Powell Industries
This is the archived full research. Read the story
Builds the custom electrical rooms, switchgear and breakers that sit between a power source and a big user of power: a data centre, a gas terminal, a chemical plant.
The scores
Growth3/4 ↑
Revenue grew 13.8% in fiscal 2026 and 33% in the fourth quarter, faster each quarter, on a lumpy project book.
Business quality3/4 →
Returns are more than double the cohort on scarce rated capacity, but the work is competitively bid, non-recurring, and a rival bought comparable capacity outright.
Financial position4/4 →
No drawn debt, cash and short-term investments of $634 million against equity of $756 million, a dividend paid and capacity expansion funded from cash.
Execution record3/4 ↑
Operating margin rose from 0.2% to 21.1% over five years, the fiscal 2025 margin promise was met, and capacity landed on plan.
Per share capture4/4 →
Share count flat quarter over quarter, no debt to service and negligible intangibles, so operating profit reaches per-share earnings with almost no leakage.
Potential3/4 ↑
Data-centre load growth is real and behind-the-meter raises content per project, but no published conversion turns megawatts into switchgear dollars.
Risk profile3/4 →
No customer above 10% and no debt, against lumpy non-recurring project revenue, a 49% petrochemical decline and craft labour flagged as a fiscal 2027 constraint.
Valuation1/4 →
About 38.7 times normal-year operating profit, 145% of a value near $104 and above the $132 bull case.
Evidence quality2/4 ↓
A load-bearing quote on data-center boundaries did not reproduce against an independent transcription of the same call; corrected this review, so the cap applies.
The Verdict
We rate Powell Unattractive. It builds the custom electrical rooms and switchgear between a power source and a big user such as a data centre, earning more than twice its rivals' return on capital, so the business is solid. Its fiscal 2026 ended strongly: sales up 33% in the last quarter, margins rising and a backlog doubled to $2.7 billion. But that margin sits at a cycle peak, and we value the business on a normal year: about $104 a share, against $151, above even our best case. Proof the high margin lasts would change the view.
The long caseData centres, gas export plants and the grid need power faster than switchgear can be built; if Powell can deliver faster, scarce delivery slots become its edge.
How we weighed it
The price against our value
Against it
Price at 145% of our value
The price sits well above our value and above the bull case, even after a strong report.
The business
In its favour
Strong
Returns on capital are more than twice its rivals'.
Growth against what the price assumes
In its favour
Sales grew in each quarter faster than the last, and the backlog doubled in a year.
What could go wrong
Against it
The margin is at a peak, skilled workers are short and orders can be cancelled.
Against competitors
In its favour
Mid-pack among listed rivals despite the best returns of the group.
How its group is behaving
Cuts both ways
Power names move together on AI power news.
The latest news and report
In its favour
The last report beat what the thesis needed on margin and orders; on the call part of the margin proved one-off, and only about half the backlog ships within a year.
The evidence under this - 8 claims
The release does not say how much of the $2.7 billion backlog converts within twelve months, the figure the thesis's main doubt rests on, and gives no figure for project closeouts in the quarter's margin; both wait for the call. Petrochemical revenue fell 49% in the quarter, so the growth is concentrated in commercial and data-centre work.
The value rests on the margin falling to its five-year average of 9.6%, less than half fiscal 2026's 21.1%; with a $2.7B backlog and the CFO calling the margin sustainable (C40), a higher normal would lift it sharply. At a 10% required return it is about $79.
- 2026-11-09editedgrowth fades as each year closes 30% of its gap to 4% and the analysts' margin is put on the filed basis, the owner's call of 9 November
- 2026-11-10editedre-valued on the owner's rules of 10 November: the return on new capital glides to its terminal level over years six to ten
- 2026-11-17editedRe-struck on the fiscal 2026 results: revenue of $1.26B, cash of $861M and the analysts' path from the actual year; the value moves from about $94 to about $104, and the price of $151.20 is about 145% of it.
The chief executive said on the same day's call that this order scale is not repeatable: 'Projects upwards of $400 million are not common in the pipeline other than potential future phases of this particular program.' A book-to-bill of 3.0 driven by one order above $400 million should therefore not be annualised, and the company's own release cautions that backlog 'may not be indicative of future operating results as orders may be cancelled or modified by our customers and associated backlog may not be recognized as revenue on the timeline we expect or at all'.
The share fell again, from 54% to about 48%, because the orders won were large and slow: the $250M LNG order runs about three years. In dollars, though, $1.3 billion scheduled within a year is about 60% more than the roughly $800 million a year earlier, and about what fiscal 2026 sold in total.
- 2026-11-17editedIts refresh moves to the fourth-quarter call, which FMP did not yet hold on 17 November; the results release does not restate it.
- 2026-11-17editedthe fiscal 2026 10-K and the Q4 call: about $1.3B of the $2.7B backlog converts within twelve months, roughly half, down from 54% at June
- Management capping its own growth expectation is unusual and is evidence of candour rather than weakness, and the same executive framed the 9% print as one he was 'very happy with'. But it is also the single most important forward statement in this file: a company whose order book tripled telling the market not to expect double-digit revenue growth is describing a capacity ceiling, not a demand one, and that ceiling is what the multiple has to be judged against.
- Fiscal 2026 revenue grew 13.8% and the fourth quarter 33% (C28, C39), so the hedged cap he gave in August did not hold for the year he was describing. On the Q4 call he called the quarter's sequential jump capacity coming online with 'no unusuals', and about $1.3B of backlog is scheduled for fiscal 2027 against $1.26B sold in fiscal 2026 (C08).
- 2026-11-17editedTested by the fiscal 2026 results: revenue grew 13.8% for the year and 33% in the fourth quarter, past the 'probably not double-digit' he gave; the claim stays as what was said, with the outcome beside it.
- 2026-11-17editedthe Q4 call: no pull-forward in the quarter, and $1.3B of backlog scheduled for fiscal 2027
- nVent's 46.2% revenue growth - the figure that lifts the cohort median to 15.5% and makes Powell look slowest - is substantially acquired rather than organic: nVent bought Avail Infrastructure Solutions' switchgear and enclosures businesses for approximately $1 billion in cash during 2025. Comparing Powell's organic 7% against a median inflated by an acquisition overstates the growth gap, though it does not close it, since Eaton and Hubbell grew 15.5% and 10.6% without a deal of that scale.
- Powell's frame-metric discount to the cohort widened between 24 August and 6 September - from 27.5 against 31.4 to 26.2 against 32.0 - but roughly half of the subject's move is the vendor share-count correction recorded at C22 rather than anything the market did. The August reading was overstated by about 4.6%, so the thesis was harsher on Powell's price than the filed share count supported.
- 2026-10-27editedcohort multiples are as of the 4 September pack and were not re-struck after the fall
The two soft quarters were 13 and 30 basis points, inside the noise of a project business, and the fourth quarter's jump may carry project closeouts the release does not size; whether the 34.9% is a level or a lumpy quarter is the call's question. What the series no longer supports is the reading of September that the margin had stopped rising.
- 2026-11-17editedContradicted by the fourth quarter: gross margin of 34.9% against 31.4% a year earlier ended the two-quarter flattening the claim read as a stop; restated with the full year's series.
The company
Anything that draws a lot of power, from a data centre to a gas export terminal, needs equipment between the supply and the load to distribute, switch and protect the electricity. Powell, founded in Houston in 1947, designs and builds that equipment, often as a whole prefabricated electrical room.
The alternative is buying switchgear, breakers and controls from several vendors and paying a contractor to assemble them on site, which is slower. In data centres, Powell wins on delivery speed rather than price.
