Excelerate Energy
This is the archived full research. Read the story
Excelerate rents out ships that turn imported LNG back into gas at a country's port, and sells some of those countries the gas as well.
The scores
Growth3/4 ↑
Adjusted EBITDA rose 29% in 2025 and is guided up about 12% in 2026, but most of 2025's rise was Jamaica, bought.
Business quality3/4 →
Scarce ships keep every owned FSRU contracted and renewals rising, but the scarcity is a cycle that newbuilds, conversions and onshore terminals can end.
Financial position3/4 ↓
Net debt near $898M, 1.9 times EBITDA, with notes due 2030 and an undrawn $500M line; growth spending exceeds free cash.
Execution record3/4 →
Jamaica was integrated and Acadia delivered early, but Iraq slipped a year and 2026 guidance was cut once, both blamed on the war.
Per share capture3/4 →
Shares steady and buybacks cover stock pay, but Class A owns 28% and the tax agreement favours the controlling holder.
Potential3/4 →
A bounded upside that is mostly signed: Iraq, Colombia and Bangladesh have contracts; the converted ship and new markets do not.
Risk profile2/4 ↓
Iraq's start depends on work inside a Gulf at war, Qatar's supply is suspended, and customers are emerging-market states.
Valuation3/4 →
About 9.9 times operating profit before depreciation, 83% of a three-stage value near $44.17 at an 8% return: fair, inside the 20% margin.
Evidence quality3/4 →
Contracts, results and debt are filed and the scarcity is measured by the GECF; ship rates and Iraq's return are management's word.
The Verdict
We rate Excelerate Neutral. It owns the largest fleet of floating gas import terminals, and ships are scarce, so every one is rented out on long contracts and renewals pay more: the business is solid. The price sits just short of our margin of safety, but it already counts on a new terminal in Iraq starting in 2027 and adding about a fifth to earnings. That terminal sits inside the Persian Gulf, where this year's war has already pushed it back a year. The growth the price needs depends on a war, so we hold Neutral.
The long caseAs new LNG floods the market, countries that need gas fast rent floating terminals, few are free, and Excelerate owns the most and charges more each time one renews.
How we weighed it
The price against our value
Cuts both ways
Price at 83% of our value
The price sits just short of the margin of safety, and already counts on the Iraq terminal.
The business
In its favour
Solid
The largest fleet of floating gas import terminals, all rented out on long contracts.
Growth against what the price assumes
Cuts both ways
The growth the price needs comes from Iraq and Colombia, which have not arrived yet.
What could go wrong
Against it
Iraq could slip again, Qatar's supply is cut, the ship shortage could end and a few emerging-market buyers dominate.
Against competitors
Cuts both ways
There is no listed rival with a comparable fleet.
How its group is behaving
Cuts both ways
Gas names move together with the gas price; its contracts make it steadier than producers.
The latest news and report
In its favour
The latest report passed all three parts of our test.
The evidence under this - 7 claims
FSRU utilisation fell to 35% in 2025 (C25), so ships sit idle at some ports, and Excelerate itself is converting a carrier, as rivals can.
Per-ship rates are not disclosed, so the uplift cannot be checked; the GECF counts FSRU utilisation falling to 35% in 2025 (C25).
The pack's vendor market value of $4.06B counts issued rather than outstanding Class A shares and misses the Class B, so vendor multiples do not match this arithmetic.
- 2026-11-04editedre-struck at the 4 November close and on Q3 2026 results
Part of the 5x return is gas supply margin, which depends on cargoes reaching a Gulf port; management has not split it between terminal, ship and supply.
The start was pushed from 2026 into 2027 in May 2026 (C10), and the site lies inside the Gulf behind the strait the conflict closed.
- 2026-11-05editedQ3 call read: mechanical completion expected April 2027; jetty reinforcement is the largest remaining scope; about $100M of yearly EBITDA at minimum volumes.
