The company · 1 · Who is this company?

Bitdeer is a bitcoin miner turning to AI

243,000 rigs

of its own design, mining bitcoin

Cheap power

in Norway, Texas and beyond

AI halls

rented to AI firms

Bitdeer competes for bitcoin's reward with machines of its own design. It now rents a powered hall at Tydal in Norway to an AI firm, and its own NVIDIA systems in Malaysia.

The company · 2 · What exactly does it sell?

Mining its own bitcoin is three quarters

Each $1 of sales, second quarter of 2026
74%11%7%6%2%0%
Mining its own bitcoinMining with partnersHosting others' rigsAI computingRenting mining powerSelling rigs

AI computing is still a small slice; the case rests on it growing.

The company · 3 · How does it make money?

Paid in bitcoin now, in AI rent later

$320.7Msales last quarter
$125.5Mloss after rig wear and interest
$163.7Mcash, from $456.8M

Mining pays whatever bitcoin is worth. Each step toward AI is paid for with new shares.

Is it a good business? · 4 · What gives it an edge?

Low-cost power, and power already connected

SEALMINER

its own chip and rig, so no rig maker's profit to pay

$44

average power cost per megawatt-hour

8.7%

of the world's mining it runs

In mining there is no customer to keep: every new rival rig shrinks Bitdeer's share.

Is it a good business? · 5 · What is the catch?

Rivals got to AI tenants first

TeraWulf, Cipherleases guaranteed by Google
Core Scientificalready bills CoreWeave
Almost 60%of big clouds' data-centre space they build themselves

Listed rivals: WULF · CIFR · CORZ · MSFT · AMZN · GOOGL · META · IREN

Other miners such as MARA and IREN chase the same switch.

Is it a good business? · 6 · What does its record show?

Less kept per $1 as research and building rose

Per $121% → 10%kept per $1 after making it, 2023 to 2025
Research8% → 25%chip research per $1
Building17% → 37%site building per $1

Power and fast-wearing rigs outran revenue, and what each sale kept then fell below zero.

Is it a good business? · 7 · How much room is there to grow?

Data-centre space is scarce in North America

7,481 MWunder construction, first half of 2026
80.4%already spoken for
Under 1,500megawatts left to lease

Nobody publishes leasable space for Norway or rural Texas, where Bitdeer's halls are.

Is it a good business? · 8 · Who is in charge?

A Bitmain co-founder chairs and runs it

19.5%of the shares Jihan Wu owns
$633Mowed to a lending group the chairman controls
69.5%of the votes, through shares carrying ten votes each

Wu has chaired it since 2021 and run it since 2024.

The story right now · 9 · Why are miners renting halls to AI?

Powered halls are what AI firms lack

Under 1,500megawatts left to lease
Googleguarantees rivals' leases
31 DecemberBitdeer's lease starts

AI firms need buildings with large power connections now. Bitcoin miners already have them, so several have re-let halls to AI tenants.

The story right now · 10 · Why does a bank guarantee matter?

Rent is only as safe as who promises it

  1. A lease is signedWith a young AI firm.
  2. A bank guarantees rentExpected, not signed.
  3. Bitdeer borrows to build$250M to $350M.
  4. Tenant may leaveAt year ten.

Rivals' leases are guaranteed by Google. Bitdeer's rests on a bank guarantee that is still only expected.

The story right now · 11 · What changed lately?

Record sales, but shares sold and cash halved

$320.7Msales, up 40% on the quarter
$125.5Mloss after rig wear and interest
$58.0Mof new shares sold

Mixed quarter

The lease's first phase is due on 31 December. The bank guarantee is expected but not signed, and the project loan is still not closed.

The story right now · 12 · What is everyone arguing about?

Is the lease worth much per share?

Many investors think

A power estate that can be re-let to AI

We think

The lease is real; its value per share is not

Against us: two officers bought shares in August, and rivals show such leases can be done.

The price and our view · 13 · What is a share worth?

No single value here: it is priced as a bet

3.7×if it works
up to 100%kept if it fails

Multiples of the company's value when the bet was last struck, 16 Nov 2026.

We put no single value on a share here, because the business does not yet earn a lasting profit. Instead we ask what the shares pay if the plan works, and what is left if it fails.

The price and our view · 14 · How could we be wrong?

The guarantee, more shares and the lender

The guarantee never arrivesBiggest

The lease rests on it.

More shares to comeShowing now

Each step sells shares.

The chairman is the lenderWatch

Conflicts on terms.

Whether the rent is highUnknown

No rival discloses its rent.

Bitcoin still pays the bills, and Norway's politics can change the power terms.

The price and our view · 15 · How will we know?

March shows whether the funding arrived

The $1.3B bank guarantee signedWe turn neutral
A second large AI lease, bank-backedWe turn positive
More shares sold to fund the buildBad sign
MAR 202715

Fourth-quarter 2026 results, 15 March. Companies report every three months; each report is a test of the story.

Our view moves on these business events, not on a price line, since we put no single value on a share here.

The price and our view · 16 · So, what do we think?

A bitcoin miner renting halls to AI, paid for in shares

Speculationthe kind of bet this is

UnattractiveMedium conviction

Bitdeer mines bitcoin on cheap power and is renting the same halls to AI firms, with one lease signed. Each step is paid with new shares, and the chairman is the largest lender. Unattractive.