The evidence under this - 3 claims
- Competing on delivery speed is an advantage only while capacity is scarce, and the same executive expects the market's rate to attenuate. The rating diversion is a real if small cost of entering the data-centre vertical: the products Powell sold into these new jobs required certifications it had to go and obtain, which is evidence the commercial vertical is genuinely new ground rather than an extension of the existing catalogue.
- On the Q4 call the chief executive said data-centre work was won first on capacity and availability and is moving to configure-to-order flow lines, more standard than Powell's engineered work, and that the market is 'very competitive' with 'a lot of players running to it'.
- 2026-11-17editedIts refresh moves to the fourth-quarter call, which FMP did not yet hold on 17 November; the results release does not restate it.
- 2026-11-17editedthe Q4 call on how data-centre work is won; refresh moved to the Q1 fiscal 2027 call
How it makes money
Every job is custom and won by competitive bid, so Powell earns by the project: an order is booked, built over one to three years, and becomes sales as it ships. Big projects rarely repeat with the same customer, and no customer was more than 10% of sales in either of the last two years.
The evidence under this - 3 claims
The share fell again, from 54% to about 48%, because the orders won were large and slow: the $250M LNG order runs about three years. In dollars, though, $1.3 billion scheduled within a year is about 60% more than the roughly $800 million a year earlier, and about what fiscal 2026 sold in total.
- 2026-11-17editedIts refresh moves to the fourth-quarter call, which FMP did not yet hold on 17 November; the results release does not restate it.
- 2026-11-17editedthe fiscal 2026 10-K and the Q4 call: about $1.3B of the $2.7B backlog converts within twelve months, roughly half, down from 54% at June
Where the money comes from, stream by stream
| Stream | Share of sales (nine months to June 2026) | How it earns it |
|---|---|---|
| Oil and gas (excluding petrochemical) | 36.9% | Switchgear, power control rooms and motor control for upstream, midstream and LNG projects, bid and built to order. |
| Electric utility | 27.7% | Substation switchgear, protection and control equipment, including Remsdaq's remote terminal units, sold to utilities. |
| Commercial and other industrial | 19.9% | The same engineered equipment for data centres and other industrial sites; the fastest-growing line. |
| Petrochemical | 8.0% | Electrical systems for chemical plants; down from 14.0% of revenue a year earlier. |
| Light rail traction power and all others | 7.5% | Traction power for transit systems, plus universities, government and other buyers. |
Who runs it
Brett Cope has run Powell since 2016 and chairs its board; Michael Metcalf has run its finances since 2018. Under them it went from barely breaking even to keeping about a fifth of each sales dollar as operating profit. Insiders own only about 2%; the largest holder, Thomas Powell, is not on the board. Bonuses and share awards ride on a profit measure and on safety, with goals set below results already reached, and nothing pays on the share price.
The evidence under this - 5 claims
Insiders have been net sellers since: 79 open-market sales and no purchases over the year to September 2026, including the chief executive's 10b5-1 sale of 4,500 shares in August 2026 (C18), so the group's stake is if anything smaller now.
The proxy states that 75% of the chief executive's target pay is at risk, and both plans cap the payout at 200% of target, so the design is variable and bounded even if its goals were low (C32).
The fiscal 2023-2025 goal was set in September 2022, when operating margin was 1.4% (C12), so a low bar was a fair reading of the business at the time it was set.
Why it wins, and who could beat it
Why customers come back
The scarce thing in this industry is not design but factory capacity and the skilled workers to run it. So buyers commit early to secure a delivery slot: last quarter Powell booked orders worth 3.0 times its sales, and its backlog takes one to three years to deliver.
The same squeeze shows at rivals. nVent says its own large orders can take more than a year to build.
The evidence under this - 3 claims
The chief executive said on the same day's call that this order scale is not repeatable: 'Projects upwards of $400 million are not common in the pipeline other than potential future phases of this particular program.' A book-to-bill of 3.0 driven by one order above $400 million should therefore not be annualised, and the company's own release cautions that backlog 'may not be indicative of future operating results as orders may be cancelled or modified by our customers and associated backlog may not be recognized as revenue on the timeline we expect or at all'.
The share fell again, from 54% to about 48%, because the orders won were large and slow: the $250M LNG order runs about three years. In dollars, though, $1.3 billion scheduled within a year is about 60% more than the roughly $800 million a year earlier, and about what fiscal 2026 sold in total.
- 2026-11-17editedIts refresh moves to the fourth-quarter call, which FMP did not yet hold on 17 November; the results release does not restate it.
- 2026-11-17editedthe fiscal 2026 10-K and the Q4 call: about $1.3B of the $2.7B backlog converts within twelve months, roughly half, down from 54% at June
The threat
Its rivals are much larger, and Powell's own filing concedes some have far greater resources and lower costs. nVent, Eaton and Hubbell are the listed ones, and nVent's $1.0B purchase of a switchgear maker targets Powell's two growth markets. If rivals add capacity faster than demand grows, the delivery-slot advantage goes.
The evidence under this - 3 claims
- nVent's 46.2% revenue growth - the figure that lifts the cohort median to 15.5% and makes Powell look slowest - is substantially acquired rather than organic: nVent bought Avail Infrastructure Solutions' switchgear and enclosures businesses for approximately $1 billion in cash during 2025. Comparing Powell's organic 7% against a median inflated by an acquisition overstates the growth gap, though it does not close it, since Eaton and Hubbell grew 15.5% and 10.6% without a deal of that scale.
- Powell's frame-metric discount to the cohort widened between 24 August and 6 September - from 27.5 against 31.4 to 26.2 against 32.0 - but roughly half of the subject's move is the vendor share-count correction recorded at C22 rather than anything the market did. The August reading was overstated by about 4.6%, so the thesis was harsher on Powell's price than the filed share count supported.
- 2026-10-27editedcohort multiples are as of the 4 September pack and were not re-struck after the fall
The rivals: NVT, ETN, HUBB, and 1 more that is private, in-house or listed abroad.
Who else does this, rival by rival
| Ticker | Rival | How far along | Priced against it |
|---|---|---|---|
| NVT | nVent Electric, which in 2025 bought the enclosures, switchgear and bus systems businesses of Avail Infrastructure Solutions for approximately $1 billion in cashPriced against it: Yes | On sale | Yes |
| ETN · HUBB | Eaton and Hubbell, the two other US-listed multinationals selling power distribution equipment into the grid, data centres and industrialsPriced against it: Yes | On sale | Yes |
| Siemens Energy, Schneider Electric and ABB, the European multinationals in the same class Powell's Item 1 namesPriced against it: Listed abroad | On sale | Listed abroad |
How big it could get
How big this could get
The demand is large and hard to size. Government projections have data-centre servers rising from about 7% of the electricity American commercial buildings use in 2025 to 22% to 33% by 2050, but nobody converts that into equipment dollars.
The limit is Powell's own capacity. It made $1.10B of sales in fiscal 2025, and only about $1.3B of its $2.4B backlog can be delivered in the next year.
The evidence under this - 3 claims
The share fell again, from 54% to about 48%, because the orders won were large and slow: the $250M LNG order runs about three years. In dollars, though, $1.3 billion scheduled within a year is about 60% more than the roughly $800 million a year earlier, and about what fiscal 2026 sold in total.
- 2026-11-17editedIts refresh moves to the fourth-quarter call, which FMP did not yet hold on 17 November; the results release does not restate it.
- 2026-11-17editedthe fiscal 2026 10-K and the Q4 call: about $1.3B of the $2.7B backlog converts within twelve months, roughly half, down from 54% at June
Who has signed
Three large orders last quarter, none with a named customer: a data-centre power system worth more than $400M, a $75M fertiliser plant and a $60M gas export terminal. The data-centre job is only the first phase of a larger programme, and the later phases have not been awarded.