The 10-Q says the timing of the end of force majeure cannot be known; Qatar's damaged trains may take up to five years to repair (C27).
The company
A country that wants to import liquefied natural gas needs a terminal to store it and warm it back into gas. Building one on land costs over $1B and takes four to seven years.
Excelerate rents out a ship that does the same job: it moors at the port, takes LNG from visiting tankers and pipes gas ashore. It runs 12 of them, the newest delivered in April 2026, for customers from Argentina and Brazil to Bangladesh, Germany and the UAE.
The evidence under this - 4 claims
How it makes money
A dollar arrives in two ways. Customers pay a fixed daily rent for each ship, rising with inflation, and bear most of its running costs: $596.6M in 2025.
Excelerate also buys LNG and resells it at a small markup, to Bangladesh under a 15-year contract and in Jamaica and Brazil. That brought in $631.6M in 2025, but $537.8M of it went on buying the gas. The rent is where the profit is.
The evidence under this - 4 claims
Most of the $17.3B is LNG resold at cost plus a margin, priced on futures, so it overstates contracted profit; terminal contracts carry early termination rights with fees.
Where the money comes from, stream by stream
| Stream | Share of sales (FY 2025) | How it earns it |
|---|---|---|
| Terminal services | 48.6% | Charters of FSRUs and Jamaica's terminals at fixed daily rates, with operating costs largely passed to customers. |
| LNG, gas and power | 51.4% | LNG and gas resold back to back to Petrobangla, in Jamaica and Brazil, and power and steam from Jamaica's plant. |
Who runs it
Steven Kobos, once the company's lawyer, has run the business since 2018. George Kaiser's holding company controls 71.9% of the votes, so outside shareholders have little say; directors and officers own 2.34% of the listed shares.
The bonus pays mostly on earnings and new business, and from 2026 long-term awards pay on three-year earnings growth. No insider bought shares on the market in the past year; one sold 6,000.
The evidence under this - 4 claims
Why it wins, and who could beat it
Why customers come back
The advantage is that the ships are scarce. Most of the world's 50 are rented out through 2030, a new one takes about four years to build and a conversion about two. A country that needs gas soon has to rent a ship that already exists.
That shows in the prices. Every ship Excelerate owns is under contract, and management says the Express's new seven-year deal in Colombia pays about 35% more, the fifth renewal at better terms in four and a half years.
The evidence under this - 5 claims
FSRU utilisation fell to 35% in 2025 (C25), so ships sit idle at some ports, and Excelerate itself is converting a carrier, as rivals can.
Per-ship rates are not disclosed, so the uplift cannot be checked; the GECF counts FSRU utilisation falling to 35% in 2025 (C25).
The threat
Other owners rent out the same ships: Höegh Evi, a private Norwegian owner, has them in Germany, Australia, Colombia and Brazil, and Energos owns the ships New Fortress Energy uses. Rivals can also convert old tankers.
The slow threat is the customer building its own terminal on land and handing the ship back when the charter ends.
The evidence under this - 4 claims
The rivals: NFE, and 4 more that are private, in-house or listed abroad.
Who else does this, rival by rival
| Ticker | Rival | Where it competes | How far along | Priced against it |
|---|---|---|---|---|
| Private | Höegh EviPriced against it: Private | Terminal services | On sale | Private |
| Private | Energos InfrastructurePriced against it: Private | Terminal services | On sale | Private |
| NFE | New Fortress EnergyPriced against it: Different product | LNG, gas and power | On sale | Different product |
| In-house | Onshore import terminals built by buyersPriced against it: In-house | Terminal services | On sale | In-house |
| Mitsui O.S.K. LinesPriced against it: One segment only | - | On sale | One segment only |
How big it could get
How big this could get
The world is adding 235 million tonnes a year of LNG supply from 2026 to 2030, more than 40% on top of today's. If floating terminals keep their fifth of import capacity, that needs about 12 more of them.
