3 deck still shows that backstop as being finalised with the $573M interim facility in place; the $180M AMD term loan is 'finalizing' with SOFR plus 250 basis points targeted (C38).
against this
  • No takeout or AMD loan closing had been announced by 4 November 2026.
  • Management declined to name the backstop provider or terms (C34), and the deck says lenders are more selective.
  1. 2026-11-04editedstatus at the Q3 results: neither the takeout nor the AMD loan was announced as closed
forwardwritten 2026-10-18
C15facthigh confidence
In August 2026 Riot signed a lease with a frontier AI lab for 191 MW of critical IT capacity at Rockdale, a Tier 3 build-to-suit: 96 MW due December 2027 and the rest June 2028. The 20-year term starts at full delivery and carries two five-year renewals and about $9.1B of base rent. With AMD, 241 MW is leased.
against this
  • The lease is described in the 10-Q and an 8-K item, but the contract itself has not been filed as an exhibit.
  • No rent is paid until the first hall is delivered in December 2027.
current state · 2026-08-10written 2026-10-18
C36factmedium confidence
On 4 November 2026 Riot announced a 15-year triple-net powered land lease with a frontier AI lab for the whole Corsicana campus, 910 MW of critical IT capacity: about $28B of rent over the initial term, $1.8B a year on average at a 99% margin, delivered in three phases (400 MW in September 2027, 200 MW in January 2028, 310 MW in July 2028). Riot builds the land, power and powered pads for about $6M per megawatt, $5.5B in all, of which $4M a megawatt is reimbursed to the tenant for its modules after each phase delivers and pays rent; the tenant owns and runs the computers and pays power as a pass-through.
against this
  • The release does not name the tenant, and the lease itself is not yet filed; the tenant may be the same unnamed lab as at Rockdale, which would concentrate rent further (C19).
  • The 99% margin and 33% yield are management's estimates before financing costs; the $3.64B tenant reimbursement is to come from project debt that has not been arranged, or through rent credits at an implied 12% a year.
current state · 2026-11-04written 2026-11-04
C19factmedium confidence
Bloomberg reported, and ForkLog repeated, that the frontier AI lab behind the 191 MW lease is Anthropic; Riot has not named its tenant.
against this

Riot's own filings say only a leading frontier AI lab; the name rests on unnamed sources in the press.

current state · 2026-08-11written 2026-10-18
C12facthigh confidence
The 2030 notes convert at 67.2767 shares per $1,000, about $14.86 a share, so $594.4M would become about 40.0 million shares. Holders could convert during Q3 2026 because the stock traded above 130% of that price, and Riot intends to settle any conversion in shares.
against this

The shares closed at $17.83 on 12 November, about 20% above the conversion price, so the notes are now worth more as shares and the dilution is closer.