The evidence under this - 2 claims
The chief executive said on the same day's call that this order scale is not repeatable: 'Projects upwards of $400 million are not common in the pipeline other than potential future phases of this particular program.' A book-to-bill of 3.0 driven by one order above $400 million should therefore not be annualised, and the company's own release cautions that backlog 'may not be indicative of future operating results as orders may be cancelled or modified by our customers and associated backlog may not be recognized as revenue on the timeline we expect or at all'.
- The future phases are unawarded and the chief executive qualified them twice - 'assuming we're successful' and 'nothing in the near term'. A two-and-a-half-year burn on a single order also means most of its revenue lands beyond this thesis's horizon, so the largest order in the company's history contributes to the backlog figure long before it contributes to earnings.
- The Q4 call did not mention the programme's later phases; it named a separate $85M data-centre order, and the chief executive said data-centre designs change quantities mid-programme, which Powell has reallocated rather than seen cancelled.
- 2026-11-17editedIts refresh moves to the fourth-quarter call, which FMP did not yet hold on 17 November; the results release does not restate it.
- 2026-11-17editedchecked against the Q4 call: the later phases were not mentioned; refresh moved to the Q1 fiscal 2027 call
Where the growth is coming from, business by business
Where the growth is coming from
| Business | Share of revenue | Growth: last quarter | Last half-year | Last year |
|---|---|---|---|---|
| Oil and Gas Service | 34% | +0.8% | +1.5% | - |
| Electricity | 28% | +18.3% | +25.2% | - |
| Commercial and Other Industrial | 24% | +54.1% | +24.6% | - |
| Petrochemical | 6% | -49.2% | -40.7% | - |
| Other, Customers | 5% | +22.9% | +28.7% | - |
| Light Rail Traction Power Customer | 3% | -6.9% | -1.2% | - |
| Whole company | 100% | +8.9% | +6.7% | - |
The filed split through 2026-06-30. These rates are not carried forward: the reading below says why.
How we read it: The blend. Electricity (+25%) and data-centre-led Commercial (+25%) are one switchgear product, offset by Petrochemical's 49% fall; lumpy projects and 54% backlog conversion cap growth, per the CFO. 2 holds.
The results
The numbers
Sales grew 14% in the year to Sep 2026, about the same pace as the 9.1% in the year before.
Operating margin is 21%, up from 8.9% in the year to Sep 2023.
Running costs take 10¢ of each sales dollar, down from 15¢ in the year to Sep 2022.
Each dollar put into the business earns 28% a year after tax, up from 2.4% in the year to Sep 2022.
It turned 33% of sales into free cash, $415M over the year.
Yearly sales growth has ranged from +9.1% to +45% over the last 5 years.
The share count barely moved in 2.0 years, and pay in shares costs 0.5% of sales.
All the numbers
Filed figures from the company's 10-K and 10-Q, read 2026-11-17. Fiscal years end in September.
| Sep 2022 | Sep 2023 | Sep 2024 | Sep 2025 | Sep 2026 | |
|---|---|---|---|---|---|
| Size and growth | |||||
| Sales | $533M | $699M | $1.01B | $1.10B | $1.26B |
| Sales growth | +13% | +31% | +45% | +9.1% | +14% |
| Profit | |||||
| Gross margin | 16% | 21% | 27% | 29% | 31% |
| Operating margin | 1.4% | 8.9% | 18% | 20% | 21% |
| Net margin | 2.6% | 7.8% | 15% | 16% | 18% |
| What growth costs, per sales dollar | |||||
| Research and development | 1.3% | 0.9% | 0.9% | 1.0% | 1.2% |
| Selling, general and admin | 13% | 11% | 8.4% | 8.6% | 8.9% |
| Pay in shares | 0.8% | 0.7% | 0.5% | 0.4% | 0.5% |
| Capital spending | 0.5% | 1.1% | 1.2% | 1.2% | 1.5% |
| Cash | |||||
| Cash from operations | −$3.58M | $183M | $109M | $168M | $434M |
| Free cash flow | −$6.03M | $175M | $96.7M | $155M | $415M |
| Balance sheet | |||||
| Cash and short-term investments | $117M | $279M | $358M | $476M | $861M |
| Debt | $0 | - | - | - | - |
| Net cash | $117M | - | - | - | - |
| Returns and shares | |||||
| Return on capital | 2.4% | 15% | 33% | 30% | 28% |
| Shares (diluted) | - | - | 36.6M | 36.5M | 36.6M |
What growth costs
For years, growing made Powell more profitable: sales doubled while office, selling and research costs grew far less. That effect has stalled; since 2024 those costs have grown a little faster than sales, so recent margin gains came from the factory floor. It spends little on buildings, leasing a plant rather than building one.
The evidence under this - 3 claims
The fiscal 2025 10-K attributes part of that year's SG&A rise to higher compensation and to costs of the Remsdaq acquisition (C34), so some of the reversal is a one-off rather than a trend.
- The leased facility does not produce anything until late in fiscal Q2 or early Q3 2027 - March to June 2027 - which is after the two prints this thesis's next test and horizon turn on. So the capacity that would lift backlog convertibility above 54% is not available during the period in which convertibility is expected to recover, and the recovery, if it comes, has to come from the existing footprint. Against that, the chief executive attributes the current throughput to running the job across at least five existing plants rather than to any single new one.
- The $70 million to $100 million greenfield figure is the alternative Powell declined, so it quantifies the capital discipline the thesis credits - but it also quantifies what a competitor willing to spend would need in order to add the capacity that constitutes Powell's moat, which is roughly a tenth of what nVent paid to buy comparable capacity outright.
- On the Q4 call the chief executive said the 335,000 square-foot Jacintoport expansion is operational and supports about $100M of yearly revenue, a further 80,000 square feet and a 275,000 square-foot lease due in fiscal Q3 2027 follow, and competition for skilled craft labour is rising but has not yet affected execution; the finance chief put fiscal 2027 capital spending at $15M to $20M.
- 2026-11-17editedthe Q4 call: capacity added and planned, labour not yet binding, fiscal 2027 capital spending
The last report (16 Nov)
Quarter ended September 2026, filed figures.
In the fourth quarter of fiscal 2026, to September 30, sales rose 33% to $397M and Powell kept 34.9 cents of each sales dollar after making it, against 31.4 cents a year earlier. Orders of $710M took the backlog to $2.7B, double a year earlier.
On the call the finance chief said about $1.3B of the backlog, roughly half, ships within a year, against 60% a year earlier, because the new orders are big and slow. About 2.3 points of the quarter's margin came from one-off project closeouts; the base margin is near 30%, which he expects to hold next year.
What it did to the thesisIt answered our three questions. Margins rose and orders stayed far above last year, in the case's favour. Delivery slowed as a share of the backlog, though not in dollars, and part of the margin was one-off. The price stays dearer than our best case.
The quarter in detail
Sales growth from the previous quarter, filed figures.
Earnings per share $2.23 against $1.57 expected.
The evidence under this - 7 claims
The release does not say how much of the $2.7 billion backlog converts within twelve months, the figure the thesis's main doubt rests on, and gives no figure for project closeouts in the quarter's margin; both wait for the call. Petrochemical revenue fell 49% in the quarter, so the growth is concentrated in commercial and data-centre work.
The fourth quarter is one quarter of a lumpy project business and the CFO warned of a seasonally slower first fiscal quarter; part of the acceleration is a weak comparison base early in fiscal 2025.
- 2026-11-17editedExtended with the fourth quarter (+33%) and the full year (+13.8%) from the 16 November results release.
The two soft quarters were 13 and 30 basis points, inside the noise of a project business, and the fourth quarter's jump may carry project closeouts the release does not size; whether the 34.9% is a level or a lumpy quarter is the call's question. What the series no longer supports is the reading of September that the margin had stopped rising.