Excelerate already runs about a quarter of the fleet. But the existing ships worked at only 35% of capacity in 2025, so part of the new supply can flow through them first.
The evidence under this - 5 claims
Forecast capacity has slipped before, and the Gulf war has delayed Qatar's own expansion (C27).
Utilisation is only 35% (C25), so existing ships could take much of the new supply before any new one is needed, and large buyers build onshore.
Who has signed
Bangladesh's Petrobangla buys LNG under a 15-year contract to 2040, though Qatar's supply behind it is suspended. Iraq signed five years of terminal and gas at a minimum flow. A Colombian port signed seven years for the Express, and Jordan nine months for the newest ship.
The evidence under this - 5 claims
The start was pushed from 2026 into 2027 in May 2026 (C10), and the site lies inside the Gulf behind the strait the conflict closed.
- 2026-11-05editedQ3 call read: mechanical completion expected April 2027; jetty reinforcement is the largest remaining scope; about $100M of yearly EBITDA at minimum volumes.
The 10-Q says the timing of the end of force majeure cannot be known; Qatar's damaged trains may take up to five years to repair (C27).
The results
The numbers
Sales grew 16% over the twelve months to Sep 2026, slower than the 44% in the year to Dec 2025.
Operating margin is 24%, up from 18% in the year to Dec 2023.
Yearly sales growth has ranged from −53% to +178% over the last 5 years, with sales falling in 2 of them.
Each dollar put into the business earns 8.8% a year after tax, about where it was (9.2%) in the year to Dec 2021.
It turned 0.8% of sales into free cash, $11.7M over the last twelve months, after spending 25% of sales on buildings and equipment.
It owes $565M more than the cash it holds, about 1.6 years of the cash its operations bring in.
The share count rose 23% in 3.8 years, and pay in shares costs 1.0% of sales.
All the numbers
Filed figures from the company's 10-K and 10-Q, read 2026-11-09. Fiscal years end in December.
| Dec 2021 | Dec 2022 | Dec 2023 | Dec 2024 | Dec 2025 | 12 mo to Sep 2026 | |
|---|---|---|---|---|---|---|
| Size and growth | ||||||
| Sales | $889M | $2.47B | $1.16B | $851M | $1.23B | $1.38B |
| Sales growth | +106% | +178% | −53% | −27% | +44% | +16% |
| Profit | ||||||
| Operating margin | 16% | 7.5% | 18% | 25% | 22% | 24% |
| What growth costs, per sales dollar | ||||||
| General and admin | 5.3% | 2.7% | 7.5% | 11% | 7.7% | 7.7% |
| Pay in shares | - | 0.0% | 0.3% | 0.9% | 1.0% | 1.0% |
| Capital spending | 4.1% | 4.8% | 27% | 13% | 13% | 25% |
| Cash | ||||||
| Cash from operations | $142M | $225M | $232M | $244M | $461M | $359M |
| Free cash flow | $106M | $106M | −$80.8M | $131M | $298M | $11.7M |
| Balance sheet | ||||||
| Cash and short-term investments | $72.8M | $517M | $556M | $538M | $538M | $357M |
| Debt | $233M | $214M | $376M | $334M | $936M | $922M |
| Net cash | −$161M | $302M | $180M | $204M | −$398M | −$565M |
| Returns and shares | ||||||
| Return on capital | 9.2% | 8.8% | 8.1% | 8.3% | 8.5% | 8.8% |
| Shares (diluted) | 0 | 26.3M | 108M | 25.8M | 30.6M | 32.2M |
What growth costs
Growth has widened the margin. Operating income nearly doubled from 2021 to 2025 while overheads rose from $47M to $95M. What growth costs now is ships and terminals: $369M of capital spending in the year to June 2026, against about $500M of yearly earnings.
The evidence under this - 2 claims
The last report (4 Nov)
Quarter ended September 2026, filed figures.
The September 2026 quarter was the company's best. Adjusted earnings before interest, tax and depreciation were $133.5M against $129.3M a year earlier, and net income $60.0M. Management narrowed its 2026 forecast to $495M to $515M.
