Keel owns land with utility agreements for 350 megawatts at Panther Creek, 110 at Sharon and 18 at Moses Lake. It plans to build data halls there and rent them to AI companies for about 15 years.
The company · 2 · What exactly does it sell?
Today's sales are still mostly mining
Each $1 of sales, second quarter of 2026
85%8%7%1%0%
Bitcoin miningSelling powerElectrical servicesHosting minersRenting to AI firms
Renting to AI companies, the whole plan, has brought in nothing yet.
The company · 3 · How does it make money?
Rent for powered halls, if a tenant signs
478 MWagreed power, no tenant
About $780Mcash after selling its bitcoin
$4.1B to $4.9Bestimated cost to build its halls, still unfunded
Keel would build halls and collect rent for years, but every dollar of building is spent before any rent arrives.
Is it a good business? · 4 · What gives it an edge?
What Keel has is a power date
End of 2027
most Pennsylvania power due
6.8 GW
short of the local grid's 2028 needs
A tenant wanting power soon has few places to go, but no tenant has agreed a price yet, so whether that means a high rent is unknown.
Is it a good business? · 5 · What is the catch?
Other former miners signed tenants first
TeraWulf, Cipherrent guaranteed by Google
Core Scientificrents hundreds of MW to CoreWeave
Almost 60%of capacity the biggest buyers build themselves
That share is Synergy Research's count of hyperscale capacity built and owned by the buyers.
Is it a good business? · 6 · What does its record show?
Mining revenue is being wound down
Sales, $M
120.4
133.3
229.3
Dec 2023Dec 2024Dec 2025
Sales$120M → $229Mrevenue, 2023 to 2025
Profit−65%operating loss per $1, 2025
Cash−$327Mcash after spending, 2025
The real cost of growth is per megawatt, all spent before any rent arrives.
Is it a good business? · 7 · How much room is there to grow?
The market is large and short of supply
1.4%of space empty in main markets
62 GWrented capacity a broker expects by 2030
1,513 MWmore applied for, not yet agreed
Most of the 2.2 gigawatts in Keel's headline is applications, not agreements.
Is it a good business? · 8 · Who is in charge?
A leasing veteran joined to sign tenants
2024Ben Gagnon became chief executive
Under 2%owned by insiders
Ganesh Aiyerpresident since July, from Digital Realty
The new president comes from leasing at Digital Realty, a large data-centre landlord.
The story right now · 9 · Why do AI firms want old mines?
AI needs powered buildings, and miners have power
1.4%space empty in main markets
Googlebacks rivals' leases
3 leasespromised by end of 2026
AI companies need buildings with big power connections now. Former bitcoin miners already hold such connections, so many are converting their sites.
The story right now · 10 · Why is an unsigned lease risky?
Building costs come years before rent
Power agreed478 MW.
Building beginsMoses Lake, September.
Costs paid up frontBillions unfunded.
Rent only after a tenantNone signed.
Debt raised to build ranks ahead of the shares, so if tenants come late, owners carry the loss first.
The story right now · 11 · What changed lately?
No lease, building begun, overheads doubled
$34Moverheads a quarter, doubled
$220M → $380Mpromised equipment purchases
About $780Mcash after selling all its bitcoin
32.8%share fall, 1 to 16 October
Mixed quarter
Management says talks are advanced at three sites, but no longer repeats its promise of three leases by year end.
The story right now · 12 · What is everyone arguing about?
Leases a matter of when, or if?
Many investors think
Scarce power with leases a matter of when
We think
The price already pays for all three sites rented
We are wrong if a strong tenant signs at Panther Creek or Sharon this year.
The price and our view · 13 · What is a share worth?
No single value here: it is priced as a bet
4.6×if it works
up to 29%kept if it fails
Multiples of the company's value when the bet was last struck, 6 Nov 2026.
We put no single value on a share here, because the business does not yet earn a lasting profit. Instead we ask what the shares pay if the plan works, and what is left if it fails.
The price and our view · 14 · How could we be wrong?
No tenant has signed yet
No tenant yetBiggest
No lease signed.
Building needs moneyShowing now
Billions unfunded.
Debt ranks firstWatch
Ahead of the shares.
What rent it getsUnknown
No public figure.
Schedules can slip and grid rules may change before any rent is earned.
The price and our view · 15 · How will we know?
March tests whether a lease is signed
A strong tenant signs for 100 MW or moreWe turn neutral
Building funded without new sharesGood sign
Another report with no tenantBad sign
MAR 2027-
Fourth-quarter 2026 results and the annual report, March. Companies report every three months; each report is a test of the story.
Our view moves on these business events, not on a price line, since we put no single value on a share here.
The price and our view · 16 · So, what do we think?