- 2026-11-17editedContradicted by the fourth quarter: gross margin of 34.9% against 31.4% a year earlier ended the two-quarter flattening the claim read as a stop; restated with the full year's series.
- Management capping its own growth expectation is unusual and is evidence of candour rather than weakness, and the same executive framed the 9% print as one he was 'very happy with'. But it is also the single most important forward statement in this file: a company whose order book tripled telling the market not to expect double-digit revenue growth is describing a capacity ceiling, not a demand one, and that ceiling is what the multiple has to be judged against.
- Fiscal 2026 revenue grew 13.8% and the fourth quarter 33% (C28, C39), so the hedged cap he gave in August did not hold for the year he was describing. On the Q4 call he called the quarter's sequential jump capacity coming online with 'no unusuals', and about $1.3B of backlog is scheduled for fiscal 2027 against $1.26B sold in fiscal 2026 (C08).
- 2026-11-17editedTested by the fiscal 2026 results: revenue grew 13.8% for the year and 33% in the fourth quarter, past the 'probably not double-digit' he gave; the claim stays as what was said, with the outcome beside it.
- 2026-11-17editedthe Q4 call: no pull-forward in the quarter, and $1.3B of backlog scheduled for fiscal 2027
The same statement about fiscal 2025's margin (C25) was met. On the call the finance chief sized fiscal 2026's closeouts at about 150 basis points (C09), so the base margin he expects to hold is near 30% gross, and the fair value still values the business on a normal-year operating margin of 9.6%, less than half fiscal 2026's 21.1%.
- 2026-11-17editedthe Q4 call sized the closeouts inside the fiscal 2026 margin the CFO calls sustainable
The share fell again, from 54% to about 48%, because the orders won were large and slow: the $250M LNG order runs about three years. In dollars, though, $1.3 billion scheduled within a year is about 60% more than the roughly $800 million a year earlier, and about what fiscal 2026 sold in total.
- 2026-11-17editedIts refresh moves to the fourth-quarter call, which FMP did not yet hold on 17 November; the results release does not restate it.
- 2026-11-17editedthe fiscal 2026 10-K and the Q4 call: about $1.3B of the $2.7B backlog converts within twelve months, roughly half, down from 54% at June
About 230 of the fourth quarter's 350 basis-point rise was closeouts, so its like-for-like margin was nearer 32.6% than 34.9%; the closeouts are non-recurring by nature, though Powell has earned them three years running. The underlying rise of about two points is pricing and volume, the part a capacity-constrained cycle supplies and a slower one takes back.
- 2026-11-17editedIts refresh moves to the fourth-quarter call, which FMP did not yet hold on 17 November; the results release does not restate it.
- 2026-11-17editedthe Q4 call sized the closeouts: about 230 basis points in the quarter, 150 in fiscal 2026, base margin near 30%
What management did with the money
It has spent lightly on capacity: $12.4M to expand a Houston yard by 62%, and a leased plant due in 2027 rather than a new build it put at $70M to $100M. It has no borrowings and $634M of cash.
The evidence under this - 2 claims
- The leased facility does not produce anything until late in fiscal Q2 or early Q3 2027 - March to June 2027 - which is after the two prints this thesis's next test and horizon turn on. So the capacity that would lift backlog convertibility above 54% is not available during the period in which convertibility is expected to recover, and the recovery, if it comes, has to come from the existing footprint. Against that, the chief executive attributes the current throughput to running the job across at least five existing plants rather than to any single new one.
- The $70 million to $100 million greenfield figure is the alternative Powell declined, so it quantifies the capital discipline the thesis credits - but it also quantifies what a competitor willing to spend would need in order to add the capacity that constitutes Powell's moat, which is roughly a tenth of what nVent paid to buy comparable capacity outright.
- On the Q4 call the chief executive said the 335,000 square-foot Jacintoport expansion is operational and supports about $100M of yearly revenue, a further 80,000 square feet and a 275,000 square-foot lease due in fiscal Q3 2027 follow, and competition for skilled craft labour is rising but has not yet affected execution; the finance chief put fiscal 2027 capital spending at $15M to $20M.
- 2026-11-17editedthe Q4 call: capacity added and planned, labour not yet binding, fiscal 2027 capital spending
The price, and where we disagree
In short. Priced for perfection. The price is about 145% of what we think the business is worth, at an 8% yearly return, and above our best case.
The shares have fallen 53.9% from their $328.00 high to $151.20 on 16 November, before the results came out that evening. The data-centre order was announced in May and the shares peaked with it already known, so the fall after the June-quarter results was a verdict on how fast the backlog converts, not on the order.
The call on 17 November put about half the backlog inside the next year and part of the quarter's margin down to one-off closeouts. The next check is the first fiscal 2027 quarter on 2 February.
The evidence under this - 5 claims
- 2026-10-27editedre-struck at the 26 October close of $157.07 after a 13.3% fall
This does not make the thesis's headline wrong - the order was genuinely booked in fiscal Q3 and the $934 million order total is genuinely a record - but it does separate two events the August page ran together. The market learned of the largest order in Powell's history on 4 May and marked the shares up to a $328 high by early July; the 34% decline began after the 3 August call, whose new information was the 54% convertibility figure and the growth cap, not the order. What repriced the stock was conversion, not demand.
The release does not say how much of the $2.7 billion backlog converts within twelve months, the figure the thesis's main doubt rests on, and gives no figure for project closeouts in the quarter's margin; both wait for the call. Petrochemical revenue fell 49% in the quarter, so the growth is concentrated in commercial and data-centre work.
The share fell again, from 54% to about 48%, because the orders won were large and slow: the $250M LNG order runs about three years. In dollars, though, $1.3 billion scheduled within a year is about 60% more than the roughly $800 million a year earlier, and about what fiscal 2026 sold in total.
- 2026-11-17editedIts refresh moves to the fourth-quarter call, which FMP did not yet hold on 17 November; the results release does not restate it.
- 2026-11-17editedthe fiscal 2026 10-K and the Q4 call: about $1.3B of the $2.7B backlog converts within twelve months, roughly half, down from 54% at June
About 230 of the fourth quarter's 350 basis-point rise was closeouts, so its like-for-like margin was nearer 32.6% than 34.9%; the closeouts are non-recurring by nature, though Powell has earned them three years running. The underlying rise of about two points is pricing and volume, the part a capacity-constrained cycle supplies and a slower one takes back.
- 2026-11-17editedIts refresh moves to the fourth-quarter call, which FMP did not yet hold on 17 November; the results release does not restate it.