Iraq's terminal is still due in the second quarter of 2027; on the call management said building finishes in April. The Bahamas gas deal adds only about $6M of earnings in 2027, and a Brazilian charter was extended to 2038.
What it did to the thesisIt passed all three parts of our test. That supports the case, but the price already pays for Iraq, so Neutral holds.
The quarter in detail
Sales growth from the previous quarter, filed figures.
Earnings per share $0.44 against $0.42 expected.
The evidence under this - 5 claims
- 2026-11-04editedQ3 2026 release narrowed 2026 guidance to $495M to $515M
The start was pushed from 2026 into 2027 in May 2026 (C10), and the site lies inside the Gulf behind the strait the conflict closed.
- 2026-11-05editedQ3 call read: mechanical completion expected April 2027; jetty reinforcement is the largest remaining scope; about $100M of yearly EBITDA at minimum volumes.
What management did with the money
Management bought Jamaica's terminals and power plant from New Fortress Energy in 2025, and is spending $520M to $550M on Iraq for about 5 times its yearly earnings. It also raises the dividend each year and buys back shares.
Insiders in 2026Q1: 15 purchases and 17 sales, from their Form 4 filings.
The evidence under this - 4 claims
The cost range rose between the November 2025 and February 2026 calls, and the start has already slipped once.
The price, and where we disagree
In short. Fair. The price is about 83% of what we think the business is worth, at an 8% yearly return.
War in the Persian Gulf closed the Strait of Hormuz in March 2026, cutting off a fifth of the world's LNG. Qatar suspended the gas Excelerate resells to Bangladesh, and the shares fell about a quarter in a month. They have recovered little since.
The September results and the 5 November call are in: Iraq's building finishes in April 2027. The next test is the 2027 guide in February.
The evidence under this - 5 claims
The 10-Q says the timing of the end of force majeure cannot be known; Qatar's damaged trains may take up to five years to repair (C27).
The start was pushed from 2026 into 2027 in May 2026 (C10), and the site lies inside the Gulf behind the strait the conflict closed.
- 2026-11-05editedQ3 call read: mechanical completion expected April 2027; jetty reinforcement is the largest remaining scope; about $100M of yearly EBITDA at minimum volumes.
The Exquisite dry dock moved into 2027 and Acadia earns from July, so the second half is not a clean comparison.
- 2026-11-04editedQ3 2026 adjusted EBITDA of $133.5M met the bar
- 2026-11-05editedQ3 call read: no 2027 guide until February; management restated the building blocks adding $250M-$300M of EBITDA by 2029.
How we value it
- Method
- Cash the business will produce, in three stages
- Required return
- 8%
- Long-run growth
- 4%
- Moat
- An average moat
| Bear | Base | Bull | |
|---|---|---|---|
| Sales growth, years 1 to 3 | 17.3%, 11.4%, -3.5% | 34.6%, 22.8%, -2.3% | 43.2%, 28.5%, -1.1% |
| Normal operating margin | 19% | 23.8% | 26.2% |
| Return on new capital after year ten | 8% | 12% | 15% |
| Value a share | $21.97 | $44.17 | $60.75 |
- Price
- $36.81
- Priced on
- 6 Nov
- Price as a share of the base value
- 83%
- Starting growth the price pays for
- 2.4%
- Yearly return the price offers on the base case
- 8.6%
- Risk check: valued at 10%, the rate for a cyclical or indebted business
- $26.08
Where each figure comes from
| Figure | Source | Where exactly |
|---|---|---|
| Sales, the last twelve months | Filed report | Quarterly report (10-Q) for the period to 30 Sep 2026, filed 5 Nov 2026; the four quarters to that date. |
| Operating margin today | Filed report | Quarterly report (10-Q) for the period to 30 Sep 2026, filed 5 Nov 2026; the four quarters to that date. |
