A builder in empty West Texas needs thousands of workers on site and nowhere for them to sleep. Target brings rooms, kitchens, laundry and security, and runs the village.
The company · 2 · What exactly does it sell?
Running the villages is three fifths of sales
Each $1 of sales, second quarter of 2026
61%36%3%
Running the villagesRenting roomsBuilding villages
It also runs a family detention centre at Dilley for the government.
The company · 3 · How does it make money?
Paid per village while each build lasts
53%kept per $1 on each village
About $2.0Bof signed revenue still to earn
September 2027first term ends at one data-centre village
Each village earns a high share of its sales with little added overhead. The catch: builders leave once the building is done.
Is it a good business? · 4 · What gives it an edge?
Size in a market of small operators
29
communities of rooms it owns
Under $15M
new capital for the Pecos village
Owning rooms already built lets it open a village quickly and cheaply. But the need lasts only as long as construction.
Big builders can run their own camps. And once a data centre is running, it needs only a fraction of the workers who built it.
Is it a good business? · 6 · What does its record show?
Sales swung with oilfields and the border
Sales, $M
291.3
502.0
563.6
386.3
320.6
377.1
Dec 2021Dec 2022Dec 2023Dec 2024Dec 2025last 12 mo
Peak$563.6Msales, 2023
Low$320.6Msales, 2025
Now+30%revenue last quarter
Sales fell when oilfield and government work shrank, and are climbing again on data-centre builds.
Is it a good business? · 7 · How much room is there to grow?
Data-centre building up 73% in a year
$84.95Byearly rate of US data-centre building
About $18Bmanagement's market estimate, unchecked
Over 20,000beds in the pipeline, management says
Nobody publishes how much of this goes to housing crews.
Is it a good business? · 8 · Who is in charge?
Archer moved it from oilfields to data centres
Since 2019Brad Archer in charge
3.8%owned by directors and officers
September 2026he and the commercial chief bought shares
His long-term pay rides on profit before interest, tax and depreciation, and on share returns.
The story right now · 9 · Why do AI builds need Target?
AI campuses rise where nobody lives
+73%data-centre building in a year
Over $1.7Bcontracts signed in 2026
West Texaswhere many are built
The new AI campuses go where land and power are cheap, often far from towns. Thousands of workers need a bed for the years each build takes.
The story right now · 10 · What happens when a build ends?
Each contract ends with its building
A campus is builtCrews need beds for years.
Target signs a contractOften with a minimum.
The building opensMost crews leave.
Renew or moveHas never disclosed a renewal.
If villages move from one finished campus to the next, the story lasts. Target has never disclosed a data-centre renewal.
The story right now · 11 · What changed lately?
Revenue up 30%, beds filling on plan
$129.1Mquarterly revenue, up 30%
$34.2Mprofit before interest, tax and depreciation
97%of beds filled in new villages
About $246Mspent building more
Solid quarter
The new villages are filling on plan, and the building is paid for with borrowed money.
The story right now · 12 · What is everyone arguing about?
Do villages outlast the builds they serve?
Many investors think
An AI building boom that doubles its sales
We think
Contracts house building crews and end with each build
Against us: villages moving from one finished campus to the next would make renewals look like new contracts.
The price and our view · 13 · What is a share worth?
The price sits a little above our value
$10.26what we think a share is worth · the last close is of that
$10.26our value
Attractive below $8.21
Neutral
Unattractive above $12.31
$5.56gloomy: growth halves and less kept per $1
$10.26our estimate: fast early growth, then slowing
$17.21sunny: growth runs a quarter faster
Value per share in three futures. None is a prediction of the share price.
We estimate what a share is worth from the cash the business should earn over many years. Our rule: buy only when the price is at least a fifth below our estimate, as a cushion for being wrong.
The price and our view · 14 · What if it all works?
As a bet on renewals, it is fragile
Priced for successthe kind of bet this is
1.2×if it works
30%kept if it fails
Multiples of the company's value when the bet was last struck, 30 Oct 2026.
If the large villages slip and nothing renews, the business is worth well below today's price after its debt.
The price and our view · 15 · How could we be wrong?
A few big customers, Dilley and debt
A few big customersBiggest
Two were a quarter of revenue.
Government cancels DilleyWatch
On 60 days' notice.
Borrowing to buildShowing now
About $320M still to pay.
RenewalsUnknown
Whether any village is renewed.
The former controlling owner still holds about 14.6% after selling most of its stake.
The price and our view · 16 · How will we know?
The yearly report tests profit and the two big villages
Yearly profit inside the plan, big villages fullGood sign
A village's ramp pushed later, or a cut planBad sign
A data-centre customer renewing a villageWe turn positive
MAR 202715
Fourth-quarter 2026 results and annual report, mid-March 2027. Companies report every three months; each report is a test of the story.
Our view also changes on price alone: we turn positive if the shares fall a fifth below our estimate, and negative if they rise a fifth above it.
The price and our view · 17 · So, what do we think?