  1. 2026-11-13editedthe 12 November close sits above the conversion price, so the counter-evidence no longer holds
current state · 2026-06-30written 2026-10-18
C13facthigh confidence
Shares outstanding rose from 350.2 million on 1 April 2025 to 375.1 million on 30 September 2026 and were 375.2 million on 2 November. No shares were sold under the at-the-market program in the first nine months of 2026; the increase came from about 8.2 million restricted stock awards and 1.4 million settled stock units, net of tax withholding.
  1. 2026-11-13editedre-sourced to the Q3 10-Q share count
current state · 2026-11-02written 2026-10-18
C38management claimmedium confidence
At the Q3 2026 results Riot's financing was still unfinished: the $573M Morgan Stanley interim facility 'remains in place' while a high investment-grade credit backstop for Rockdale is finalised, the $180M AMD term loan is described as closed or expected to close shortly, and Corsicana financing is to launch in 2027. Riot says credit-led spreads have widened since September and lenders are more selective. It sold 20,264 bitcoin for about $1.5B in the first nine months and ended September with $950.2M of cash and bitcoin ($748.2M cash including $79.2M restricted, and 2,418 bitcoin worth $202.0M), no equity raised in 2026, and says none is currently anticipated for announced projects.
against this
  • Management planned the AMD term loan for the end of Q3 and the Rockdale takeout 'near term' on the Q2 call (C18, C34); neither has been announced as closed, and the deck's cumulative sources chart shows $0.8B to $1.5B of Riot cash equity needed against about $1.2B of near-term liquidity.
  • The deck's illustrative project debt is $6.1B to $7.0B across Rockdale and Corsicana, sized to contracted rent, in a market the deck itself calls tighter.
forwardwritten 2026-11-04
C28facthigh confidence
Rival filings describe the same product: Cipher says several miners, naming Hut 8, IREN, TeraWulf, Core Scientific and Applied Digital, have signed leases with hyperscalers and HPC tenants; TeraWulf calls itself an owner of HPC infrastructure on reused industrial sites; Applied Digital builds about 150 MW campuses in 14 to 18 months for investment-grade hyperscalers.
current state · 2026-07-29written 2026-10-18
What we still do not know
  • Who backs the 191 MW project's long-term debt, and on what terms?
  • Whether the Corsicana project debt of billions is raised on the terms Riot shows, or the tenant funds it through rent credits at about 12% a year.
  • Whether the Corsicana tenant is the same lab as at Rockdale.
  • Whether any 2030 notes were converted into shares during Q3 2026.
The evidence under this - 5 claims
C18management claimmedium confidence
Management plans to replace the bridge with long-term debt once a high investment-grade backstop is finalised, borrowing 80% to 90% of cost, and the Q3 deck still shows that backstop as being finalised with the $573M interim facility in place; the $180M AMD term loan is 'finalizing' with SOFR plus 250 basis points targeted (C38).
against this
  • No takeout or AMD loan closing had been announced by 4 November 2026.
  • Management declined to name the backstop provider or terms (C34), and the deck says lenders are more selective.
  1. 2026-11-04editedstatus at the Q3 results: neither the takeout nor the AMD loan was announced as closed
forwardwritten 2026-10-18
C38management claimmedium confidence
At the Q3 2026 results Riot's financing was still unfinished: the $573M Morgan Stanley interim facility 'remains in place' while a high investment-grade credit backstop for Rockdale is finalised, the $180M AMD term loan is described as closed or expected to close shortly, and Corsicana financing is to launch in 2027. Riot says credit-led spreads have widened since September and lenders are more selective. It sold 20,264 bitcoin for about $1.5B in the first nine months and ended September with $950.2M of cash and bitcoin ($748.2M cash including $79.2M restricted, and 2,418 bitcoin worth $202.0M), no equity raised in 2026, and says none is currently anticipated for announced projects.
against this
  • Management planned the AMD term loan for the end of Q3 and the Rockdale takeout 'near term' on the Q2 call (C18, C34); neither has been announced as closed, and the deck's cumulative sources chart shows $0.8B to $1.5B of Riot cash equity needed against about $1.2B of near-term liquidity.
  • The deck's illustrative project debt is $6.1B to $7.0B across Rockdale and Corsicana, sized to contracted rent, in a market the deck itself calls tighter.
forwardwritten 2026-11-04
C36factmedium confidence
On 4 November 2026 Riot announced a 15-year triple-net powered land lease with a frontier AI lab for the whole Corsicana campus, 910 MW of critical IT capacity: about $28B of rent over the initial term, $1.8B a year on average at a 99% margin, delivered in three phases (400 MW in September 2027, 200 MW in January 2028, 310 MW in July 2028). Riot builds the land, power and powered pads for about $6M per megawatt, $5.5B in all, of which $4M a megawatt is reimbursed to the tenant for its modules after each phase delivers and pays rent; the tenant owns and runs the computers and pays power as a pass-through.
against this
  • The release does not name the tenant, and the lease itself is not yet filed; the tenant may be the same unnamed lab as at Rockdale, which would concentrate rent further (C19).
  • The 99% margin and 33% yield are management's estimates before financing costs; the $3.64B tenant reimbursement is to come from project debt that has not been arranged, or through rent credits at an implied 12% a year.
current state · 2026-11-04written 2026-11-04
C12facthigh confidence
The 2030 notes convert at 67.2767 shares per $1,000, about $14.86 a share, so $594.4M would become about 40.0 million shares. Holders could convert during Q3 2026 because the stock traded above 130% of that price, and Riot intends to settle any conversion in shares.
against this

The shares closed at $17.83 on 12 November, about 20% above the conversion price, so the notes are now worth more as shares and the dilution is closer.