| Tax rate | Filed report | Quarterly report (10-Q) for the period to 30 Sep 2026, filed 5 Nov 2026; the four quarters to that date. |
| Sales per dollar of new capital | Filed report | Annual report (10-K) for the period to 31 Dec 2025, filed 27 Feb 2026: the year's sales over its operating capital. |
| Shares | Filed report | Read by hand from the filed statements; the period it was read from was not recorded. |
| Cash and investments | Filed report | Quarterly report (10-Q) for the period to 30 Sep 2026, filed 5 Nov 2026; the balance sheet on that date. |
| Debt | Filed report | Quarterly report (10-Q) for the period to 30 Sep 2026, filed 5 Nov 2026; the balance sheet on that date. |
| Sales growth, years 1 to 3 | Analysts' forecasts | FMP's consensus for the years to 31 Dec 2026, 31 Dec 2027 and 31 Dec 2028, as it stood when the value was struck on 10 Nov 2026: the average of 3 to 7 analysts' revenue estimates, 34.6%, 22.8%, -2.3%. FMP publishes how many analysts, not who they are. |
| Normal operating margin | Analysts' forecasts | FMP's consensus operating margin for the year to 31 Dec 2028, as it stood when the value was struck on 10 Nov 2026, the average of 7 analysts' estimates, less stock pay: 23.8% in the base case. FMP publishes how many analysts, not who they are. |
| Return on new capital after year ten | Our method's rule | Set by our reading of the moat: the 8% rate with none, 12% with an average one, 15% with a strong one; the bear case earns the rate. |
| The bear and bull cases | Our method's rule | Our method's spread: the bear case takes half the growth and a fifth off the margin, the bull a quarter more growth and a tenth more margin. |
| Price | Market price | FMP's closing price on 6 Nov 2026. |
What each case rests on
Bear caseGrowth runs at half the analysts' path, 17%, 11% and -4%, the margin settles a fifth lower at 19.0%, and new capital earns only the 8% rate: the downturn test.
Base caseRevenue grows 35%, 23% and -2% over three years, the analysts' path (C39), then fades toward 4%, closing 30% of the gap each year; the margin moves to 23.8%, the analysts' year-three figure after stock pay.
Bull caseGrowth runs a quarter above the analysts' path, 43%, 28% and -1%, the margin reaches 26.2%, and new capital earns 15%.
What moves the base value
| Lower | Higher | |
|---|---|---|
| Growth in years 1 to 3, a quarter lower or higher | $41.59 | $46.77 |
| The normal margin, 15% lower or higher | $35.81 | $52.53 |
| Capital per dollar of growth, a quarter more or less | $39.85 | $46.76 |
| Return on new capital after year ten, at the rate or one step up | $34.03 | $48.23 |
| The rate, a point higher or lower | $33.32 | $62.21 |
| Long-run growth a point lower | $39.18 | - |
Value a share as growth and margin change
| Normal margin ↓ · growth → | 50% | 75% | 100% | 125% | 150% |
|---|---|---|---|---|---|
| 19% | $29.88 | $31.49 | $33.03 | $34.56 | $36.07 |
| 21.4% | $34.42 | $36.54 | $38.60 | $40.66 | $42.73 |
| 23.8% | $38.97 | $41.59 | $44.17 | $46.77 | $49.39 |
| 26.2% | $43.51 | $46.64 | $49.74 | $52.88 | $56.05 |
| 28.6% | $48.05 | $51.69 | $55.31 | $58.99 | $62.71 |
Growth is shown as a share of the base case's. Green: the price is at or under 80% of that value. Red: at or over 120%.
How we read the multiple
A buyer pays for the current fleet plus the new contracts arriving on time.
1. The shares, Kaiser's included, are worth about $3.9B; with about $898M of net debt the business is valued at about $4.8B. 2. It earned $484.1M before interest, tax and depreciation over the past year. 3. So the business costs about 10 times those earnings. 4. Iraq would add about a fifth to them once running.