Scarce power, priced for leases nobody has signed
Speculationthe kind of bet this is
UnattractiveMedium conviction
Keel shut its bitcoin mines to rent their power connections to AI companies, and that power is scarce. But no lease is signed, billions of building costs are unfunded and debt ranks ahead of the shares.
↑ ↓ to move · C for contents
What it does
More about the company
Who it is
Keel Infrastructure is what Bitfarms became in April 2026, when it moved from Canada to Delaware. It owns land with signed agreements from electric utilities to deliver power: 350 megawatts at Panther Creek and 110 at Sharon in Pennsylvania, and 18 at Moses Lake in Washington.
It plans to put buildings on that land, fill them with power and cooling, and rent them for about 15 years to big cloud and AI companies, who bring their own computers. It has already bought equipment for Moses Lake.
How it makes money
Today it barely does. The $30.4M of revenue in the June quarter came from bitcoin mining and selling electricity, both being wound down, and the company lost money.
The plan is rent. A tenant pays every month for a share of the power, for 15 years. A rival, Applied Digital, earns about $1.63M a year per megawatt and keeps about 91 cents of each dollar after running costs. Keel has no tenant, so none of that has started.
Growth and profit
What growth costs
Growth here is not paid for out of sales. Sales are shrinking as mining shuts, so office costs and stock pay take a bigger share each quarter. The real cost is building: roughly $10M or more for each megawatt of power, spent before any tenant pays rent.
Its record
The numbers
Is it growing?Fast
Sales grew 72% in the year to Dec 2025, faster than the 11% in the year before.
Is it profitable?Losing
Operating margin is −65%.
Does growth pay off?Unclear
Running costs take 57¢ of each sales dollar, up from 22¢ in the year to Dec 2023.
Does it earn good returns?Poor
Shareholders' money lost 49% a year, down from −17% in the year to Dec 2023.
Is it making cash?Burning
It used up $327M more cash than it brought in, 143% of sales, after spending 44% of sales on buildings and equipment.
Are shares being diluted?Diluting
The share count rose 110% in 2.0 years, and pay in shares costs 6.4% of sales.
Why it wins
The evidence
What Keel has is a date. Its utilities have agreed to deliver most of its Pennsylvania power by the end of 2027. The grid that serves the state, run by PJM, bought 6.8 gigawatts less power than it says it needs for 2028, the second shortfall in a row, and PJM says a new gas plant takes at least four years.
So a tenant wanting power soon has few places to go. Whether that lets Keel charge a high rent is still unknown, because nobody has agreed a rent yet.
Who could beat it
The rivals in full
Other former bitcoin miners got there first. TeraWulf and Cipher signed tenants whose rent Google guarantees; Core Scientific and Galaxy rent hundreds of megawatts to CoreWeave. And the biggest buyers build most of their own buildings: almost 60%, by one research firm's count.
Each rival
Hyperscalers' own-built campuses: Microsoft, Amazon, Google and MetaMSFTAMZNGOOGLMETA
The tenant builds its own campus on its own power and never tenders a lease, which Synergy measures as almost 60% of hyperscale capacity.
Fluidstack's Google-backstopped leases at TeraWulf and CipherWULFCIFR
An AI lab takes its next tranche of capacity from a landlord whose rent Google guarantees, so Keel's negotiation starts against a structure it does not yet have.
Core Scientific and Galaxy, leasing to CoreWeave and AMDCORZGLXY
The GPU cloud signs its 2027 megawatts with converted miners already billing hundreds of megawatts, rather than with one whose first building is unbuilt.
A hyperscaler takes 15-year capacity from a developer with 1,410 MW already leased and a repeatable build at $11M to $13M a megawatt.
How big it could get
The market and who has signed
The market
The market is large and short of supply. In North America's main data-center markets only 1.4% of space sits empty, and 80% of what is being built is spoken for before it opens. One broker expects 62 gigawatts of rented capacity to be added worldwide by 2030.
Keel holds 478 megawatts of it with no tenant, plus applications for 1,513 more that the utilities have not yet agreed.
Who runs it
Leaders, pay and the cash
Who runs it
Ben Gagnon, who ran the old mining business, has been chief executive since 2024, and in July a leasing veteran from Digital Realty joined as president to sign tenants. Insiders own under 2%, though the chief executive bought shares in August. His bonus rides on planning goals, not on signing leases or profit; most of his shares pay out only if the stock keeps up with the wider market.
What they did with the money
It did what was in its control: it left Latin America, repaid its lender, moved to the United States and began building at Moses Lake. In May it said it needed no new money to reach its first leases; a month later it borrowed $458M through notes that can turn into shares.
The last report
The latest report
Keel signed no lease, started building at Moses Lake, and its overheads doubled
What it did to the thesis Mixed quarter
Building at Moses Lake is real progress, but the main gap is unchanged: no tenant has signed. Overheads and equipment promises grew while the three-lease aim went unrepeated, so the view stays Unattractive.