Real contracts that end with each build
$10.26our value
Attractive below $8.21
Neutral
Unattractive above $12.31
NeutralMedium conviction
Target houses the crews building remote AI campuses, and builders signed over $1.7B of contracts in 2026. But builders leave once the building is done, and the price sits a little above our value. Neutral.
↑ ↓ to move · C for contents
What it does
More about the company
Who it is
A company building a data centre or a power plant in empty West Texas needs thousands of workers on site, and there is nowhere for them to sleep. Target brings in modular rooms it owns, adds kitchens, laundry and security, and runs the whole village day and night for one bill.
Its biggest new village, in North Texas, is for about 4,000 people; another, for AI infrastructure, is for about 3,370. Without it, the builder runs its own camp or pays crews to drive from motels hours away.
How it makes money
Every contract is a lease on the rooms plus a fee for meals and services, with a minimum the customer pays whether the beds are full or not. In the June 2026 quarter services were 61% of revenue and rent 36%. Customers often pay in advance, which funded much of the building: first-half cash from operations was $111.0M. The money stops when the contract ends, unless it is renewed.
Growth and profit
What growth costs
Growth here costs capital rather than running costs. Each new village is bought and built up front, about $500M in 2026, and then earns a high margin with little added overhead, so profit grows much faster than sales. The risk is that the capital is borrowed against contracts that end in a few years.
Its record
The numbers
Is it growing?Steady
Sales grew 20% over the twelve months to Sep 2026, faster than the −17% in the year to Dec 2025.
Is it profitable?Losing
Operating margin is −9.5%, down from 43% in the year to Dec 2023.
Does growth pay off?Pays off
Running costs take 25¢ of each sales dollar, up from 22¢ in the year to Dec 2021.
Does it earn good returns?Poor
Shareholders' money lost 13% a year, down from −4.7% in the year to Dec 2021.
Is it making cash?Strong
The business brought in $160M of cash from operations, 42% of sales, before capital spending, which the filer does not tag.
Is the balance sheet safe?Light debt
It owes $228M more than the cash it holds, about 1.4 years of the cash its operations bring in.
Are shares being diluted?Stable
The share count rose 3.4% in 4.8 years, and pay in shares costs 2.1% of sales.
Why it wins
The evidence
Target's edge is size in a market of small operators. It owns thousands of rooms across Texas, New Mexico and Nevada, so it can move idle beds to a new site: the Pecos data-centre village needed under $15M of new capital. A rival's annual report names it among the few firms that own and lease units at scale.
The weakness is time. That rival finds operating crews are a fifth to a quarter of building crews, so the need peaks during construction.
Who could beat it
The rivals in full
The rivals are regional and private operators, motels and RV parks, and the builders themselves, who can run their own camp. Civeo, the one listed rival, left the US. For the Dilley detention centre the risk is the government moving people elsewhere.
Each rival
Regional and private-equity-owned workforce lodging operatorsprivate
The same village, bid project by project.
CiveoCVEO
Remote lodging and hospitality, today only in Australia and Canada after it left the US.
Developers and contractors housing their own crewsin house
The whole contract, with a camp the builder runs or per-diem allowances in nearby towns.
Small independent lodges and RV parks in the Permiannot listed
Rooms for oilfield crews at lower prices with fewer services.
Detention capacity elsewhere if ICE moves people from Dilley.
How big it could get
The market and who has signed
The market
US private spending on data-centre construction ran at a $84.95B yearly rate in August 2026, up 73% in a year. What nobody publishes is how much of that goes to housing crews, so the market cannot be sized from outside. Management puts it at about $18B across data centres, power and mining, a figure no outside source checks.
Who has signed
Seven contracts carry minimums: two hyperscaler villages in Texas, an AI infrastructure village, two power-plant villages, the first data-centre village and a lithium mine hub. The largest customer can walk away, in some cases paying a fee, and the government can cancel Dilley on 60 days' notice.
Who runs it
Leaders, pay and the cash
Who runs it
Brad Archer has run the company since 2019 and led the switch from government and oilfield work to data-centre villages after the 2025 contract loss. Directors and officers own 3.8%, and he and the commercial chief bought shares in September. His long-term pay rides on profit before interest, tax and depreciation, share returns against other small companies and share-price targets. TDR Capital, the controlling owner since 2019, sold most of its stake in 2026.
What they did with the money
It repaid its costly 2025 bonds, bought $30M of stock when its largest shareholder sold in September, and is spending about $500M in 2026 on new villages, paid for by customer advances and a new $660M credit line rather than new shares.
The last report
The latest report
Target's September-quarter profit before interest, tax and depreciation reached $34.2M
What it did to the thesis Solid quarter
It showed the new villages filling and earning on plan, paid for with debt. The quarterly filing then said every contract signed this year began earning and spending stays inside the plan, but it does not name the two largest villages.
The report
In the September 2026 quarter revenue rose 30% to $129.1M and profit before interest, tax and depreciation rose 59% to $34.2M, from $18.2M in June. The new villages did it: the WHS segment kept $39.8M of every $79.5M it billed, with 97% of its beds filled.