- 2026-11-17editedthe Q4 call sized the closeouts: about 230 basis points in the quarter, 150 in fiscal 2026, base margin near 30%
How we value it
- Method
- Cash the business will produce, in three stages
- Required return
- 8%
- Long-run growth
- 4%
- Moat
- An average moat
| Bear | Base | Bull | |
|---|---|---|---|
| Sales growth, years 1 to 3 | 8.9%, 8.2%, 7.1% | 17.7%, 16.3%, 14.2% | 22.1%, 20.4%, 17.8% |
| Normal operating margin | 7.7% | 9.6% | 10.5% |
| Return on new capital after year ten | 8% | 12% | 15% |
| Value a share | $66.20 | $104 | $132 |
- Price
- $151
- Priced on
- 16 Nov
- Price as a share of the base value
- 145%
- Starting growth the price pays for
- 42.6%
- Yearly return the price offers on the base case
- 6.5%
- Risk check: valued at 10%, the rate for a cyclical or indebted business
- $78.82
Where each figure comes from
| Figure | Source | Where exactly |
|---|---|---|
| Sales, the last full year | Filed report | Filed report (8-K) for the period to 30 Sep 2026, filed 16 Nov 2026; the full year. |
| Operating margin today | Filed report | Filed report (8-K) for the period to 30 Sep 2026, filed 16 Nov 2026; the full year. |
| Tax rate | Filed report | Quarterly report (10-Q) for the period to 30 Jun 2026, filed 4 Aug 2026; the four quarters to that date. |
| Sales per dollar of new capital | Filed report | Annual report (10-K) for the period to 30 Sep 2025, filed 19 Nov 2025: the year's sales over its operating capital, held to between 0.5 and 6. |
| Shares | Filed report | Filed report (8-K) for the period to 30 Sep 2026, filed 16 Nov 2026; the diluted share count. |
| Cash and investments | Filed report | Filed report (8-K) for the period to 30 Sep 2026, filed 16 Nov 2026; the balance sheet on that date. |
| Debt | Filed report | Quarterly report (10-Q) for the period to 30 Jun 2026, filed 4 Aug 2026; the balance sheet on that date. |
| Sales growth, years 1 to 3 | Analysts' forecasts | FMP's consensus for the years to 30 Sep 2027, 30 Sep 2028 and 30 Sep 2029: the average of 1 to 4 analysts' revenue estimates, 17.7%, 16.3%, 14.2%. FMP publishes how many analysts, not who they are. |
| Normal operating margin | Filed report | The average operating margin of its last five filed years, since the business sits at a peak or a trough of its cycle. |
| Return on new capital after year ten | Our method's rule | Set by our reading of the moat: the 8% rate with none, 12% with an average one, 15% with a strong one; the bear case earns the rate. |
| The bear and bull cases | Our method's rule | Our method's spread: the bear case takes half the growth and a fifth off the margin, the bull a quarter more growth and a tenth more margin. |
| Price | Market price | FMP's closing price on 16 Nov 2026. |
What each case rests on
Bear caseGrowth runs at half the analysts' path, 9%, 8% and 7%, the margin settles a fifth lower at 7.7%, and new capital earns only the 8% rate: the downturn test.
Base caseRevenue grows 18%, 16% and 14% over three years on fiscal 2026's $1.26B, the analysts' path (C37), then fades toward 4%, closing 30% of the gap each year; the margin settles at its five-year average of 9.6%, not today's cycle peak, though the $2.7B backlog (C39) and the CFO's statement (C40) hold it high in the early years.
Bull caseGrowth runs a quarter above the analysts' path, 22%, 20% and 18%, the margin reaches 10.5%, and new capital earns 15%.
What moves the base value
| Lower | Higher | |
|---|---|---|
| Growth in years 1 to 3, a quarter lower or higher | $93.83 | $116 |
| The normal margin, 15% lower or higher | $93.18 | $115 |
| Capital per dollar of growth, a quarter more or less | $102 | $105 |
| Return on new capital after year ten, at the rate or one step up | $89.18 | $110 |
| The rate, a point higher or lower | $88.95 | $129 |
| Long-run growth a point lower | $96.87 | - |
Value a share as growth and margin change
| Normal margin ↓ · growth → | 50% | 75% | 100% | 125% | 150% |
|---|---|---|---|---|---|
| 7.7% | $74.29 | $81.43 | $89.54 | $98.73 | $109 |
| 8.6% | $79.56 | $87.63 | $96.81 | $107 | $119 |
| 9.6% | $84.82 | $93.83 | $104 | $116 | $129 |
| 10.6% | $90.08 | $100 | $111 | $124 | $139 |
| 11.5% | $95.34 | $106 | $119 | $133 | $149 |
Growth is shown as a share of the base case's. Green: the price is at or under 80% of that value. Red: at or over 120%.
How we read the multiple
Debt included, buyers pay about 26 times Powell's yearly operating profit, the profit from its business before interest and tax. Its three listed rivals' middle is 32. Powell also earns the most on the money invested in it: 22.6% against their 9.6%.
The catch is growth. At 7.0% a year it is the slowest of the four, and the finance chief has said it probably will not reach double digits at the current pace.
Against its own history. Far dearer than its own past, but that past includes years it barely made money, so the old normal is a poor guide.
The evidence under this - 5 claims
- Management capping its own growth expectation is unusual and is evidence of candour rather than weakness, and the same executive framed the 9% print as one he was 'very happy with'. But it is also the single most important forward statement in this file: a company whose order book tripled telling the market not to expect double-digit revenue growth is describing a capacity ceiling, not a demand one, and that ceiling is what the multiple has to be judged against.
- Fiscal 2026 revenue grew 13.8% and the fourth quarter 33% (C28, C39), so the hedged cap he gave in August did not hold for the year he was describing. On the Q4 call he called the quarter's sequential jump capacity coming online with 'no unusuals', and about $1.3B of backlog is scheduled for fiscal 2027 against $1.26B sold in fiscal 2026 (C08).
- 2026-11-17editedTested by the fiscal 2026 results: revenue grew 13.8% for the year and 33% in the fourth quarter, past the 'probably not double-digit' he gave; the claim stays as what was said, with the outcome beside it.
- 2026-11-17editedthe Q4 call: no pull-forward in the quarter, and $1.3B of backlog scheduled for fiscal 2027
- nVent's 46.2% revenue growth - the figure that lifts the cohort median to 15.5% and makes Powell look slowest - is substantially acquired rather than organic: nVent bought Avail Infrastructure Solutions' switchgear and enclosures businesses for approximately $1 billion in cash during 2025. Comparing Powell's organic 7% against a median inflated by an acquisition overstates the growth gap, though it does not close it, since Eaton and Hubbell grew 15.5% and 10.6% without a deal of that scale.
- Powell's frame-metric discount to the cohort widened between 24 August and 6 September - from 27.5 against 31.4 to 26.2 against 32.0 - but roughly half of the subject's move is the vendor share-count correction recorded at C22 rather than anything the market did. The August reading was overstated by about 4.6%, so the thesis was harsher on Powell's price than the filed share count supported.
- 2026-10-27editedcohort multiples are as of the 4 September pack and were not re-struck after the fall
This own-history comparison is close to meaningless as a valuation signal, and saying so is the point: the prior medians span fiscal 2021 and 2022, when Powell's operating margin was 0.2% and 1.4% (C12). A company earning a 19.7% operating margin and a 22.6% return on invested capital is not the company those multiples were struck on, so the expansion from 1.01 to 5.70 times sales measures a change in the business at least as much as a change in what buyers will pay. The cohort comparison in C13, against live peers today, is the more informative reading.
- 2026-09-26editedCounter-evidence quoted price to sales of 5.95, the August pack's figure before the vendor's share-count correction (C22); the claim itself and the 6 September pack give 5.70.
- 2026-10-27editedown-history multiples are as of the 4 September pack and were not re-struck
The value rests on the margin falling to its five-year average of 9.6%, less than half fiscal 2026's 21.1%; with a $2.7B backlog and the CFO calling the margin sustainable (C40), a higher normal would lift it sharply. At a 10% required return it is about $79.
- 2026-11-09editedgrowth fades as each year closes 30% of its gap to 4% and the analysts' margin is put on the filed basis, the owner's call of 9 November
- 2026-11-10editedre-valued on the owner's rules of 10 November: the return on new capital glides to its terminal level over years six to ten
- 2026-11-17editedRe-struck on the fiscal 2026 results: revenue of $1.26B, cash of $861M and the analysts' path from the actual year; the value moves from about $94 to about $104, and the price of $151.20 is about 145% of it.
Priced against its rivals
The competitors its own annual report names, each confirmed against the rival's filing. Measured on company value for each $1 of operating profit, cheapest first:
| Ticker | Company | company value for each $1 of operating profit |
|---|---|---|
| HUBB | Hubbell Incorporated | 23.3× |
| POWL | Powell Industries | 26.2× |
| NVT | nVent Electric | 32.0× |
| ETN | Eaton | 34.0× |
The middle of the other 3 is 32.0. Powell Industries, Inc. is 2nd cheapest of 4.