The report
The September-quarter results, published on 5 November 2026, again showed no lease. Management said negotiations are advanced at three sites with several creditworthy parties, and that building began at Moses Lake in September, the first site expected to earn rent in 2027.
Overheads doubled to $34M a quarter, and promised equipment purchases rose to $380M from $220M. It sold all its bitcoin and holds about $780M in cash. Four of Panther Creek and Sharon's environmental permits are still to come.
What's happening now
The background
Because the promise has a deadline that is no longer repeated. Management said in May it would sign three leases by the end of 2026; the November results did not restate it, and year-end is the next dated test.
The shares have already run ahead of a lease twice, rising about fivefold in 2025 and nearly fourfold in 2026, and fell back each time a report came with no tenant. In October they fell another third with no news, as other former miners did. They closed at $2.10 on 4 November.
Where we disagree
Both sides in full
The market
A company with scarce power about to sign leases, so the rent is a matter of when, not whether.
We believe
The power is scarce and real, but the price already pays for all three sites rented and financed.
The argument
Most of the 2.2 gigawatts in the company's headline is applications, not agreements, and the price is already set as if the 478 megawatts that are agreed were rented out.
We are wrong if a big tenant with strong credit signs at Panther Creek or Sharon this year, and lenders pay for the building without new shares.
What it's worth
How we value it
No fair value: the analysts' forecasts show no lasting operating profit after stock pay, so a value built on earnings would rest on a guess; the bet prices it instead.
The bet
This is a bet that a former miner becomes a landlord to AI companies. If all three sites are rented on terms like its rivals', the business could be worth a few times today's value in two to three years, before counting the new shares the building may need.
If no tenant signs, the cash drains on overheads and equipment, the notes are repaid first, and what is left is land, power agreements and machinery worth at most what the accounts carry them at, a small part of today's price.
The bet
Seen as a bet
This is a bet that a former miner becomes a landlord to AI companies. If all three sites are rented on terms like its rivals', the business could be worth a few times today's value in two to three years, before counting the new shares the building may need.
If no tenant signs, the cash drains on overheads and equipment, the notes are repaid first, and what is left is land, power agreements and machinery worth at most what the accounts carry them at, a small part of today's price.
What could go wrong
Every risk
The risks
No tenant yet
Eighteen months into the plan, no lease is signed, and the three promised for 2026 are no longer promised.
Building needs money
Building costs $4-5B. Lenders want a tenant with strong credit; without one, shareholders must find far more, which means new shares.
Debt ranks first
$1.05B of notes are owed before shareholders get anything; they turn into shares only if the price roughly triples.
Schedules slip
Panther Creek's permits and Moses Lake's opening have both moved later this year.
Grid rules may change
PJM is rewriting how large new users connect while its supply is short, which could change the terms of future power.
What we still do not know
How much computer capacity each site really supports: the company has not said, so our 375 megawatts is an estimate from rivals.
What rent Pennsylvania or Washington power commands: no public figure exists for either state.
Whether PJM's new rules for large users will touch agreements Keel already holds.
When Panther Creek's remaining environmental permits arrive.
What changes our view
Every route to a new view
Every route to a new view
→ Neutral
A tenant with strong credit, or a guarantor, signs for 100 megawatts or more at Panther Creek or Sharon, with rent and length disclosed. The building is paid for with project loans, and no new shares are sold that quarter.
→ Attractive
Leases are signed at all three sites, covering all 478 secured megawatts. Pennsylvania utilities agree to deliver 300 megawatts or more of new power on top.
The next test
It supports the case if
No lease is announced, the three-lease aim is dropped, or Panther Creek's permits slip into 2027: the price keeps paying for leases that have not been signed.
It pressures the case if
A lease of 100 MW or more at Panther Creek or Sharon is signed with an investment-grade tenant or wrap, with disclosed rent and term: the main gap in the view closes and the funding question becomes a financing one.
We would also be wrong if
No lease of any size is signed at any site by 30 June 2027.
Panther Creek or Sharon slips past the end of 2027.
The verdict
Scores and how we weighed it
The scores
Growthnot scored
Business quality
2 of 4
Financial position
2 of 4
Execution record
2 of 4
Per share capture
2 of 4
Potential
2 of 4
Risk profile
2 of 4
Valuation
2 of 4
Evidence quality
3 of 4
How we weighed it
ValueMixed
No fair value is drawn: the forecasts show no lasting profit after stock pay, so the bet prices it.
BusinessNegative
A weak business today: no tenant and no rent.
GrowthMixed
Growth cannot be measured until a lease is signed.
RisksNegative
No tenant has signed, building needs large funding and debt ranks first.
RivalsNegative
Mid-group among former miners, but they have signed rent and it has not.
The groupMixed
AI hosting names move together on AI spending and funding news.
Latest newsNegative
The last report showed building progress, with no tenant.