The company spent about $246M building more villages, so its borrowings rose to about $223M. It repeated its 2026 plan.
What's happening now
The background
The next test is the fourth-quarter report and annual filing, due by mid-March: whether yearly profit lands inside the plan and the two largest villages are reported full of workers. After the results three insiders, the chief executive among them, bought shares with their own money. Behind it all, data-centre building in the US is still rising fast, though Texas is auditing every project waiting for grid power.
Where we disagree
Both sides in full
The market
An AI building boom that doubles Target's sales by 2027 and turns it to a profit, with every analyst positive.
We believe
The contracts are real, but they house building crews and end with each build, so the price is fair rather than cheap.
The argument
The market may be right that builders will keep coming: data-centre construction is still rising and Target keeps winning contracts, some built from idle beds at little cost. If villages move from one finished campus to the next, renewals look like new contracts.
Against us, the only evidence on what follows a build comes from a rival, and Target has never disclosed a data-centre renewal either way.
What it's worth
How we value it
Valued on the analysts' revenue path for three years, each later year closing 30% of the gap to 4%, on official operating profit with stock pay a cost and tax paid in full; the thesis's own evidence is the check on that path.
The three cases
Bear case$5.56
Growth runs at half the analysts' path, 30% and 13%, the margin settles a fifth lower at 15.0%, and new capital earns only the 8% rate: the downturn test.
Our value$10.26
Revenue grows 60% and 26% over three years, the analysts' path (C41), held to at most 60% a year, then fades toward 4%, closing 30% of the gap each year; the margin moves to 18.7%, the analysts' year-three figure after stock pay.
Bull case$17.21
Growth runs a quarter above the analysts' path, 75% and 33%, the margin reaches 20.6%, and new capital earns 11%.
The bet
Seen as a bet
The bet is on the whole company: the large data-centre villages open on time and reach management's 2027 pace from contracts already signed.
Even then, valued as a business whose contracts end in a few years, the company is worth only a little more than today, so the bet is expensive. If the villages slip and nothing renews, shareholders keep about a quarter of what they hold, because the building is paid for with debt.
What could go wrong
Every risk
The risks
A few big customers
Two customers were a third of first-half revenue, and the largest new contract lets the customer walk away, sometimes paying a fee.
Government cancels Dilley
The detention-centre contract, the most profitable per bed, can be cancelled on 60 days' notice; a similar contract ended that way in 2025.
Texas slows data centres
The governor ordered an audit of every data centre waiting for grid power, and most of the new villages are in Texas.
Borrowing to build
About $320M of building is still to pay for in 2026, mostly borrowed against contracts that end within a few years.
A large seller
The former controlling owner still holds about 14.6% after selling most of its stake this year.
What we still do not know
Does any data-centre customer renew its village once the campus is built, and at what size?
What would the AI infrastructure customer owe if it ended its contract early?
Is Target trying to sell the Dilley detention centre?
What changes our view
Every route to a new view
Every route to a new view
→ Attractive
The share price falls to about $8.21, 80% of what we think the business is worth.
→ Unattractive
The share price rises to about $12.31, 20% above what we think the business is worth.
→ Attractive
Target announces that a data-centre or power customer renewed or extended a village beyond its first term. Quarterly profit before interest, tax and depreciation reaches $60M, from $34.2M.
The next test
It supports the case if
2026 adjusted EBITDA inside the guide, both villages reported housing workers on plan, and a 2027 guide consistent with a $300M exit-2027 pace.
It pressures the case if
2026 adjusted EBITDA below $105M, either village's ramp pushed later than its plan, or a 2027 guide that moves the exit pace back.
We would also be wrong if
The North Texas hub or the AI infrastructure village opens later than the end of 2026.
The government cancels the Dilley contract.
Profit before interest, tax and depreciation for 2026 falls below $105M.
The verdict
Scores and how we weighed it
The scores
Growth
3 of 4
Business quality
2 of 4
Financial position
3 of 4
Execution record
3 of 4
Per share capture
4 of 4
Potential
3 of 4
Risk profile
2 of 4
Valuation
3 of 4
Evidence quality
3 of 4
How we weighed it
ValueMixed
The price is a little above our value, with the bear case well below.
BusinessMixed
Movable rooms win fast contracts, but each one ends when the building is finished.
GrowthPositive
Large new contracts were signed this year, and the villages are filling on plan.
RisksNegative
Two customers carry much of revenue, the detention contract can be cancelled, Texas is auditing data centres and the build is funded with debt.
RivalsMixed
No filed rival offers a clean comparison; its own past profit says little about the new villages.
The groupMixed
It sits in none of our ranked groups; data-centre building and government contracts move it.
Latest newsPositive
The last report showed the new villages filling and earning on plan.
In plain words
Our estimate of value
We forecast how much cash the business can earn over the next ten years and beyond, then ask what that stream is worth today to an investor who wants an 8% yearly return. We do it three times: a gloomy future, an expected one and a sunny one. We call a share Attractive only when its price is at least 20% below the expected estimate, and Unattractive when it is 20% above.