If Iraq slips again, the price has paid for earnings that are not there.
Against its own history. Buyers pay a little more for each dollar of earnings than the company's usual, for growth from Iraq and Colombia that has not arrived yet.
The evidence under this - 4 claims
The pack's vendor market value of $4.06B counts issued rather than outstanding Class A shares and misses the Class B, so vendor multiples do not match this arithmetic.
- 2026-11-04editedre-struck at the 4 November close and on Q3 2026 results
Part of the 5x return is gas supply margin, which depends on cargoes reaching a Gulf port; management has not split it between terminal, ship and supply.
Interest will rise with the larger debt, Class B distributions take most of that cash before Class A sees it, and growth capital of $380M to $400M uses all of it in 2026.
- 2026-11-04editedQ3 2026 release narrowed 2026 guidance to $495M to $515M
Priced against its rivals
None of the listed rivals above sells the same thing to the same buyers as a large part of what it does. A price comparison needs at least two, so the price is judged against its own history instead.
Also checked and set aside: Golar LNG Limited (a substitute, not the same product).
Where we disagree with the market
A contracted gas terminal landlord with visible growth from Iraq and Colombia; nine of 13 analysts rate it a buy.
The rent is real and the ships scarce, but the growth the price pays for sits in Iraq, inside the war zone.
Analysts count Iraq's earnings in 2027 and see a contracted landlord growing steadily. The filings show that start has already moved once, the gas from Qatar is suspended and this year's growth spending uses all the cash.
Against us: the contracts held through the war, guidance was raised again in August, and the ships are scarce enough that every one is working.
What analysts say, and the evidence
The evidence under this - 6 claims
The pack's vendor market value of $4.06B counts issued rather than outstanding Class A shares and misses the Class B, so vendor multiples do not match this arithmetic.
- 2026-11-04editedre-struck at the 4 November close and on Q3 2026 results
The start was pushed from 2026 into 2027 in May 2026 (C10), and the site lies inside the Gulf behind the strait the conflict closed.
- 2026-11-05editedQ3 call read: mechanical completion expected April 2027; jetty reinforcement is the largest remaining scope; about $100M of yearly EBITDA at minimum volumes.
The cost range rose between the November 2025 and February 2026 calls, and the start has already slipped once.
The 10-Q says the timing of the end of force majeure cannot be known; Qatar's damaged trains may take up to five years to repair (C27).
- 2026-11-04editedQ3 2026 release narrowed 2026 guidance to $495M to $515M
What could go wrong, and how we would know
The risks
- Iraq slips again The terminal sits inside the Gulf; another delay leaves up to $550M spent and earning nothing, with debt near 2 times earnings.
- Qatar's gas stays cut The Bangladesh contract depends on Qatar's supply, now suspended; Qatar's damaged plants may take up to five years to repair.
- The ship shortage ends Conversions, new ships and land terminals could leave a ship without a renter when its charter ends.
- Customers in emerging markets Three customers took 40% of 2025 revenue, mostly state buyers in emerging markets, which can be slow to pay.
- Kaiser controls the votes Kaiser's company holds 71.9% of the votes and takes most of the cash paid out, through its own shares and a tax agreement.
The evidence under this - 7 claims
The start was pushed from 2026 into 2027 in May 2026 (C10), and the site lies inside the Gulf behind the strait the conflict closed.
- 2026-11-05editedQ3 call read: mechanical completion expected April 2027; jetty reinforcement is the largest remaining scope; about $100M of yearly EBITDA at minimum volumes.
The cost range rose between the November 2025 and February 2026 calls, and the start has already slipped once.
The 10-Q says the timing of the end of force majeure cannot be known; Qatar's damaged trains may take up to five years to repair (C27).
FSRU utilisation fell to 35% in 2025 (C25), so ships sit idle at some ports, and Excelerate itself is converting a carrier, as rivals can.
What we still do not know
- What each ship earns a day and when each charter ends; the company gives only totals.