  1. 2026-11-13editedthe 12 November close sits above the conversion price, so the counter-evidence no longer holds
current state · 2026-06-30written 2026-10-18
C19factmedium confidence
Bloomberg reported, and ForkLog repeated, that the frontier AI lab behind the 191 MW lease is Anthropic; Riot has not named its tenant.
against this

Riot's own filings say only a leading frontier AI lab; the name rests on unnamed sources in the press.

current state · 2026-08-11written 2026-10-18

What would change our view

  1. Neutral→AttractiveThe Rockdale build is financed

    It needs:

    • ○Long-term loans cover at least 80% of the 191 MW build, with no new shares sold.watched as it happens
  2. Neutral→AttractiveA price at which mining alone is paid for

    It needs:

    • ○The company's value falls to 5 times its yearly sales, about where pure miners trade.checked daily
We would also be wrong if
  • The bridge loan is repaid with new shares or extended past mid-2027.
  • The first 400 MW at Corsicana is not delivered by March 2028.
  • Shares outstanding pass 430 million before the lab's hall opens.

What is coming

  • 31 December 2026 Bridge loan maturity: Whether long-term financing for the 191 MW project is in place.
Every dated event ahead
  • 31 December 2026 Bridge loan maturity: Whether long-term financing for the 191 MW project is in place.
  • 31 May 2027 AMD's second 25 MW delivered: Whether Riot keeps delivering halls on time.
  • 31 December 2027 First 96 MW delivered to the frontier lab: Whether the Tier 3 hall is built on time and rent begins.
Since we wrote this
Written
18 Oct
Price the thesis read
$17.83
12 Nov
  • 13 NovPrice movePrice claims re-struck at $17.83; Neutral holdsThe shares rose 27% from the 3 November strike after the Corsicana lease. The 10-Q shows the Rockdale loan still due 31 December with no long-term lender named, so the view holds.
  • 4 NovEarningsRiot signed all of Corsicana, 910 MW; the build is still unfinancedThe $28B lease half-fires the route to Attractive; the Rockdale bridge is not refinanced and lenders are more selective, so the view holds.
  • 4 NovBet moveBet re-struck: Asymmetric to SpeculationRe-priced at the 3 November close.
  • 4 NovBet moveBet re-struck: Fair bet to Cheap betRe-priced at the 3 November close.
  • 3 NovBet moveBet re-struck: Speculation to AsymmetricRe-priced at the 2 November close.
  • 28 OctBet moveBet re-struck: Asymmetric to SpeculationRe-priced at the 27 October close.
  • 26 OctBet moveBet re-struck: Speculation to AsymmetricRe-priced at the 23 October close.
  • 18 OctThesis writtenNeutral, medium convictionWritten eleven days before Q3 results, after the shares fell 40% in three weeks with the whole group while bitcoin barely moved.

Also checked 1 time with nothing new to act on.

Sources 26

Where this came from

Sources - 26

Every claim above cites one of these, or states the reasoning that derived it. The quote is frozen at the date it was read: a link can rot, and an agent fetch returns a reading of a page rather than the page. Backs counts the whole claim ledger, so it can name a claim this page does not surface.