Rivals' figures come from a data provider, so read the spread of the group rather than any single pair.
Mid-pack against its listed rivals despite the best returns of the group. The discount is its own, and it is for slower growth.
Private or foreign rivals that cannot be priced: Siemens Energy, Schneider Electric, ABB and Mitsubishi Electric, Smaller regional competitors.
Where we disagree with the market
A slowing industrial that ran too far: sales grew 9% while orders tripled, and only 3 of 10 analysts say buy.
The fall removed the excess without creating a bargain. The growth ceiling management describes is real, and set by its own capacity.
The market is reading Powell against its own history, when it barely made money. Against live rivals it is mid-pack on price and earns double their returns, which is why we are not bearish.
We would be too cautious if the deliverable share of backlog recovers toward the low sixties, growth outpaces rivals again, and the later data-centre phases come to Powell.
What analysts say, and the evidence
The evidence under this - 6 claims
- The two sales closest to the fiscal Q3 print were both pre-arranged, which removes the timing inference: the chief executive's 4,500 shares at $207.01 on 2026-08-13 were sold under a Rule 10b5-1 plan he adopted on 2025-11-26, and director Richard Williams's 2,250 shares at $203.05 on 2026-08-14 under a plan adopted 2026-04-06 - both months before the convertibility disclosure of 2026-08-03. The chief executive retained 512,733 shares, so the sale was about 0.9% of his holding. Zero open-market purchases across a year remains a real absence; selling ten days after a bad call does not.
- Short interest at 8.66% of float is elevated in absolute terms but has fallen from 2,817,817 shares in late May to 2,499,783 in mid-August, so the short base was being covered into the decline rather than built. The figure is settled twice a month and is read as of 2026-08-14, not as of today.
The chief executive said on the same day's call that this order scale is not repeatable: 'Projects upwards of $400 million are not common in the pipeline other than potential future phases of this particular program.' A book-to-bill of 3.0 driven by one order above $400 million should therefore not be annualised, and the company's own release cautions that backlog 'may not be indicative of future operating results as orders may be cancelled or modified by our customers and associated backlog may not be recognized as revenue on the timeline we expect or at all'.
- nVent's 46.2% revenue growth - the figure that lifts the cohort median to 15.5% and makes Powell look slowest - is substantially acquired rather than organic: nVent bought Avail Infrastructure Solutions' switchgear and enclosures businesses for approximately $1 billion in cash during 2025. Comparing Powell's organic 7% against a median inflated by an acquisition overstates the growth gap, though it does not close it, since Eaton and Hubbell grew 15.5% and 10.6% without a deal of that scale.
- Powell's frame-metric discount to the cohort widened between 24 August and 6 September - from 27.5 against 31.4 to 26.2 against 32.0 - but roughly half of the subject's move is the vendor share-count correction recorded at C22 rather than anything the market did. The August reading was overstated by about 4.6%, so the thesis was harsher on Powell's price than the filed share count supported.
- 2026-10-27editedcohort multiples are as of the 4 September pack and were not re-struck after the fall
The share fell again, from 54% to about 48%, because the orders won were large and slow: the $250M LNG order runs about three years. In dollars, though, $1.3 billion scheduled within a year is about 60% more than the roughly $800 million a year earlier, and about what fiscal 2026 sold in total.
- 2026-11-17editedIts refresh moves to the fourth-quarter call, which FMP did not yet hold on 17 November; the results release does not restate it.
- 2026-11-17editedthe fiscal 2026 10-K and the Q4 call: about $1.3B of the $2.7B backlog converts within twelve months, roughly half, down from 54% at June
- The future phases are unawarded and the chief executive qualified them twice - 'assuming we're successful' and 'nothing in the near term'. A two-and-a-half-year burn on a single order also means most of its revenue lands beyond this thesis's horizon, so the largest order in the company's history contributes to the backlog figure long before it contributes to earnings.
- The Q4 call did not mention the programme's later phases; it named a separate $85M data-centre order, and the chief executive said data-centre designs change quantities mid-programme, which Powell has reallocated rather than seen cancelled.
- 2026-11-17editedIts refresh moves to the fourth-quarter call, which FMP did not yet hold on 17 November; the results release does not restate it.
- 2026-11-17editedchecked against the Q4 call: the later phases were not mentioned; refresh moved to the Q1 fiscal 2027 call
What could go wrong, and how we would know
The risks
- Not enough skilled workers. The chief executive expects craft labour to be a challenge in 2027 and 2028, which would delay deliveries.
- Margins have stopped rising. Gross margin was lower than a year earlier in each of the last two quarters, as one-off gains from closing projects fade.
- Orders can be cancelled. Customers may walk away from the backlog, usually paying costs and a margin rather than the full order.
- Insiders selling. Insiders made 79 open-market sales and no purchases in the past year.
The evidence under this - 5 claims
- The leased facility does not produce anything until late in fiscal Q2 or early Q3 2027 - March to June 2027 - which is after the two prints this thesis's next test and horizon turn on. So the capacity that would lift backlog convertibility above 54% is not available during the period in which convertibility is expected to recover, and the recovery, if it comes, has to come from the existing footprint. Against that, the chief executive attributes the current throughput to running the job across at least five existing plants rather than to any single new one.
- The $70 million to $100 million greenfield figure is the alternative Powell declined, so it quantifies the capital discipline the thesis credits - but it also quantifies what a competitor willing to spend would need in order to add the capacity that constitutes Powell's moat, which is roughly a tenth of what nVent paid to buy comparable capacity outright.
- On the Q4 call the chief executive said the 335,000 square-foot Jacintoport expansion is operational and supports about $100M of yearly revenue, a further 80,000 square feet and a 275,000 square-foot lease due in fiscal Q3 2027 follow, and competition for skilled craft labour is rising but has not yet affected execution; the finance chief put fiscal 2027 capital spending at $15M to $20M.
- 2026-11-17editedthe Q4 call: capacity added and planned, labour not yet binding, fiscal 2027 capital spending
The two soft quarters were 13 and 30 basis points, inside the noise of a project business, and the fourth quarter's jump may carry project closeouts the release does not size; whether the 34.9% is a level or a lumpy quarter is the call's question. What the series no longer supports is the reading of September that the margin had stopped rising.
- 2026-11-17editedContradicted by the fourth quarter: gross margin of 34.9% against 31.4% a year earlier ended the two-quarter flattening the claim read as a stop; restated with the full year's series.
About 230 of the fourth quarter's 350 basis-point rise was closeouts, so its like-for-like margin was nearer 32.6% than 34.9%; the closeouts are non-recurring by nature, though Powell has earned them three years running. The underlying rise of about two points is pricing and volume, the part a capacity-constrained cycle supplies and a slower one takes back.
- 2026-11-17editedIts refresh moves to the fourth-quarter call, which FMP did not yet hold on 17 November; the results release does not restate it.
- 2026-11-17editedthe Q4 call sized the closeouts: about 230 basis points in the quarter, 150 in fiscal 2026, base margin near 30%
The cost-plus-reasonable-margin reimbursement materially softens this: a cancelled Powell project is not a total loss, and the company reports bookings net of cancellations rather than gross, so the historical order series already absorbs whatever cancellation has occurred. But it is why the three mega orders are recorded here as conditional rather than firm commitments. Nothing in the record quarter is a filed offtake agreement with a named counterparty; they are purchase orders in a backlog whose own governing document says customers may terminate at their discretion.
- The two sales closest to the fiscal Q3 print were both pre-arranged, which removes the timing inference: the chief executive's 4,500 shares at $207.01 on 2026-08-13 were sold under a Rule 10b5-1 plan he adopted on 2025-11-26, and director Richard Williams's 2,250 shares at $203.05 on 2026-08-14 under a plan adopted 2026-04-06 - both months before the convertibility disclosure of 2026-08-03. The chief executive retained 512,733 shares, so the sale was about 0.9% of his holding. Zero open-market purchases across a year remains a real absence; selling ten days after a bad call does not.