- How many new floating terminals are on order or being converted for delivery by 2030.
- How much of Iraq's return is the terminal and how much the gas sold through it.
The evidence under this - 3 claims
Part of the 5x return is gas supply margin, which depends on cargoes reaching a Gulf port; management has not split it between terminal, ship and supply.
What would change our view
- Neutral→AttractiveThe price falls 20% under fair value
It needs:
- ○The share price falls to about $35.34, 80% of what we think the business is worth.about ≈$35.69 today, -3% below the last close
- Neutral→UnattractiveThe price runs 20% above fair value
It needs:
- ○The share price rises to about $53.00, 20% above what we think the business is worth.about ≈$50.94 today, 47% above the last close
- Neutral→AttractiveIraq starts and 2027 is guided higher
It needs all of:
- ○Iraq's terminal starts working by 30 June 2027.watched as it happens
- ○Management guides 2027 earnings before interest, tax and depreciation at $600M or more.checked at the next results, due by 26 Feb
- Neutral→UnattractiveThe growth or the scarcity fails
It needs any of:
- ○Iraq is suspended, or its start moves into 2028.watched as it happens
- ○A ship Excelerate owns ends a charter with no new renter.watched as it happens
We would also be wrong if
- Net debt rises above 3 times yearly earnings.
- Petrobangla stops taking or paying for cargoes after Qatar's supply returns.
What is coming
- 4 November 2026 Q3 2026 results: Whether 2026 guidance and Iraq's Q2 2027 start hold, and whether the second half earns about $130M a quarter.
Every dated event ahead
- 4 November 2026 Q3 2026 results: Whether 2026 guidance and Iraq's Q2 2027 start hold, and whether the second half earns about $130M a quarter.
- 31 March 2027 Express starts in Colombia: Whether the first recontract of 2027 earns the higher rate on time.
- 30 June 2027 Iraq terminal starts: Whether the main growth project works inside the Gulf on time and cost.
Since we wrote this
- 9 NovThesis reviewStill Neutral: priced at 83% of a value near $44.25Re-valued in three stages at an 8% return, the method now drawn on every thesis: the price sits inside the 20% margin of safety.
- 5 NovEarningsCall: Iraq builds finish April; Bahamas adds about $6M in 2027Management confirmed Iraq's date and sized the Bahamas deal small. The price already pays for Iraq, so Neutral holds until February's guide.
- 4 NovEarningsEarnings beat last year's and Iraq held its dateAll three parts of the test passed, but the price already pays for Iraq at about 9.8 times, so Neutral holds.
- 7 OctThesis writtenNeutral, medium convictionWritten a month before Q3 results, after the shares fell a quarter in March on the Gulf war and recovered little.
Also checked 1 time with nothing new to act on.
Sources 20
Sources - 20
Every claim above cites one of these, or states the reasoning that derived it. The quote is frozen at the date it was read: a link can rot, and an agent fetch returns a reading of a page rather than the page. Backs counts the whole claim ledger, so it can name a claim this page does not surface.
- S01primarycompany filing2026-02-27the fleet, contract terms, customers and concentration, the Petrobangla and Iraq agreements, competition classes, control, debt and the FY2025 statementsbacksC01C03C05C06C07C09C18C30C31C34C36
- S02primarycompany filing2026-08-06remaining performance obligations, the share count, the balance sheet and debt, the Jordan charter and the Qatar force majeurebacksC02C04C05C08C15C16C17C24
- S03primarycompany release2026-08-05Q2 2026 results, adjusted EBITDA, the Express charter, the carrier purchase, Iraq's timing, revised guidance and cash flowsbacksC02C04C09C11C12C14C15C16C24C36C37
- S04primarytranscript2026-08-06Excelerate Energy Q2 2026 earnings call transcript (FMP), held 6 August 2026the Express uplift, the five recontracts, net debt and leverage
The new agreement is expected to increase the Express' annual EBITDA contribution by about 35% compared to its current contract.