  1. S01primarycompany filing2026-03-02
    the business, competition classes, power contracts, convertible notes and risk factors
    backsC01C02C07C12
  2. S02primarycompany release2026-03-02
    2025 revenue by segment and the net loss
    backsC02
  3. S03primarycompany filing2026-08-10
    segments, cost to mine, power credits, bitcoin held and sold, debt, shares, both leases and the bridge loan
    backsC01C03C04C05C06C07C08C09C10C12C14C15C17C23
  4. S04primarycompany release2026-08-10
    the quarter's results, the lab lease terms and liquidity
    backsC03C10C14C15
  5. S05primarycompany release2026-08-10
    lease revenue, operating income and capital cost per lease, hashprice by quarter and the financing plan
    backsC08C16C18
  6. S06primarytranscript2026-08-10
    Riot Platforms Q2 2026 earnings call transcript (FMP), held 10 August 2026
    the Corsicana letter of intent, the financing plan, the batch-process remark and the backlog
    the entire Corsicana campus is now under a nonbinding LOI to a single tenant
    backsC10C34C15C16C18C21C22C23
  7. S07primarycompany filing2026-08-14
    the bridge loan's size, security, rate and maturity
    backsC17
  8. S08primarycompany filing2026-09-25
    the $200M bitcoin-backed loan repaid in full
    backsC11
  9. S09primarycompany filing2026-04-30
    insider ownership, the say-on-pay vote and the bonus and long-term award design
    backsC13C30C31
  10. S10primaryvendor data2026-10-16
    Research pack for RIOT (FMP market tier, FINRA short interest, filed cohort), fetched 18 October 2026
    the 16 October close, market and company value, the price move split, ratings, short interest, the filed cohort and the earnings date
    backsC24C26C27C29C32
  11. S11primaryregulator2026-07-29
    large-load requests by status and year, energized load and the Batch Zero milestones
    ERCOT is tracking approximately 474 GW of Large Loads seeking interconnection, of which ~90% are data centers.
    backsC20C21
  12. S12primaryregulator2026-06-18
    the batch process for loads of 75 MW or more and the 438 GW of requests in June
    ensuring large electricity users like data centers only connect in quantities and locations the Texas grid can reliably support
    backsC20C21
  13. S13secondarynews2026-08-11
    the press identification of the frontier lab
    According to Bloomberg , the partner is Anthropic.
    backsC19
  14. S14primarycompany filing2026-02-27
    a converted miner describing itself as an HPC infrastructure owner on reused industrial sites
    backsC28
  15. S15primarycompany filing2026-02-24
    the miners named as having signed leases with hyperscalers and HPC tenants
    backsC28
  16. S16primarycompany filing2026-07-29
    a rival building about 150 MW AI campuses for investment-grade hyperscalers
    backsC28
  17. S17primaryvendor data2026-10-17
    FMP daily bitcoin prices (BTCUSD), 25 June to 17 October 2026
    bitcoin's close on 17 October and its path since June
    backsC09C25
  18. S18primaryindustry data2026-10-18
    the network's average hash rate over the last 30 days
    {"hashrates":[{"timestamp":1784419200,"avgHashrate":1.036719851877133e+21}
    backsC09
  19. S19primarycompany filing2026-08-14
    Form 4 filings by Riot insiders, read for the Rule 10b5-1 flag (scripts/insider_fetch.py)
    nine open-market sales, all under pre-arranged plans
    backsC30
  20. S20primaryvendor data2026-10-16
    FMP daily closes for Riot, its filed peers, CoreWeave and the Nasdaq-100 fund, 25 September to 16 October 2026
    each name's fall over the three weeks
    backsC25
  21. S21primarycompany filing2025-11-19
    a rival maker of switchgear and power control rooms
    backsC35
  22. S22primarycompany filing2026-11-04
    the Corsicana lease terms, Q3 revenue by segment, bitcoin produced and sold, cash and bitcoin at 30 September, no equity raised in 2026
    backsC10C22C32C36C37C38
  23. S23primarycompany filing2026-11-04
    financing status of the Rockdale bridge and the AMD term loan, the Corsicana funding paths, project capital and portfolio net operating income
    backsC18C26C36C37C38
  24. S24tertiaryvendor data2026-11-04
    FMP daily closes for RIOT to 3 November 2026
    the 3 November 2026 close of $14.02 and the vendor company value of $5.07B
    read, but no claim rests on it
  25. S25primarycompany filing2026-11-04
    debt principal by facility at 30 September, the $573M facility's December 2026 maturity and $20.8M drawn, shares outstanding at 30 September and 2 November, nine-month segment revenue, Engineering contract liabilities
    backsC11C13C26C33
  26. S26secondaryvendor data2026-11-13
    the 12 November close of $17.83, market value $6.69B, company value $6.51B after adding $202M of long-term investments to the vendor's $6.71B, trailing revenue $675.7M
    backsC24C26C33
Rendered from content/RIOT/thesis.json · thesis reviewed 2026-11-13. This page explains a company; it does not say what to pay, when to buy or how much.