←AAONAAONOur view: NeutralFull analysisעברית
Updated 16 Nov 2026
The company · 1 · Who is this company?

AAON builds heating and cooling equipment to order

Rooftop units

on shops, schools and offices

BASX

cooling for data centres

Tulsa

where it is based, since 1988

AAON makes the heating and cooling boxes on top of commercial buildings, and under its BASX brand the large cooling systems that keep data centres from overheating.

The company · 2 · What exactly does it sell?

Data-centre cooling is now over half of sales

Each $1 of sales, nine months to September 2026
43%33%24%
Rooftop units and heat pumpsData-centre air coolingCoils and liquid cooling

The Texas coil plant now makes mostly liquid cooling for data centres, so data-centre work is more than its own line shows.

The company · 3 · How does it make money?

It sells equipment one order at a time

$1.85Bof orders waiting to be built
18 to 26 weekswait for an AAON rooftop unit
3customers each took a tenth of sales

Each unit is built to the buyer's plan and paid for as it ships, so sales follow orders a few months later.

Is it a good business? · 4 · What gives it an edge?

Built to order at near-catalogue cost

20%

AAON-brand sales growth last quarter

4.4%

fall in commercial building spending

Fitting each unit to the building on a production line wins orders even when building is weak.

Is it a good business? · 5 · What is the catch?

Bigger rivals with fatter profits

Tranerooftop units and data-centre cooling
Vertivabout seven times AAON's sales
Lennoxcommercial sales up 24%

Listed rivals: LII · CARR · TT · JCI · 6367.T · VRT · MOD · MTRS.ST

AAON keeps less of each sale than most of its larger rivals.

Is it a good business? · 6 · What does its record show?

Sales nearly tripled while profit per $1 fell

Sales, $B
0.5
0.9
1.2
1.2
1.4
Dec 2021Dec 2022Dec 2023Dec 2024Dec 2025
Sales$514.6M → $1,442.1Msales, 2020 to 2025
Profit19.8% → 10.1%operating profit per $1, 2020 to 2025
Now84%sales growth last quarter

New plants and data-centre work cost profit for three years; it is coming back as the plants fill.

Is it a good business? · 7 · How much room is there to grow?

A $56B market, cooling growing fastest

About $56Ba year of data-centre power and cooling
40%yearly growth in data-centre cooling
About 3%BASX's slice of the whole market

Spending on new American data-centre buildings nearly doubled in a year.

Is it a good business? · 8 · Who is in charge?

A data-centre founder runs it

2025Matt Tobolski, who co-founded BASX, became chief executive
16.8%of the shares the founder still owns
67%of the yearly bonus paid on operating profit

The founder of AAON still owns about a sixth; the man who built BASX runs the whole company.

The story right now · 9 · Why do data centres need so much cooling?

AI chips turn power into heat that must go

$96.5Byearly rate of American data-centre building
218%BASX sales growth last quarter
Permitsnow the biggest brake on new sites

Every watt a chip uses becomes heat. The newest racks run so hot that air is not enough, and coolant is piped to the chips.

The story right now · 10 · Why do orders matter more than sales?

Today's orders are next year's sales

  1. A data centre is plannedCooling ordered early.
  2. AAON books the orderIt waits to be built.
  3. The unit shipsMonths later, as sales.
  4. Orders slowSales follow down later.

That is why the shares fell by almost two thirds after one weak quarter of data-centre orders, while sales were still rising.

The story right now · 11 · What changed lately?

Sales rose 84% and the outlook went up

$707.4Msales last quarter, up 84%
72% to 75%2026 growth now expected
$10.7Mfirst-half sales restated upward
5.9%fall in orders waiting since June

Solid quarter

Cash flow turned positive for the first time in two years, but the revenue controls had a weakness.

The story right now · 12 · What is everyone arguing about?

Can profit per $1 climb back?

Many investors think

An AI cooling winner whose fall went too far

We think

Growth is real; the profit recovery is still a target

Against us: the Oklahoma plants keeping 35% of each sale after making it, with data-centre orders waiting above $1.5B.

The price and our view · 13 · What is a share worth?

The price sits about an eighth above our value

$70.99what we think a share is worth
$70.99our value
Attractive
below $56.79
Neutral
Unattractive
above $85.19
$30.60gloomy: data-centre orders stall
$70.99our estimate: the analysts' path, profit recovering
$98.76sunny: faster growth and fuller plants

Value per share in three futures. None is a prediction of the share price.

We estimate what a share is worth from the cash the business should earn over many years. Our rule: buy only when the price is at least a fifth below our estimate, as a cushion for being wrong.

The price and our view · 14 · How could we be wrong?

Few buyers, swinging orders, weak controls

A few big buyersBiggest

Three took a tenth each.

Orders swingShowing now

Orders fell after June.

ControlsWatch

First half restated.

Who the buyers areUnknown

None is named.

Permits slowing new data centres and bigger rivals also weigh on the case.

The price and our view · 15 · How will we know?

Early March brings the 2027 outlook

Data-centre bookings at or above last year'sGood sign
Oklahoma profit per $1 climbing backGood sign
Orders waiting falling below $1.2B for BASXBad sign
MAR 20271

Fourth-quarter 2026 results and 2027 outlook, early March. Companies report every three months; each report is a test of the story.

Our view also changes on price alone: a fall to a fifth below our estimate would make it Attractive.

The price and our view · 16 · So, what do we think?

A real growth story priced about right

$70.99our value
Attractive
below $56.79
Neutral
Unattractive
above $85.19

NeutralMedium conviction

Data-centre cooling has made AAON a fast grower and its plants are built. But profit per $1 is still recovering and a few buyers dominate. The price sits a little above our value: worth watching, not chasing.

↑ ↓ to move · C for contents