- Short interest at 8.66% of float is elevated in absolute terms but has fallen from 2,817,817 shares in late May to 2,499,783 in mid-August, so the short base was being covered into the decline rather than built. The figure is settled twice a month and is read as of 2026-08-14, not as of today.
What we still do not know
- Whether the later phases of the data-centre programme come to Powell. None has been awarded.
- Whether the leased plant, due in 2027, lifts how much of the backlog converts each year.
The evidence under this - 3 claims
- The future phases are unawarded and the chief executive qualified them twice - 'assuming we're successful' and 'nothing in the near term'. A two-and-a-half-year burn on a single order also means most of its revenue lands beyond this thesis's horizon, so the largest order in the company's history contributes to the backlog figure long before it contributes to earnings.
- The Q4 call did not mention the programme's later phases; it named a separate $85M data-centre order, and the chief executive said data-centre designs change quantities mid-programme, which Powell has reallocated rather than seen cancelled.
- 2026-11-17editedIts refresh moves to the fourth-quarter call, which FMP did not yet hold on 17 November; the results release does not restate it.
- 2026-11-17editedchecked against the Q4 call: the later phases were not mentioned; refresh moved to the Q1 fiscal 2027 call
- The leased facility does not produce anything until late in fiscal Q2 or early Q3 2027 - March to June 2027 - which is after the two prints this thesis's next test and horizon turn on. So the capacity that would lift backlog convertibility above 54% is not available during the period in which convertibility is expected to recover, and the recovery, if it comes, has to come from the existing footprint. Against that, the chief executive attributes the current throughput to running the job across at least five existing plants rather than to any single new one.
- The $70 million to $100 million greenfield figure is the alternative Powell declined, so it quantifies the capital discipline the thesis credits - but it also quantifies what a competitor willing to spend would need in order to add the capacity that constitutes Powell's moat, which is roughly a tenth of what nVent paid to buy comparable capacity outright.
- On the Q4 call the chief executive said the 335,000 square-foot Jacintoport expansion is operational and supports about $100M of yearly revenue, a further 80,000 square feet and a 275,000 square-foot lease due in fiscal Q3 2027 follow, and competition for skilled craft labour is rising but has not yet affected execution; the finance chief put fiscal 2027 capital spending at $15M to $20M.
- 2026-11-17editedthe Q4 call: capacity added and planned, labour not yet binding, fiscal 2027 capital spending
The share fell again, from 54% to about 48%, because the orders won were large and slow: the $250M LNG order runs about three years. In dollars, though, $1.3 billion scheduled within a year is about 60% more than the roughly $800 million a year earlier, and about what fiscal 2026 sold in total.
- 2026-11-17editedIts refresh moves to the fourth-quarter call, which FMP did not yet hold on 17 November; the results release does not restate it.
- 2026-11-17editedthe fiscal 2026 10-K and the Q4 call: about $1.3B of the $2.7B backlog converts within twelve months, roughly half, down from 54% at June
What would change our view
- Unattractive→NeutralThe price falls back within 20% of fair value
It needs:
- ○The share price falls to about $125, back within 20% of what we think the business is worth.about ≈$120.33 today, 34% below the last close
- Unattractive→AttractiveThe price falls 20% under fair value
It needs:
- ○The share price falls to about $83, 80% of what we think the business is worth.about ≈$70.72 today, 61% below the last close
- Unattractive→NeutralThe margin is not a peak
It needs all of:
- ○Gross margin holds at fiscal 2026's 31.3% or better through the next two quarters, with at least $1.3B of the backlog deliverable within a year.checked at the next results, due by 2 Feb
- ○Quarterly orders stay above $500M, so the order book is a level, not two big orders.checked at the next results, due by 2 Feb
We would also be wrong if
- Gross margin falls against the year before for three quarters in a row.
What is coming
- 17 November 2026 Q4 fiscal 2026 results and the fiscal 2026 10-K: Backlog convertibility against 54%, fourth-quarter gross margin against 31.39% a year earlier, orders against $362M, and whether the Jacintoport yard finished on time.
Every dated event ahead
- 17 November 2026 Q4 fiscal 2026 results and the fiscal 2026 10-K: Backlog convertibility against 54%, fourth-quarter gross margin against 31.39% a year earlier, orders against $362M, and whether the Jacintoport yard finished on time.
- January 2027 Proxy statement for the February 2027 annual meeting: The fiscal 2026 bonus against its EBITDA goal, whether fiscal 2027 goals are set above results already reached, and insider and Powell-holder stakes after the split.
- February 2027 Q1 fiscal 2027 results: Whether convertibility keeps recovering and overhead per sales dollar stops rising, before any new capacity is running.
- June 2027 Leased Houston facility begins manufacturing: Whether capacity arrives as promised, late in fiscal Q2 or early Q3 2027, the step that lets the $2.4B backlog convert faster.
Since we wrote this
- 17 NovEarningsSales up 33%, backlog doubled; about half ships within a yearThe September quarter beat the margin and orders the thesis needed, though the call showed part of the margin was one-off and about half the backlog ships within a year; the price sits above even our best case.
- 9 NovThesis reviewUnattractive: priced at 137% of a value near $97.37Re-valued in three stages at an 8% return, the method now drawn on every thesis: the price sits beyond the 20% margin of safety.
- 27 OctPrice moveShares fell 13% with no company news; view heldThe price claim was re-struck at $157.07. The view rests on backlog conversion, which only the 17 November results can show.
- 5 OctThesis reviewThe long case now sits under the verdictAfter the five-name pilot, the owner asked for the long case on every thesis.
- 4 OctThesis reviewMargin-promise claim carried to the November print. View heldFiscal 2026 has closed but not been reported, so the claim can only be judged on the 17 November release. Nothing new exists to move the view before then.
- 4 OctThesis reviewOwner's checklist: revenue streams, cost of growth, management, catalystsThe owner's checklist found the method silent on who runs the company, what growth costs, where the money comes from and what is dated ahead; this pass fills those four blocks from the proxy and filings.
- 26 SepThesis reviewValuation text brought to 26.2 times profit; view heldFour passages still quoted 27.5 times operating profit against a peer median of 31.4, from before a share-count correction. The September figures, 26.2 against 32.0, leave Powell second cheapest of four.
- 6 SepThesis reviewOrder was known at the high; margins stalled. View heldThe data-centre order was public in May, so the fall priced slower conversion. A vendor share-count error had overstated the multiples, and gross margin has stopped rising. The evidence cut both ways.
- 24 AugThesis writtenNeutral, medium convictionWritten three weeks after record orders and a third off the share price, on a call that cut how fast the backlog becomes sales.
Also checked 2 times with nothing new to act on.
Sources 25
Sources - 25
Every claim above cites one of these, or states the reasoning that derived it. The quote is frozen at the date it was read: a link can rot, and an agent fetch returns a reading of a page rather than the page. Backs counts the whole claim ledger, so it can name a claim this page does not surface.