backsC13C30 - S05primarycompany release2026-02-25FY2025 and quarterly adjusted EBITDA and the first 2026 guidancebacksC03C14C24C37
- S06primarytranscript2026-02-26Excelerate Energy Q4 2025 earnings call transcript (FMP), held 26 February 2026Iraq's cost and build multiple, the dividend target, the buyback and leverage at year end
The Iraq project is expected to achieve an EBITDA build multiple of approximately 5x.
backsC10C11C35 - S07primarytranscript2026-05-07Excelerate Energy Q1 2026 earnings call transcript (FMP), held 7 May 2026the Qatar force majeure and its cost, Iraq's delay into 2027 and the guidance cut
we expect the financial impact to be approximately $1 million per month while the Strait of Hormuz remains closed
backsC07C08C10C14 - S08primarycompany filing2026-04-16voting control, insider holdings, the officers and their tenure, 2025 pay and the incentive designbacksC18C19C20
- S09primarycompany filing2026-10-06the one open-market sale and its plan flagbacksC21
- S10primaryvendor data2026-10-06Research pack for EE (FMP market tier, FINRA short interest), fetched 7 October 2026the 6 October close, returns and the price move split, the range, analyst ratings and estimates, short interest and the insider seriesbacksC21C22C23C24
- S11primaryindustry data2026-02-23the FSRU count and capacity, share of regasification, utilisation, build times, costs and new liquefaction to 2030
Most of the 50 operational units are locked into long-term charter agreements through 2030, leaving a negligible pool of vessels for prompt redeployment.
backsC25C26C28C29C30 - S12primarygovernment data2026-09-01US LNG exports in the first half of 2026 and the Hormuz disruption
In March, disruptions to shipments of LNG through of the Strait of Hormuz cut off 20% of global LNG supplies, mostly from Qatar.
backsC27 - S13primarygovernment data2026-04-16the damage to Qatar's export capacity and the repair time
Qatar also sustained damage to 17% of its export capacity after a March 18 attack on the Ras Laffan LNG export facility damaged two liquefaction trains.
backsC27 - S14primarycompany filing2026-08-06Excelerate's filed statements 2020 to June 2026, from its own XBRL tags (content/EE/financials.json)revenue, operating income, overhead, stock pay, cash flow and capital spending by yearbacksC34C38
- S15primarycompany filing2026-04-13its FSRUs and their owner Energos, its going-concern doubt, and its view that FSRUs beat onshore terminals on cost and timebacksC33
- S16primaryother2026-10-07Höegh Evi's FSRUs, where they work and for whom
Höegh Esperanza Location Wilhelmshaven, Germany Customer Federal Republic of Germany Ship Type FSRU Year of build 2018
backsC32 - S17primarycompany filing2026-11-04Q3 adjusted EBITDA $133.5M, narrowed guidance, Iraq start, cash, Bahamas and Petrobras agreements
Excelerate has narrowed its full-year 2026 Adjusted EBITDA guidance range. For the full year, Adjusted EBITDA is now expected to range between $495 million and $515 million.
backsC14C24C37 - S18primarytranscript2026-11-05Excelerate Energy Q3 2026 earnings call transcript (FMP), held November 5, 2026Iraq mechanical completion April 2027, Iraq run rate about $100M at minimum take, Bahamas hub EBITDA $6M in 2027 and about $15M at full rate, Methane Patricia Camila conversion about $260M, building blocks of $250M-$300M EBITDA growth by 2029, 2027 guidance in February.
The real milestone that we're looking forward to is mechanical completion in early second quarter of 2027, so April of 2027.
backsC09C37 - S19primarycompany filing2026-11-09trailing revenue, operating profit, stock pay, tax, debt, cash and the diluted share countbacksC40
- S20secondaryvendor data2026-11-09the analysts' average revenue and operating profit for the next three fiscal years, and the closebacksC39C40