- S01primarycompany filing2025-11-19business and product description, competition classes, customer-concentration language, the Jacintoport capacity expansion, the backlog definition and the pre-split share countbacksC01C02C03C10C12C13C14C23C24C29C30C34C35
- S02primarycompany filing2026-08-03fiscal Q3 2026 revenue, margin and earnings; new orders, book-to-bill and backlog; the three mega orders; end-market revenue movements; cash and short-term investments; and the backlog cautionbacksC04C05C06C16C18C27C28
- S03primarycompany filing2026-08-04the three-for-one stock split detail, the post-split share count, the equity roll-forward including treasury shares, the undrawn revolver and letters of credit, and the intangible asset schedulebacksC03C16C22C28C34C35C36
- S04primarytranscript2026-08-04Powell Industries fiscal Q3 2026 earnings call transcript (question section)Alpha Vantage EARNINGS_CALL_TRANSCRIPT, POWL 2026Q3the backlog convertibility figures, the growth cap, the project-closeout margin contribution, the capacity and labour commentary, the data-centre order detail and the behind-the-meter content mechanism
Of the $2.4 billion of backlog, roughly just under $1.3 billion will be convertible over the next 12 months, so roughly 54%. As we spoke last quarter, that was in the low 60s, and with this big slug of orders - the $900-plus million order bookings that we recognized this quarter - that convertibility slipped down to about 54%. [...] our book-and-burn cadence is about $75 million a quarter
backsC06C07C08C09C10C11C20C26C27 - S05primarycompany filing2026nVent Electric plc Form 10-K for fiscal year 2025 nVent Electric plca competitor's own filing pricing the same switchgear capacity at $1 billion, confirming the product overlap, and corroborating the one-year-plus design and manufacturing cycle for infrastructure orders
In 2025, we completed the acquisition of the enclosures, switchgear and bus systems businesses of Avail Infrastructure Solutions (the "Electrical Products Group") for approximately $1.0 billion in cash.
backsC15 - S06secondaryvendor data2026-08-24Portfolio-management research pack (market tier and filed statement series)content/POWL/research-pack.jsonprice and technicals, volatility bucket and beta, analyst consensus and earnings-surprise history, insider Form 4 aggregation, measured news reaction, own-history valuation series, and the filed annual and quarterly revenue and margin series from the filer's own XBRLbacksC01C12C14C17C18C22
- S07secondaryvendor data2026-08-24Portfolio-management research pack (vendor_fundamentals tier: peer_valuation cohort)content/POWL/research-pack.jsoncohort valuation and operating metrics against nVent, Eaton and Hubbell, with all three comparable and none withheld for a filed-versus-vendor margin gapbacksC13
- S08primarycompany filing2026-08-03the declared quarterly cash dividend of $0.09 per share, payable September 16, 2026backsC16
- S09primaryindustry data2026EIA - Data center server energy use grows across the commercial building stock US Energy Information Administrationthe independent national demand base for the prize block, reused from this repo's Constellation Energy and Bloom Energy theses
Across all cases, servers alone accounted for an estimated 7% of commercial sector electricity consumption in 2025. Data center server electricity use grows to 22%-33% of commercial building electricity use by 2050 across our cases.
backsC19 - S10secondaryindustry data2026independent tracking of behind-the-meter generation actually online, reused from this repo's Vistra, Constellation Energy and Bloom Energy theses
approximately 2 GW of behind-the-meter generation capacity is online across four projects, with the vast majority belonging to xAI
backsC21 - S11secondaryvendor data2026-08-24Portfolio-management filed-competitor roster (data/reference/competitors.json, POWL entry)data/reference/competitors.jsonthe recorded cohort search: the class Powell names, the candidates chased, the confirmation verdict on each, and the unlisted European and regional rivals the cohort cannot reachread, but no claim rests on it
- S12primarycompany release2025-11-18backsC12C18C25
- S13primarycompany filing2026-05-04the 4 May announcement of the $400 million-plus data-centre order as a subsequent event, the chief financial officer's forward margin statement, and fiscal Q2 2026 revenue, gross margin, orders and backlog - the document the source audit named as unread at the August reviewbacksC26C27C28
- S14primarytranscript2026-08-04Powell Industries fiscal Q3 2026 earnings call transcript (FMP, full call including prepared remarks)FMP earning-call-transcript, POWL 2026Q3a second transcription of the same call, against which every quoted passage in this ledger was re-checked; the prepared remarks, which carry the leased-facility timing, the $70-100 million greenfield alternative and the 'previously announced' description of the data-centre order; and the finding that the August page's data-centre boundary quote does not appear in the call. Same origin as S04 - one call, two vendors, not two pieces of evidence
at the compute level, where we don't compete, the 1-megawatt rack is definitely on its way and it is built around DC distribution technology. And so as that moves up the power curve, the outside of the data center will remain largely AC Energy. There's a mix of ideas to do DC. I mean a really wide-ranging mix of DC stuff that will get inside the data center. And yes, I still see an opportunity for Powell more midterm on the DC side, but we definitely are looking at it.
read, but no claim rests on it - S15primarycompany filing2026-08-17the footnotes establishing that both sales closest to the fiscal Q3 print were executed under Rule 10b5-1 plans adopted 2025-11-26 and 2026-04-06, and the shares retained after eachbacksC18
- S16primarycompany filing2026-01-06directors and executive officers with tenure, beneficial ownership as of December 19, 2025, the fiscal 2025 bonus and performance-unit metrics, targets and payouts, and the summary compensation tablebacksC29C30C31C32C33
- S17primarycompany filing2026-07-06the special retention award of 36,000 restricted stock units to the chief executive, its back-loaded vesting and the retirement-at-60 provision it overridesbacksC33
- S18primarycompany filing2026-10-04revenue, cost of sales, R&D, SG&A, stock pay, capital spending and diluted shares for FY2021 to FY2025 and the four quarters to June 2026backsC32C34C35
- S19secondaryvendor data2026-10-27the 26 October close, 252-day range, moving averages, returns and the 20-day rangebacksC17
- S20primarycompany filing2026-11-09trailing revenue, operating profit, stock pay, tax, debt, cash and the diluted share countread, but no claim rests on it
- S21secondaryvendor data2026-11-09the analysts' average revenue and operating profit for the next three fiscal years, and the closeread, but no claim rests on it
- S22primarycompany filing2026-11-16fourth-quarter and full-year fiscal 2026 revenue, gross profit, net income, orders, backlog, the two mega orders, cash and short-term investments, and the CFO's statement on fiscal 2027 margins; read through an agent fetch because this repository's EDGAR client was not available to the review, with revenue, gross profit, net income and EPS reconciled to FMP's statement rows
New orders totaled $710 million, an increase of 162%, representing a fourth-quarter book-to-bill ratio of 1.8x ... Backlog as of September 30, 2026 totaled $2.7 billion, an increase of 96%
backsC27C28C38C39C40 - S23secondaryvendor data2026-11-17the analysts' average revenue for fiscal 2027 to 2029, read before they were updated for the fourth-quarter print, and the 16 November close of $151.20backsC37C38
- S24primarytranscript2026-11-17Powell Industries fiscal Q4 2026 earnings call transcript (FMP, via scripts/transcript_fetch.py), held 17 November 2026data/cache/transcripts/POWL-2026Q4.jsonbacklog convertible within twelve months of about $1.3B of $2.7B against 60% a year earlier; project closeouts of about 230 basis points in the fourth quarter's gross margin, about 150 in fiscal 2026 and 185 in fiscal 2025, base margins exiting backlog near 30% against 28%; a three-year burn on the $250M LNG order; data-centre quantity changes reallocated with no de-book; craft-labour competition rising but not yet delaying work; capacity of about 3.2 million square feet next year and capital spending of $15M to $20M; book-and-ship of $75M to $80M a quarter; five analysts asked questions
So at the end of 4Q, of that $2.7 billion of backlog, we see $1.3 billion of it scheduled to convert in '27. The remainder would convert thereafter. So roughly 50%.
backsC08C09C40 - S25primarycompany filing2026-11-17backlog and the part expected to be recognised within twelve months; no customer above 10% of revenue in fiscal 2026 or 2025
As of September 30, 2026, we had backlog of $ 2.7 billion, of which approximately $ 1.3 billion is expected to be recognized as revenue within the next twelve months .
backsC08